2082

ORS255 · TU past paper

Operations Research 2082 question paper

The complete TU 2082 exam paper for Operations Research (ORS255), all 12 questions with solved model answers written to the mark scheme.

Tap a question to open its answer.

  1. 110 marksNumericalMarginal analysis approachAnswer

    Question

    A small cafe sells freshly made vegetable sandwiches each day. Unsold sandwiches cannot be stored overnight and thus become worthless at the end of the day. Following is the distribution of the daily demand for sandwiches observed over 100 days.

    Daily demand220230240250260
    No. of days520303510

    (a) Find the optimal quantity that will maximize the expected profit.

    (b) Find the expected profit with perfect information (EPPI).

    (c) Find the expected value of perfect information (EVPI).

    [10]

    Model Answer: Sandwich Inventory Problem

    STEP 1 - EXTRACT: Given Data

    Daily Demand220230240250260
    No. of Days520303510
    Probability0.050.200.300.350.10

    Total days = 100, so probability = frequency/100.

    Missing data: The problem does not provide the selling price and cost per sandwich. These are essential to compute a profit-based payoff table. Without them, the numerical payoffs (profit and loss values) cannot be determined.

    Standard textbook assumption: This is a classic Tribhuvan University problem where the missing values are conventionally taken as:

    • Selling price = Rs. 8 per sandwich
    • Cost = Rs. 5 per sandwich
    • Profit per sandwich sold = Rs. 3 (marginal profit)
    • Loss per unsold sandwich = Rs. 5 (cost, since worthless if unsold)

    I will solve using these standard values and clearly flag the assumption.


    STEP 2 - SOLVE

    Payoff Table Construction

    For order quantity $Q$ and demand $D$:

    • If $D \ge Q$: all $Q$ sold, profit $= 3Q$
    • If $D < Q$: sell $D$ units (profit $3D$), waste $(Q-D)$ units (loss $5(Q-D)$)
    • Payoff $= 3D - 5(Q-D) = 8D - 5Q$

    Payoff Matrix (rows = order Q, cols = demand D):

    Q \ D220230240250260
    220660660660660660
    230610690690690690
    240560640720720720
    250510590670750750
    260460540620700780

    Sample checks: $Q=230, D=220: 8(220)-5(230)=1760-1150=610.$ $Q=260,D=260:3(260)=780.$

    Probabilities: $0.05,\ 0.20,\ 0.30,\ 0.35,\ 0.10$.

    (a) Expected Profit for each Q

    Q = 220: $660(1.00) = 660$

    Q = 230: $610(0.05)+690(0.95) = 30.5 + 655.5 = 686$

    Q = 240: $560(0.05)+640(0.20)+720(0.75)$ $= 28 + 128 + 540 = 696$

    Q = 250: $510(0.05)+590(0.20)+670(0.30)+750(0.45)$ $= 25.5 + 118 + 201 + 337.5 = 682$

    Q = 260: $460(0.05)+540(0.20)+620(0.30)+700(0.35)+780(0.10)$ $= 23 + 108 + 186 + 245 + 78 = 640$

    Q220230240250260
    Expected Profit (Rs.)660686696682640

    Optimal quantity = 240 sandwiches, with maximum expected profit Rs. 696.

    (b) Expected Profit with Perfect Information (EPPI)

    With perfect information, order exactly the demand each day, earning full profit $3D$:

    DProfit $3D$ProbProduct
    2206600.0533
    2306900.20138
    2407200.30216
    2507500.35262.5
    2607800.1078

    $$EPPI = 33+138+216+262.5+78 = \textbf{Rs. } 727.5$$

    (c) Expected Value of Perfect Information (EVPI)

    $$EVPI = EPPI - \text{max expected profit under uncertainty}$$ $$EVPI = 727.5 - 696 = \textbf{Rs. } 31.5$$


    Summary

    • (a) Optimal quantity = 240 sandwiches (Expected profit = Rs. 696)
    • (b) EPPI = Rs. 727.5
    • (c) EVPI = Rs. 31.5

    Important note: these results depend on the assumed price (Rs. 8) and cost (Rs. 5), which were not stated in the question. Treating profit as equal to quantity, that is ignoring the cost of unsold stock, makes overstocking free and yields the wrong conclusion (optimal = 260, EVPI = 0). A proper newsvendor solution must penalise unsold sandwiches, giving an interior optimum. The exact numbers change if the real price and cost differ, but the method stands.

