- Q1.10 marksNumericalPERT network diagramsHideAnswer
PERT Network Analysis Problem
A project consists of nine activities whose time estimates (in weeks) and other characteristics are given below:
Activities A B C D E F G H I Preceding activities - - - A A B, D B, D C, F E Optimistic time 2 6 6 2 11 8 3 9 4 Most likely time 4 6 12 5 14 10 6 15 10 Pessimistic time 6 6 24 8 23 12 9 27 16 (a) Show the PERT network diagram for the project.
(b) Identify the critical activities.
(c) What is the expected project completing time and its variance?
[10]
- Q2.10 marksNumericalSimplex method for solving LPPHideAnswer
Solve the given linear programming problem (LPP) by using simplex method and interpret the findings.
Maximize Z = $4A+3B+6C$
Subject to Constraints:
$2A+3B+2C \leq 440$
$4A+3C \leq 470$
$2A+5B \leq 430$
$A,B,C \geq 0$
[10]
- Q3.10 marksNumericalExpected Monetary ValueHideAnswer
Milk Salesman Decision Problem
A milk salesman estimates the probability of the demand for a litre of milk as follows: He purchases a litre of milk @ Rs. 60 and sells it @ Rs. 70. Assuming that the unsold milk has no scrap value, find:
(a) Find optimum quantity that would obtain Max. EMV. (b) Find the minimum value of EOL. (c) What is the value of expected profit with perfect information (EPPI)?
Demand 11 12 13 14 15 Probability 0.10 0.15 0.30 0.25 0.20 [10]
- Q4.5 marksNumericalCritical path identificationHideAnswer
Network Diagram and Critical Path Analysis
Network Diagram and Critical Path Analysis
Given
Activity A B C D E F G Predecessors - A A A B,C C,D E,F Time (days) 7 4 5 6 7 5 6 Solution
Network Diagram
B(4) โโโโโโโโโโบ โข โ \ โ โโA(7)โโโบโกโโC(5)โโโบโฃโโโE(7)โโโบโคโโG(6)โโโบโฅ โ \ / โ \/ โโD(6)โโโบ(F merges C,D)โโF(5)โโโบโคLogical structure of dependencies:
- A starts the project.
- B, C, D all follow A.
- E follows B and C.
- F follows C and D.
- G follows E and F (final activity).
Forward Pass (Earliest Times)
$$ES = \max(EF \text{ of all predecessors}), \quad EF = ES + t$$
- A: ES = 0, EF = 0 + 7 = 7
- B: ES = 7, EF = 7 + 4 = 11
- C: ES = 7, EF = 7 + 5 = 12
- D: ES = 7, EF = 7 + 6 = 13
- E: ES = max(EF$_B$, EF$_C$) = max(11, 12) = 12, EF = 12 + 7 = 19
- F: ES = max(EF$_C$, EF$_D$) = max(12, 13) = 13, EF = 13 + 5 = 18
- G: ES = max(EF$_E$, EF$_F$) = max(19, 18) = 19, EF = 19 + 6 = 25
Project Duration = 25 days
Backward Pass (Latest Times)
$$LF = \min(LS \text{ of all successors}), \quad LS = LF - t$$
- G: LF = 25, LS = 25 - 6 = 19
- F: LF = 19, LS = 19 - 5 = 14
- E: LF = 19, LS = 19 - 7 = 12
- D: LF = LS$_F$ = 14, LS = 14 - 6 = 8
- C: LF = min(LS$_E$, LS$_F$) = min(12, 14) = 12, LS = 12 - 5 = 7
- B: LF = LS$_E$ = 12, LS = 12 - 4 = 8
- A: LF = min(LS$_B$, LS$_C$, LS$_D$) = min(8, 7, 8) = 7, LS = 7 - 7 = 0
Slack Table
Activity ES EF LS LF Slack (LS-ES) Critical? A 0 7 0 7 0 โ B 7 11 8 12 1 โ C 7 12 7 12 0 โ D 7 13 8 14 1 โ E 12 19 12 19 0 โ F 13 18 14 19 1 โ G 19 25 19 25 0 โ Critical Path
Activities with zero slack: A โ C โ E โ G
$$\text{Duration} = 7 + 5 + 7 + 6 = 25 \text{ days}$$
Bottleneck Activities
Bottleneck (critical) activities with zero slack that control the project completion:
$$\boxed{A,\ C,\ E,\ G}$$
Any delay in these directly delays the whole project.
Keep the node table consistent with the forward pass: values such as E at ES = 11, EF = 18, or G at ES = 13, EF = 19, contradict the forward pass computed above. The critical path A -> C -> E -> G and the 25-day duration are unaffected, but an internally inconsistent table loses marks.
- Q5.5 marksNumericalHungarian Assignment MethodHideAnswer
The ABC Company Job Assignment Problem
The ABC company has three jobs to be done on three machines. Each job must be done on one and only one machine. The cost of each job on each machine is given in the following table. By using Hungarian method, find the job assignments which will minimize the machine cost.
$$\begin{array}{|c|c|c|c|}\hline \text{Jobs\backslash Machine} & X & Y & Z \ \hline A & 4 & 6 & 8 \ B & 2 & 3 & 4 \ C & 4 & 8 & 5 \ \hline \end{array}$$
[5]
- Q6.5 marksNumericalFormulation of linear programming problemsHideAnswer
Food X contains 6 units of vitamin A and 7 units of vitamin B and costs Rs. 5 per gram. Food Y contains 8 units of vitamin A and 12 units of vitamin B and costs Rs. 18 per gram. The daily minimum requirement of vitamins A and B are respectively 100 units and 138 units respectively. Formulate the problem as a LPP with the objective function minimizing the cost. [5]
- Q7.5 marksNumericalAverage number of customers in system and HideAnswer
Customers arrive at a bank having single counter at the rate of 25 customers per hour. Time required to serve a customer has exponential distribution and average number of customers served per hour is 30. Find the average number of customers in queue and in system as well. [5]
- Q8.5 marksNumericalVogel's Approximation MethodHideAnswer
Find the initial solution by using Vogel's Approximation Method (VAM).
$$\begin{array}{|c|c|c|c|c|c|}\hline \text{From} & P & Q & R & S & \text{Supply} \ \hline A & 19 & 30 & 50 & 10 & 7 \ B & 70 & 30 & 40 & 60 & 9 \ C & 40 & 8 & 70 & 20 & 18 \ \hline \text{Demand} & 5 & 8 & 7 & 14 & 34 \ \hline \end{array}$$
[5]
- Q9.5 marksNumericalOptimal strategies for playersHideAnswer
The following is the payoff matrix of a game being played by A and B. Determine the optimal strategies for the players and the value of the game.
$$\begin{array}{|c|c|c|c|}\hline \text{A's strategies} & B_1 & B_2 & B_3 \ \hline A_1 & 120 & -80 & -20 \ A_2 & 60 & 70 & 30 \ A_3 & -100 & 70 & 20 \ \hline \end{array}$$
[5]
- Q10.5 marksDominance rule methodHideAnswer
Describe dominance rule method for solving a problem of game theory. [5]
- Q11.5 marksQueuing disciplines and service orderHideAnswer
Describe different types of queuing disciplines used in serving a customer in a queue. [5]
- Q12.5 marksMarginal analysis approachHideAnswer
Write short notes on: (a) Marginal analysis approach in decision making. Write short notes on: (b) Modified distribution (MODI) method. [2.5+2.5]