BIT402 · 2080 · 10 marks
Draw activity-on-arrow diagram for the above scenario and find the critical path. | Project Activities | Duration (Week) | Precedence | |---|---|---| | A | 2 | | | B | 3 | A | | C | 4 | A | | D | 5 | B, C | | E | 2 | D |
Draw activity-on-arrow diagram for the above scenario and find the critical path.
| Project Activities | Duration (Week) | Precedence |
|---|---|---|
| A | 2 | |
| B | 3 | A |
| C | 4 | A |
| D | 5 | B, C |
| E | 2 | D |
[10]
Activity-on-Arrow (AOA) Diagram and Critical Path
Given
| Activity | Duration (weeks) | Predecessor |
|---|---|---|
| A | 2 | - |
| B | 3 | A |
| C | 4 | A |
| D | 5 | B, C |
| E | 2 | D |
Step 2: Build the AOA Network
Nodes (events) are numbered; arrows are activities.
- Node 1: Start
- A runs from Node 1 → Node 2
- After A, both B and C start from Node 2
- B and C both must finish before D. So B: 2 → 3 and C: 2 → 3 (both merge at Node 3)
- D runs from Node 3 → Node 4
- E runs from Node 4 → Node 5 (End)
B(3)
┌──────────┐
↓ │
(1)──A(2)──►(2) ├──►(3)──D(5)──►(4)──E(2)──►(5)
│ ↑
└──────────┘
C(4)
Since B and C share the same start (Node 2) and end (Node 3), a dummy activity is technically required to keep unique identification in strict AOA notation:
(1) --A(2)--> (2) --B(3)--> (3)
\ ^
C(4) | dummy(0)
\ |
v |
(3')----+
|
D(5)
v
(4) --E(2)--> (5)
For simplicity the merge is shown at Node 3.
Step 3: Forward Pass (ES, EF)
$EF = ES + \text{Duration}$
| Activity | Duration | ES | EF |
|---|---|---|---|
| A | 2 | 0 | 2 |
| B | 3 | 2 | 5 |
| C | 4 | 2 | 6 |
| D | 5 | $\max(5,6)=6$ | 11 |
| E | 2 | 11 | 13 |
Project duration (EF of E) = 13 weeks
Step 4: Backward Pass (LF, LS)
$LS = LF - \text{Duration}$, starting from $LF_E = 13$
| Activity | Duration | LF | LS |
|---|---|---|---|
| E | 2 | 13 | 11 |
| D | 5 | 11 | 6 |
| B | 3 | 6 | 3 |
| C | 4 | 6 | 2 |
| A | 2 | 2 | 0 |
Step 5: Slack / Float
$\text{Slack} = LS - ES$
| Activity | ES | LS | Slack | Critical? |
|---|---|---|---|---|
| A | 0 | 0 | 0 | Yes |
| B | 2 | 3 | 1 | No |
| C | 2 | 2 | 0 | Yes |
| D | 6 | 6 | 0 | Yes |
| E | 11 | 11 | 0 | Yes |
Step 6: Critical Path
Activities with zero slack: A, C, D, E
$$\boxed{\text{Critical Path: } A \to C \to D \to E}$$
Total Project Duration $= 2 + 4 + 5 + 2 = 13$ weeks
Any delay in A, C, D, or E delays the whole project. Activity B has 1 week of float.