BIT402 · 2080 · 10 marks

Draw activity-on-arrow diagram for the above scenario and find the critical path. | Project Activities | Duration (Week) | Precedence | |---|---|---| | A | 2 | | | B | 3 | A | | C | 4 | A | | D | 5 | B, C | | E | 2 | D |

Draw activity-on-arrow diagram for the above scenario and find the critical path.

Project ActivitiesDuration (Week)Precedence
A2
B3A
C4A
D5B, C
E2D

[10]

Software Project ManagementChapter 2: Project Planning and SchedulingCritical path and critical activitiesNumerical: activity on arrow critical path

Activity-on-Arrow (AOA) Diagram and Critical Path

Given

ActivityDuration (weeks)Predecessor
A2-
B3A
C4A
D5B, C
E2D

Step 2: Build the AOA Network

Nodes (events) are numbered; arrows are activities.

  • Node 1: Start
  • A runs from Node 1 → Node 2
  • After A, both B and C start from Node 2
  • B and C both must finish before D. So B: 2 → 3 and C: 2 → 3 (both merge at Node 3)
  • D runs from Node 3 → Node 4
  • E runs from Node 4 → Node 5 (End)
            B(3)
        ┌──────────┐
        ↓          │
(1)──A(2)──►(2)     ├──►(3)──D(5)──►(4)──E(2)──►(5)
        │          ↑
        └──────────┘
            C(4)

Since B and C share the same start (Node 2) and end (Node 3), a dummy activity is technically required to keep unique identification in strict AOA notation:

(1) --A(2)--> (2) --B(3)--> (3)
                 \          ^
                  C(4)      | dummy(0)
                   \        |
                    v       |
                    (3')----+
                    |
                    D(5)
                    v
                   (4) --E(2)--> (5)

For simplicity the merge is shown at Node 3.

Step 3: Forward Pass (ES, EF)

$EF = ES + \text{Duration}$

ActivityDurationESEF
A202
B325
C426
D5$\max(5,6)=6$11
E21113

Project duration (EF of E) = 13 weeks

Step 4: Backward Pass (LF, LS)

$LS = LF - \text{Duration}$, starting from $LF_E = 13$

ActivityDurationLFLS
E21311
D5116
B363
C462
A220

Step 5: Slack / Float

$\text{Slack} = LS - ES$

ActivityESLSSlackCritical?
A000Yes
B231No
C220Yes
D660Yes
E11110Yes

Step 6: Critical Path

Activities with zero slack: A, C, D, E

$$\boxed{\text{Critical Path: } A \to C \to D \to E}$$

Total Project Duration $= 2 + 4 + 5 + 2 = 13$ weeks

Any delay in A, C, D, or E delays the whole project. Activity B has 1 week of float.