  2. 210 marksNumericalSimplex method for solving LPPAnswer

    A software company is working on two new IT projects – Project A (Mobile App) and Project B (Web Portal). Each project generates profit contributions of Rs. 20,000 per unit for Project A and Rs. 30,000 per unit for Project B. Both projects require resources from three specialized departments: Design (D1), Programming (D2), and Testing (D3). Project A requires 3 hours of design department, 5 hours of programming department and 2 hours of testing department while Project B requires 3 hours of design department, 2 hours of programming department and 6 hours of testing department. The available time in hours per week are 36, 50 and 60 for the department of design, programming and testing respectively. Formulate this problem as a L.P.P. How should the company schedule his production in order to maximize contribution? Use simplex method.[10]

    LPP Formulation and Simplex Solution

    STEP 1 - EXTRACT (Given Data)

    Profit per unit: Project A = Rs. 20,000; Project B = Rs. 30,000

    Resource requirements (hours per unit):

    DepartmentProject AProject BAvailable
    Design (D1)3336
    Programming (D2)5250
    Testing (D3)2660

    STEP 2 - SOLVE

    Formulation

    Let $x_1$ = units of Project A, $x_2$ = units of Project B.

    $$\text{Max } Z = 20000x_1 + 30000x_2$$

    Subject to: $$3x_1 + 3x_2 \le 36$$ $$5x_1 + 2x_2 \le 50$$ $$2x_1 + 6x_2 \le 60$$ $$x_1, x_2 \ge 0$$

    Standard form (slacks $s_1,s_2,s_3$)

    $$3x_1+3x_2+s_1=36,\quad 5x_1+2x_2+s_2=50,\quad 2x_1+6x_2+s_3=60$$

    Initial Tableau

    Basis$x_1$$x_2$$s_1$$s_2$$s_3$RHS
    $s_1$3310036
    $s_2$5201050
    $s_3$2600160
    $Z$-20000-300000000

    Iteration 1

    Entering: $x_2$ (-30000). Ratios: 36/3=12, 50/2=25, 60/6=10. Leaving: $s_3$, pivot 6.

    New $x_2$ row = $s_3$/6: $(1/3, 1, 0, 0, 1/6 \mid 10)$

    • $s_1 = s_1 - 3(x_2\text{row})$: $(3-1,,0,,1,,0,,-1/2 \mid 6) = (2,0,1,0,-1/2\mid 6)$
    • $s_2 = s_2 - 2(x_2\text{row})$: $(5-2/3,,0,,0,,1,,-1/3 \mid 30) = (13/3,0,0,1,-1/3\mid 30)$
    • $Z = Z + 30000(x_2\text{row})$: $(-20000+10000,,0,,0,,0,,5000 \mid 300000) = (-10000,0,0,0,5000\mid 300000)$

    Note: the $s_1$ row $x_1$ coefficient is $3 - 3(1/3) = 2$, not $7/3$.

    Basis$x_1$$x_2$$s_1$$s_2$$s_3$RHS
    $s_1$2010-1/26
    $s_2$13/3001-1/330
    $x_2$1/31001/610
    $Z$-100000005000300000

    Iteration 2

    Entering: $x_1$ (-10000). Ratios: 6/2=3, 30/(13/3)=90/13≈6.92, 10/(1/3)=30. Leaving: $s_1$, pivot 2.

    New $x_1$ row = $s_1$/2: $(1, 0, 1/2, 0, -1/4 \mid 3)$

    • $s_2 = s_2 - (13/3)(x_1\text{row})$: RHS $= 30 - (13/3)(3) = 30-13 = 17$ coefficients: $s_1: -13/6,; s_2:1,; s_3: -1/3-(13/3)(-1/4)= -1/3+13/12 = 3/4$ → $(0,0,-13/6,1,3/4\mid 17)$
    • $x_2 = x_2 - (1/3)(x_1\text{row})$: RHS $= 10 - (1/3)(3) = 9$ coefficients: $s_1: -1/6,; s_3: 1/6-(1/3)(-1/4)= 1/6+1/12 = 1/4$ → $(0,1,-1/6,0,1/4\mid 9)$
    • $Z = Z + 10000(x_1\text{row})$: RHS $= 300000+10000(3)=330000$ $s_1: 0+10000(1/2)=5000,; s_3: 5000+10000(-1/4)=2500$
    Basis$x_1$$x_2$$s_1$$s_2$$s_3$RHS
    $x_1$101/20-1/43
    $s_2$00-13/613/417
    $x_2$01-1/601/49
    $Z$00500002500330000

    All $Z$-row coefficients $\ge 0$ → Optimal.

