CSC425 · TU past paper
Software Project Management 2078 question paper
The complete TU 2078 exam paper for Software Project Management (CSC425), all 12 questions with solved model answers written to the mark scheme.
Tap a question to open its answer.
- Q1.NumericalEarned value analysisHideAnswer
Earned Value Analysis
- Q2.10 marksEconomic analysisHideAnswer
Differentiate between programme management and portfolio management. Define Payback period. How can it be used as an evaluation technique? What are its advantages and disadvantages?[10]
- Q3.10 marksRisk analysisHideAnswer
Suppose you have been assigned to develop online voting system. List four risks that might affect the success of the system. Rank the risks based on Risk exposure. Develop contingency plan for the highest ranked risk.[10]
- Q4.5 marksNumericalEconomic analysisHideAnswer
Calculate ROI for the following project
$$\begin{array}{|c|c|}\hline \text{Year} & \text{Project} \ \hline 0 & -50000 \ 1 & 5000 \ 2 & 5000 \ 3 & 20000 \ 4 & 40000 \ 5 & 50000 \ \hline \end{array}$$
[5]
- Q5.5 marksObjectives of activity planningHideAnswer
Differentiate between activity-based approach and hybrid-based approach for identifying activities. [5]
- Q6.5 marksSP Vs. other types of projects activities HideAnswer
Why software project management is a challenging activity? [5]
- Q7.5 marksNumericalNetwork planning modelHideAnswer
Draw precedence network diagram for the following and identify the critical path.
Activity Duration (Weeks) Precedence A 5 B 3 A C 5 A D 10 B, C [5]
Precedence Network Diagram and Critical Path
Given
Activity Duration (Weeks) Precedence A 5 None (start) B 3 A C 5 A D 10 B, C Solution
Precedence Network (Activity-on-Node)
+--------+ +-->| B: 3 |---+ | +--------+ | +--------+ | v +--------+ | A: 5 |---+ +-->| D: 10 |---> Finish +--------+ | ^ +--------+ | +--------+ | +-->| C: 5 |---+ +--------+- A has no predecessor (starts the project).
- B and C both follow A.
- D follows both B and C (both must complete before D starts).
Forward Pass (Earliest Start / Earliest Finish)
$EF = ES + \text{Duration}$
Activity ES Duration EF A 0 5 5 B 5 3 8 C 5 5 10 D $\max(8,10)=10$ 10 20 Project Duration = 20 weeks
Backward Pass (Latest Finish / Latest Start)
$LS = LF - \text{Duration}$
Activity LF Duration LS D 20 10 10 C 10 5 5 B 10 3 7 A $\min(7,5)=5$ 5 0 Total Float ($TF = LS - ES$)
Activity ES LS Total Float Critical? A 0 0 0 Yes B 5 7 2 No C 5 5 0 Yes D 10 10 0 Yes Critical Path
Path enumeration:
- $A \to B \to D = 5 + 3 + 10 = 18$ weeks
- $A \to C \to D = 5 + 5 + 10 = 20$ weeks (longest)
$$\boxed{A \rightarrow C \rightarrow D, \quad \text{Duration} = 20 \text{ weeks}}$$
- Q8.5 marksMotivationHideAnswer
Explain Maslow's hierarchy of needs. [5]
- Q9.5 marksSoftware qualityHideAnswer
Briefly explain different quality factors. [5]
- Q10.5 marksIntroductionHideAnswer
Explain the process of Software Configuration Management. [5]
- Q11.5 marksVisualizing progressHideAnswer
Differentiate between Gantt chart and slip chart. [5]
- Q12.5 marksEconomic analysisHideAnswer
Short Notes: 1. Present worth 2. PERT diagram [5]