BIT402 ยท 2082 ยท 5 marks
List estimation models. Explain estimation by analogy with example.
List estimation models. Explain estimation by analogy with example. [5]
Quick answer
The main estimation models used in software project estimation are: Algorithmic/Parametric Models; COCOMO (Constructive Cost Model); SLIM (Software Lifecycle Management).
Estimation Models - Model Answer
List of Estimation Models
The main estimation models used in software project estimation are:
-
Algorithmic/Parametric Models
- COCOMO (Constructive Cost Model)
- SLIM (Software Lifecycle Management)
- Function Point Analysis
-
Expert Judgment Models
- Delphi Technique
- Planning Poker
- Expert Opinion
-
Analogy-Based Models
- Estimation by Analogy
- Case-Based Reasoning
-
Machine Learning Models
- Neural Networks
- Regression Analysis
-
Hybrid Models
- Combination of multiple approaches
Estimation by Analogy - Explanation with Example
Definition
Estimation by analogy is a technique where project effort/cost is estimated by comparing the current project with similar completed projects from historical data. The estimation is based on the assumption that similar projects will require similar effort and resources.
Process
- Identify completed projects with similar characteristics
- Find the closest match(es) from historical records
- Adjust estimates based on differences between current and past projects
- Use the adjusted values as estimates for the current project
Example
Scenario: Estimating effort for a new e-commerce website project.
Historical Project (Completed):
- Similar e-commerce website built 6 months ago
- Size: 50,000 lines of code
- Team: 5 developers
- Effort: 2,000 person-hours
- Duration: 4 months
Current Project:
- New e-commerce website
- Estimated Size: 60,000 lines of code (20% larger)
- Similar technology stack
- Similar complexity
Estimation:
- Base estimate from analogy: 2,000 person-hours
- Adjustment factor for 20% larger size: 1.2
- Estimated effort = 2,000 ร 1.2 = 2,400 person-hours
- Estimated duration โ 4.8 months (approximately 5 months)
Advantages
- Simple and intuitive
- Based on real project data
- Quick estimation process
Limitations
- Requires good historical data
- Difficult to find truly similar projects
- Subjective adjustment factors
Short on time? The 1, 5 and 10 mark versions of this answer, flashcards and practice sets come with a program pass.