BIT402 ยท TU past paper
Software Project Management 2080 question paper
The complete TU 2080 exam paper for Software Project Management (BIT402), all 12 questions with solved model answers written to the mark scheme.
Tap a question to open its answer.
- Q1.10 marksIncremental delivery approachHideAnswer
Explain incremental delivery approach with a neat diagram. What are its advantages and disadvantages?[10]
- Q2.10 marksCOCOMO II model and stagesHideAnswer
What is cost estimation? Explain COCOMO II with respect to post architecture effort multipliers. List its advantages.[10]
- Q3.10 marksNumericalCritical path and critical activitiesHideAnswer
Draw activity-on-arrow diagram for the above scenario and find the critical path.
Project Activities Duration (Week) Precedence A 2 B 3 A C 4 A D 5 B, C E 2 D [10]
Activity-on-Arrow (AOA) Diagram and Critical Path
Given
Activity Duration (weeks) Predecessor A 2 - B 3 A C 4 A D 5 B, C E 2 D Step 2: Build the AOA Network
Nodes (events) are numbered; arrows are activities.
- Node 1: Start
- A runs from Node 1 โ Node 2
- After A, both B and C start from Node 2
- B and C both must finish before D. So B: 2 โ 3 and C: 2 โ 3 (both merge at Node 3)
- D runs from Node 3 โ Node 4
- E runs from Node 4 โ Node 5 (End)
B(3) โโโโโโโโโโโโ โ โ (1)โโA(2)โโโบ(2) โโโโบ(3)โโD(5)โโโบ(4)โโE(2)โโโบ(5) โ โ โโโโโโโโโโโโ C(4)Since B and C share the same start (Node 2) and end (Node 3), a dummy activity is technically required to keep unique identification in strict AOA notation:
(1) --A(2)--> (2) --B(3)--> (3) \ ^ C(4) | dummy(0) \ | v | (3')----+ | D(5) v (4) --E(2)--> (5)For simplicity the merge is shown at Node 3.
Step 3: Forward Pass (ES, EF)
$EF = ES + \text{Duration}$
Activity Duration ES EF A 2 0 2 B 3 2 5 C 4 2 6 D 5 $\max(5,6)=6$ 11 E 2 11 13 Project duration (EF of E) = 13 weeks
Step 4: Backward Pass (LF, LS)
$LS = LF - \text{Duration}$, starting from $LF_E = 13$
Activity Duration LF LS E 2 13 11 D 5 11 6 B 3 6 3 C 4 6 2 A 2 2 0 Step 5: Slack / Float
$\text{Slack} = LS - ES$
Activity ES LS Slack Critical? A 0 0 0 Yes B 2 3 1 No C 2 2 0 Yes D 6 6 0 Yes E 11 11 0 Yes Step 6: Critical Path
Activities with zero slack: A, C, D, E
$$\boxed{\text{Critical Path: } A \to C \to D \to E}$$
Total Project Duration $= 2 + 4 + 5 + 2 = 13$ weeks
Any delay in A, C, D, or E delays the whole project. Activity B has 1 week of float.
- Q4.5 marksPersonnel selection and job assignmentHideAnswer
Explain how we can select the right person for the job. [5]
- Q5.5 marksContract management processHideAnswer
What is a contract? Explain contract management process. [5]
Model Answer: Contract and Contract Management Process
What is a Contract?
A contract is a legally binding agreement between two or more parties that establishes mutual obligations and rights. In the context of software engineering and IT projects, a contract specifies:
- Deliverables: What products or services will be provided
- Terms and conditions: Payment, timeline, and performance standards
- Responsibilities: Duties of each party
- Legal enforceability: Consequences for breach or non-compliance
Contracts form the foundation of formal agreements between clients and service providers, ensuring clarity and protection for all parties involved.
Contract Management Process
The contract management process typically involves the following phases:
1. Contract Planning
- Identify the need for a contract
- Define scope, objectives, and requirements
- Determine contract type (fixed-price, time-and-materials, etc.)
- Establish success criteria and performance metrics
2. Contract Development
- Draft contract terms and conditions
- Include detailed specifications and deliverables
- Define payment schedules and milestones
- Specify roles, responsibilities, and timelines
- Include risk allocation and dispute resolution clauses
3. Contract Review and Negotiation
- Review contract by legal and technical teams
- Negotiate terms with the other party
- Resolve conflicts and ambiguities
- Obtain necessary approvals from stakeholders
4. Contract Execution
- Finalize and sign the contract by authorized representatives
- Distribute copies to all relevant parties
- Establish baseline documentation and records
5. Contract Monitoring and Control
- Track deliverables against agreed specifications
- Monitor timelines and milestones
- Manage changes through formal change control procedures
- Ensure compliance with contract terms
- Document performance metrics and issues
6. Contract Closure
- Verify all deliverables have been completed
- Conduct final acceptance testing
- Process final payments
- Archive contract documentation
- Conduct post-project review and lessons learned
Key Point: Effective contract management ensures mutual understanding, reduces disputes, and facilitates successful project completion.
- Q6.5 marksModern project management practicesHideAnswer
Explain modern project management practices. List out the importance of project management. [5]
- Q7.5 marksProgress visualization methodsHideAnswer
Explain any two methods that can be used to visualize progress of a project. [5]
- Q8.5 marksCoordination dependencies in organizationsHideAnswer
What are different classification of coordination dependencies that exists in an organization? Explain. [5]
- Q9.5 marksBreak Even Point significanceHideAnswer
Explain the significance of Break Event Point and Return on Investment. [5]
- Q10.5 marksRisk handling approachesHideAnswer
Explain different approaches that can be used to handle risk. [5]
- Q11.5 marksSoftware quality enhancement techniquesHideAnswer
Briefly explain the techniques that can be used to enhance the software quality. [5]
- Q12.5 marksScrum frameworkHideAnswer
Write short notes on a. Scrum b. Resource schedule [5]