2079 2

BIT253 ยท 2079 ยท 10 marks

What is project planning? Explain project initiation and planning in detail.

What is project planning? Explain project initiation and planning in detail.[10]

Systems Analysis and DesignChapter 3: Project Identification, Selection, and PlanningProject planning definition and activities

Quick answer

Project planning is the process of defining the objectives, scope, schedule, resources, costs, and activities required to complete a software project successfully. It is a managerial activity that establishes a roadmap for the entire project lifecycle, helping the project manager to estimate, schedule, and control the project from start to finish.

Project Planning: Project Initiation and Planning

What is Project Planning?

Project planning answers the key questions:

  • What needs to be done?
  • How will it be done?
  • Who will do it?
  • When will it be done?
  • How much will it cost?

Project Initiation

Project initiation is the first phase of the project lifecycle. It involves formally recognizing that a new project exists and establishing a foundation for the project before detailed planning begins.

Key Activities in Project Initiation

1. Identifying the Need or Problem

  • The project begins when a client, stakeholder, or organization identifies a business need, problem, or opportunity.
  • A feasibility study may be conducted to determine whether the project is worth pursuing.

2. Feasibility Study

The feasibility study evaluates the project from multiple angles:

TypeDescription
Technical FeasibilityCan the system be built with available technology?
Economic FeasibilityIs the project cost-effective? (Cost-Benefit Analysis)
Operational FeasibilityWill the system work in the organization's environment?
Schedule FeasibilityCan the project be completed within the required timeframe?
Legal FeasibilityAre there any legal or regulatory constraints?

3. Project Charter / Project Proposal

  • A project charter is a formal document that officially authorizes the project.
  • It includes:
    • Project title and description
    • Objectives and goals
    • Stakeholders and their roles
    • High-level scope
    • Initial budget and timeline estimates
    • Assumptions and constraints

4. Identifying Stakeholders

  • All individuals or groups who have an interest in the project are identified.
  • Examples: clients, end users, developers, managers, sponsors.

5. Appointing the Project Manager

  • A project manager is formally assigned with authority and responsibility to lead the project.

6. Initial Risk Identification

  • High-level risks are identified early so that mitigation strategies can be considered during planning.

Project Planning

Once the project is initiated, project planning begins. This is the most critical phase where detailed plans are created to guide execution and control.

Key Activities in Project Planning

1. Defining Project Scope

  • The scope defines the boundaries of the project: what is included and what is excluded.
  • A Work Breakdown Structure (WBS) is created to decompose the project into smaller, manageable tasks.

2. Resource Planning

  • Identifying the human resources (developers, testers, analysts), hardware, software, and tools required.
  • Assigning roles and responsibilities to team members.

3. Time / Schedule Planning

  • Estimating the duration of each task.
  • Creating a project schedule using tools such as:
    • Gantt Charts: Bar charts showing tasks against time.
    • PERT (Program Evaluation and Review Technique): Network diagram showing task dependencies and critical path.
    • CPM (Critical Path Method): Identifies the longest path of dependent tasks.

4. Cost Estimation and Budgeting

  • Estimating the cost of each activity and resource.
  • Common estimation techniques:
    • LOC (Lines of Code) based estimation
    • Function Point Analysis
    • COCOMO Model (Constructive Cost Model)
  • A project budget is prepared and approved.

5. Risk Management Planning

  • Identifying potential risks that could affect the project.
  • Analyzing the probability and impact of each risk.
  • Developing risk mitigation and contingency plans.

6. Quality Planning

  • Defining quality standards and metrics for the project.
  • Planning for reviews, inspections, and testing activities.

7. Communication Planning

  • Defining how information will be shared among stakeholders.
  • Deciding on meeting schedules, reporting formats, and communication channels.

8. Configuration Management Planning

  • Planning how changes to project artifacts (code, documents) will be tracked and controlled.

Relationship Between Initiation and Planning

Project Need Identified
        |
        v
  Feasibility Study
        |
        v
  Project Charter (Initiation Complete)
        |
        v
  Scope Definition
        |
        v
  WBS, Schedule, Cost, Risk Plans (Planning Complete)
        |
        v
  Project Execution Begins

Summary Table

PhaseKey Output
InitiationProject Charter, Feasibility Report, Stakeholder List
PlanningWBS, Schedule (Gantt/PERT), Budget, Risk Plan, Quality Plan

Conclusion

Project initiation and planning together form the foundation of successful software project management. Initiation establishes the justification and authorization for the project, while planning provides the detailed roadmap. Without proper initiation and planning, projects are likely to face cost overruns, schedule delays, and scope creep, ultimately leading to project failure.