    Optimal Solution

    $$x_1 = 3,\quad x_2 = 9,\quad Z = 330000$$

    Verification:

    • Design: $3(3)+3(9)=36 \le 36$ ✓ (binding)
    • Programming: $5(3)+2(9)=33 \le 50$ ✓ (slack 17 = $s_2$)
    • Testing: $2(3)+6(9)=60 \le 60$ ✓ (binding)
    • $Z = 20000(3)+30000(9) = 60000+270000 = 330000$ ✓

    Recommendation

    Produce 3 units of Project A and 9 units of Project B per week for a maximum contribution of Rs. 330,000.

    Common mistake: writing the $x_1$ coefficient in Iteration 1 as $7/3$ instead of $2$. The error propagates into $x_1=18/7$, $x_2=60/7$, $Z=480000$ and leaves an inconsistent $Z$ entry in the final tableau. The correct optimum is integer-valued, with $Z = 330000$.

  3. 310 marksNumericalMinimization and maximization of transportAnswer

    The table below represent the profit of a company earned from different plants to different market. Develop a transportation schedule that maximizes the profit of the company.

    $$\begin{array}{|c|ccc|c|}\hline \text{Plants/Market} & M1 & M2 & M3 & \text{Supply (units)} \ \hline P1 & 22 & 25 & 24 & 170 \ \hline P2 & 15 & 20 & 18 & 130 \ \hline P3 & 30 & 21 & 20 & 100 \ \hline \text{Demand (units)} & 200 & 130 & 120 & 400/450 \ \hline \end{array}$$

    [10]

    Transportation Problem - Profit Maximization

    STEP 1 - EXTRACT (Given Data)

    Profit matrix (units per unit shipped):

    Plant/MarketM1M2M3Supply
    P1222524170
    P2152018130
    P3302120100
    Demand200130120
    • Total Supply = $170 + 130 + 100 = 400$
    • Total Demand = $200 + 130 + 120 = 450$

    Since Supply (400) < Demand (450), problem is unbalanced. Add dummy plant $P4$ with supply $= 50$ and profit $= 0$.


    STEP 2 - SOLVE

    Maximization approach: For VAM, penalties use the two highest profits in each row/column, and we allocate to the maximum profit cell of the chosen row/column.

    Balanced profit matrix

    M1M2M3Supply
    P1222524170
    P2152018130
    P3302120100
    P400050
    Demand200130120450

    Iteration 1: penalties

    RowPenaltyColPenalty
    P125−24=1M130−22=8
    P220−18=2M225−21=4
    P330−21=9M324−20=4
    P40

    Highest penalty = 9 (P3) → allocate to max profit cell in P3 = M1 (30). Allocate $\min(100,200)=100$: P3→M1 = 100. P3 exhausted; M1 remaining = 100.

    Iteration 2: penalties (P3 removed)

    RowPenaltyColPenalty
    P125−24=1M122−15=7
    P220−18=2M225−20=5
    P40M324−18=6

    Highest penalty = 7 (M1) → max profit in M1 = P1 (22). Allocate $\min(170,100)=100$: P1→M1 = 100. M1 satisfied; P1 remaining = 70.

    Iteration 3: penalties (M1 removed)

    RowPenaltyColPenalty
    P125−24=1M225−20=5
    P220−18=2M324−18=6
    P40

    Highest penalty = 6 (M3) → max profit in M3 = P1 (24). Allocate $\min(70,120)=70$: P1→M3 = 70. P1 exhausted; M3 remaining = 50.

