BIT253 ยท 2082 ยท 5 marks
write short notes on a. Single-location installation Decision Tree [2.5+2.5]
write short notes on a. Single-location installation Decision Tree [2.5+2.5]
Quick answer
A Decision Tree is a graphical, tree-shaped diagram used to evaluate decisions under conditions of uncertainty by mapping out possible choices, chance events, and their outcomes.
Short Notes: Single-Location Installation Decision Tree
Single-Location Installation Decision Tree
A Single-Location Installation Decision Tree is applied when an organization must decide whether, when, and how to install a system (or facility) at one specific location, considering costs, probabilities, and expected payoffs.
Structure of a Decision Tree
| Symbol | Meaning |
|---|---|
| Square node ( $\square$ ) | Decision node (choice made by decision maker) |
| Circle node ( $\bigcirc$ ) | Chance node (outcome depends on probability) |
| Branch | A possible action or outcome |
| Leaf/End node | Final payoff or value |
Key Components
- Decision Alternatives - e.g., Install now, Delay installation, Do not install
- States of Nature - e.g., High demand, Low demand (with associated probabilities)
- Probabilities - Each chance branch has a probability; all branches from a chance node must sum to 1.0
- Payoffs - Net benefit or cost at each end node
Steps to Solve
- Draw the tree from left to right (decisions first, then chance events)
- Assign probabilities to chance branches
- Assign payoffs to terminal nodes
- Roll back (right to left):
- At chance nodes: compute Expected Monetary Value (EMV) $$EMV = \sum_{i} P_i \times \text{Payoff}_i$$
- At decision nodes: select the alternative with the highest EMV
Worked Example
Suppose a company decides whether to install a system at a single location:
-
Alternative 1: Install Now - Cost = Rs. 50,000
- High demand (P = 0.6): Revenue = Rs. 1,20,000 โ Net = Rs. 70,000
- Low demand (P = 0.4): Revenue = Rs. 30,000 โ Net = Rs. -20,000
-
Alternative 2: Do Not Install - Net payoff = Rs. 0
EMV Calculation:
$$EMV(\text{Install Now}) = (0.6 \times 70{,}000) + (0.4 \times -20{,}000)$$ $$= 42{,}000 - 8{,}000 = \textbf{Rs. 34,000}$$
$$EMV(\text{Do Not Install}) = \textbf{Rs. 0}$$
Decision: Install Now, since Rs. 34,000 > Rs. 0
Advantages
- Provides a visual and systematic approach to complex decisions
- Handles uncertainty through probability
- Easy to understand and communicate to stakeholders
Limitations
- Probabilities may be subjective or difficult to estimate
- Can become complex with many branches
- Assumes outcomes are mutually exclusive
Conclusion: The Single-Location Installation Decision Tree is a powerful tool for evaluating installation decisions at one site by comparing expected values of alternatives, helping managers make rational, data-driven choices.
Short on time? The 1, 5 and 10 mark versions of this answer, flashcards and practice sets come with a program pass.