List and explain the process of the control system.

List and explain the process of the control system. [5]

Principles of ManagementChapter 10: Control and Quality ManagementConcept, process, and types of control systems

Quick answer

Controlling is the process of evaluation and correction of performance in order to make sure that the objectives of the enterprise are accomplished through the plans formulated to attain them. It is the systematic effort through which a manager assures that actual activities match planned activities.

Control System Process

Definition


Steps/Process of the Control System

The following four steps are involved in the controlling process:


1. Setting Standards

  • The first and foremost step in the controlling process is to set the standard of performance.
  • A standard is a reference point against which actual performance is measured.
  • Usually, the planning function sets the standard of performance.
  • Standards should be stated in definite and measurable terms such as cost, income, units of service, man-hours, speed, etc.
  • Example: A sales target of Rs. 5,00,000 per month is a measurable standard.

2. Measuring the Actual Performance

  • After setting the standard, information related to individual performance and activities is gathered and evaluated.
  • Measurement can be done through:
    • Personal observation
    • Report writing
  • This step ensures that there is a factual and objective basis for comparison.
  • Example: Recording the actual monthly sales achieved by the sales team.

3. Comparing Actual Performance Against Standard

  • In this step, the actual performance of an individual or group is compared with the standard performance.
  • This comparison helps to determine any deviation that may occur between actual and standard activities.
  • Deviations can be positive (performance exceeds standard) or negative (performance falls below standard).
  • Example: If the standard was Rs. 5,00,000 but actual sales were Rs. 4,00,000, the deviation is Rs. 1,00,000 (negative).

4. Taking Corrective Actions

  • If any deviation is found between standard and actual performance after comparison, remedial measures are adopted.
  • Corrective action helps to correct the differences and put actual performance back on track toward the standard.
  • Corrective actions may involve:
    • Change in methods or procedures
    • Change in machinery
    • Improving physical working conditions
    • Changing the nature of supervision
    • Employee training and motivation
  • Example: Providing additional sales training to the team to meet the sales target.

Summary Diagram

Setting Standards --> Measuring Actual Performance
        --> Comparing with Standards --> Taking Corrective Action
                    (Feedback Loop back to Standards if needed)

Note: The controlling process is cyclical and continuous in nature. It is closely linked with planning, as plans provide the standards against which performance is measured.