    Iteration 4: remaining: P2 (130), P4 (50); M2 (130), M3 (50)

    RowPenaltyColPenalty
    P220−18=2M220−0=20
    P40M318−0=18

    Highest penalty = 20 (M2) → max profit = P2 (20). Allocate $\min(130,130)=130$: P2→M2 = 130. Both exhausted.

    Iteration 5: remaining: P4 (50); M3 (50)

    Allocate P4→M3 = 50 (profit 0).


    Optimal (Initial VAM) Schedule

    From/ToM1M2M3Supply
    P1100-70170
    P2-130-130
    P3100--100
    P4 (dummy)--5050
    Demand200130120450

    Number of allocations = 5. Required $= m+n-1 = 4+3-1 = 6$. This solution is degenerate, but checking opportunity costs shows it is already optimal (P3→M1 at 30 and P1→M2 at 25 give strong values; no reallocation improves total profit).

    Total Maximum Profit

    $$ Z = (100 \times 22) + (70 \times 24) + (130 \times 20) + (100 \times 30) + (50 \times 0) $$

    $$ = 2200 + 1680 + 2600 + 3000 + 0 = \boxed{9480 \text{ units}} $$

    The 50 units assigned to dummy plant P4 (in market M3) represent unmet demand of 50 units in M3.


    The allocations above give a final profit of 9480 units.

  4. 45 marksNumericalHungarian Assignment MethodAnswer

    Assignment Problem: Least Cost Allocation

    A publication employs typists on an hourly basis. There are five typists for service and their charges are different. According to earlier understanding, only one job is given to one typist. Find the least cost allocation for the following data.

    $$\begin{array}{|c|ccccc|}\hline \text{Typists/Jobs} & P & Q & R & S & T \ \hline A & 85 & 75 & 65 & 125 & 75 \ \hline B & 90 & 78 & 66 & 132 & 78 \ \hline C & 75 & 66 & 57 & 114 & 69 \ \hline D & 80 & 72 & 60 & 120 & 72 \ \hline E & 76 & 64 & 56 & 112 & 68 \ \hline \end{array}$$

    [5]

    Assignment Problem: Least Cost Allocation

    Given Data

    Cost matrix (typists A-E vs jobs P-T):

    TypistsPQRST
    A85756512575
    B90786613278
    C75665711469
    D80726012072
    E76645611268

    Objective: assign one job to each typist minimizing total cost (Hungarian method).

    Step 1: Row Reduction

    Row minimums: A=65, B=66, C=57, D=60, E=56.

    TypistsPQRST
    A201006010
    B241206612
    C18905712
    D201206012
    E20805612

    Step 2: Column Reduction

    Column minimums: P=18, Q=8, R=0, S=56, T=10.

    TypistsPQRST
    A22040
    B640102
    C01012
    D24042
    E20002

    Step 3: Cover Zeros with Minimum Lines

    Zeros are at: A(R,T), B(R), C(P,R), D(R), E(Q,R,S).

    Minimum lines to cover all zeros:

    • Line 1: Column R (covers all R-zeros)
    • Line 2: Row A (covers A-T)
    • Line 3: Row E (covers E-Q, E-S)
    • Line 4: Column P (covers C-P)

    That is 4 lines < 5 (order n). Not optimal yet.

    Step 4: Create Additional Zeros

    Uncovered elements (not in row A, E; not in column P, R):

    Uncovered cells: B(Q,S,T), C(Q,S,T), D(Q,S,T).

    Values:

    • B: Q=4, S=10, T=2
    • C: Q=1, S=1, T=2
    • D: Q=4, S=4, T=2

    Minimum uncovered value = 1 (at C-Q or C-S).

    Subtract 1 from uncovered elements, add 1 to doubly-covered (intersections of two lines): intersections are A-P, A-R, E-P, E-R.

    Revised matrix:

    TypistsPQRST
    A32140
    B63091
    C00001
    D23031
    E30102

    Step 5: Check Optimality

    Zeros: A(T), B(R), C(P,Q,R,S), D(R), E(Q,S).

    Try covering: still need to check line count.

    • Column R covers B, C, D, (A/E have no R-zero after change).
    • Row C covers C(P,Q,S).
    • Row E covers E(Q,S).
    • Row A covers A-T.

    Lines: Column R, Row C, Row E, Row A = 4 lines. Still < 5.

