Software Project Management208010 marksNumerical: activity on arrow critical pathCritical path and critical activities

Draw activity-on-arrow diagram for the above scenario and find the critical path. | Project Activities | Duration (Week) | Precedence | |---|---|---| | A | 2 | | | B | 3 | A | | C | 4 | A | | D | 5 | B, C | | E | 2 | D |

Draw activity-on-arrow diagram for the above scenario and find the critical path.

Project ActivitiesDuration (Week)Precedence
A2
B3A
C4A
D5B, C
E2D

[10]

Activity Duration (weeks) Predecessor ----------------------------------------- A 2 - B 3 A C 4 A D 5 B, C E 2 D Nodes (events) are numbered; arrows are activities. - Node 1: Start - A runs from Node 1 → Node 2 - After A, both B and C start from Node 2 - B and C both must finish before D. So B: 2...