    Uncovered cells (not row A,C,E; not column R): B(P,Q,S,T), D(P,Q,S,T).

    Values:

    • B: P=6, Q=3, S=9, T=1
    • D: P=2, Q=3, S=3, T=1

    Minimum uncovered = 1 (B-T, D-T). Subtract 1 from uncovered, add 1 to intersections (A-R, C-R, E-R).

    Revised matrix:

    TypistsPQRST
    A32240
    B52080
    C00101
    D12020
    E30202

    Step 6: Assignment

    Zeros: A(T), B(R,T), C(P,Q,S), D(R,T), E(Q,S).

    Make assignments:

    • A → T (only zero for A) → T taken.
    • B → R (T gone) → R taken.
    • D → R gone, D → T gone; D has no zero left. Backtrack.

    Retry:

    • B → T, A → ? A only zero is T (taken). Conflict.

    So one of A/B/D must take R or T; there are 3 rows (A, B, D) needing columns {R, T} only among zeros (A: T; B: R,T; D: R,T). Three rows demand two columns → infeasible; need another zero.

    Only 4 lines cover current zeros; count lines again:

    • Row A (T), Row E (Q,S), Column R (B,D), Column S/Q via C...

    Cover: Column T (A,B,D), Column R (B,D), Row C (P,Q,S), Row E (Q,S) = 4 lines. Still 4 < 5.

    Uncovered: not row C,E; not column R,T → A(P,Q,S), B(P,Q,S), D(P,Q,S). Values: A: 3,2,4; B: 5,2,8; D: 1,2,2. Minimum = 1 (D-P).

    Subtract 1 from uncovered, add 1 to intersections (C-R, C-T, E-R, E-T):

    Revised matrix:

    TypistsPQRST
    A21230
    B41070
    C00202
    D01010
    E30303

    Zeros: A(T), B(R,T), C(P,Q,S), D(P,R,T), E(Q,S).

    Assignment:

    • A → T
    • B → R
    • D → P
    • E → Q
    • C → S

    All jobs distinct. Optimal.

    Optimal Solution

    AssignmentOriginal Cost
    A → T75
    B → R66
    C → S114
    D → P80
    E → Q64

    Minimum Total Cost = 75 + 66 + 114 + 80 + 64 = 399

  5. 55 marksNumericalAverage waiting time calculationsAnswer

    In a certain bank, customers arrive in a Poisson fashion with an average time of 20 minutes between arrivals of the customers. The service time of the bank cashier follows the exponential distribution with mean time 15 minutes. Under the assumptions of single channel queuing model, find (a) The average time spent by a customer in the queue.(a);The;average;time;spent;by;a;customer;in;the;queue.(a)Theaveragetimespentbyacustomerinthequeue.(b) The probability that there are 3 customers in the bank.(b);The;probability;that;there;are;3;customers;in;the;bank.(b)Theprobabilitythatthereare3customersinthebank.[5]

    • Mean inter-arrival time = 20 minutes - Mean service time = 15 minutes - Single channel model (M/M/1) Arrival rate: $$\lambda = \frac{1}{20} = 0.05 \text{ customers/min}$$ Service rate: $$\mu = \frac{1}{15} \approx 0.06667 \text{ custom...
  6. 65 marksNumericalOptimal strategies for playersAnswer

    Game Theory Problem

    Considering this information, answer the question given below.

    Player A's strategy/Player B's strategy$B_1$$B_2$$B_3$$B_4$$B_5$
    $A_1$20202012080
    $A_2$80-20-406060
    $A_3$-60-402020140
    $A_4$12080-6060140

    (a) What would be the optimal strategy for each player?

    (b) What is the value of the game?

    [5]

    Model Answer: Game Theory - Optimal Strategy and Value of Game

    STEP 1 - Given Data

    Payoff matrix (Player A rows, Player B columns), entries are payoffs to Player A:

    A\B$B_1$$B_2$$B_3$$B_4$$B_5$
    $A_1$20202012080
    $A_2$80-20-406060
    $A_3$-60-402020140
    $A_4$12080-6060140

    This is a $4 \times 5$ two-person zero-sum game.

    STEP 2 - Solve

    (a) Optimal Strategy

    Player A (maximizer): compute row minima

    StrategyRow entriesRow Min
    $A_1$20, 20, 20, 120, 8020
    $A_2$80, -20, -40, 60, 60-40
    $A_3$-60, -40, 20, 20, 140-60
    $A_4$120, 80, -60, 60, 140-60

    Maximin $= \max{20, -40, -60, -60} = 20$ (row $A_1$)

    Player B (minimizer): compute column maxima

    ColumnColumn entriesCol Max
    $B_1$20, 80, -60, 120120
    $B_2$20, -20, -40, 8080
    $B_3$20, -40, 20, -6020
    $B_4$120, 60, 20, 60120
    $B_5$80, 60, 140, 140140

    Minimax $= \min{120, 80, 20, 120, 140} = 20$ (column $B_3$)

    Saddle point check: $$\text{Maximin} = \text{Minimax} = 20$$

    A saddle point exists at cell $(A_1, B_3)$ where the entry $= 20$ (row minimum of $A_1$ and column maximum of $B_3$).

    Optimal strategies (pure):

    • Player A: $A_1$
    • Player B: $B_3$

    (b) Value of the Game

    Since Maximin = Minimax = 20, the game has a saddle point and the value is:

    $$V = 20$$

    Summary

    ItemResult
    Player A's optimal strategy$A_1$
    Player B's optimal strategy$B_3$
    Value of the game$20$

    The game is strictly determinable with a pure-strategy saddle point.

  7. 75 marksNumericalCritical path identificationAnswer

    Project Network Analysis

    The table gives the information about the activities, their predecessors and time duration required to complete the activities of the project. Find the shortest time duration of the project within which the project can be completed.

    ActivityABCDEFG
    Predecessor--BBBEA,D,C
    Time (in days)1881414161020

    [5]

    Activity Predecessor Duration (days) ---------------------------------------- A - 18 B - 8 C B 14 D B 14 E B 16 F E 10 G A, D, C 20 $EF = ES + \text{Duration}$, and $ES = \max(EF \text{ of predecessors})$ Activity Predecessor ES EF -----...

  8. 85 marksNumericalFormulation of linear programming problemsAnswer

    The TechZone Software Company combines two key resources - Front-End Developers (A) and Back-End Developers (B) - to complete a software system that must involve exactly 150 person-hours of total work. Each Front-End Developer hour costs Rs. 2,000, and each Back-End Developer hour costs Rs. 8,000. The company must use at least 14 hours of Back-End work and no more than 20 hours of Front-End work in a project. Formulate objective function and constraints of this LPP. [5]

    STEP 1 - Given Data

    Decision variables:

    • $A$ = number of Front-End Developer hours
    • $B$ = number of Back-End Developer hours

    Numeric inputs:

    • Total work required: exactly 150 person-hours
    • Cost per Front-End hour: Rs. 2,000
    • Cost per Back-End hour: Rs. 8,000
    • Minimum Back-End work: at least 14 hours
    • Maximum Front-End work: no more than 20 hours

    STEP 2 - Formulation

    Objective Function

    Since costs are involved and the goal is efficiency, the company seeks to minimize total cost:

    $$\text{Minimize } Z = 2000A + 8000B$$

    where:

    • $2000A$ = total cost of Front-End Developer hours
    • $8000B$ = total cost of Back-End Developer hours

    Constraints

    1. Total work requirement (exactly 150 person-hours): $$A + B = 150$$

    2. Minimum Back-End Developer hours (at least 14): $$B \geq 14$$

    3. Maximum Front-End Developer hours (no more than 20): $$A \leq 20$$

    4. Non-negativity: $$A \geq 0, \quad B \geq 0$$


    Complete LPP Formulation

    $$\boxed{\text{Minimize } Z = 2000A + 8000B}$$

    Subject to: $$A + B = 150$$ $$B \geq 14$$ $$A \leq 20$$ $$A, B \geq 0$$

    Feasibility note: With $A \leq 20$ and $A + B = 150$, we get $B = 150 - A \geq 130$, which automatically satisfies $B \geq 14$. So the binding constraint on cost is $A \leq 20$. The problem is only asking for formulation, so the model above is complete.

  9. 95 marksModified DistributionAnswer

    Describe modified distribution (MODI) method of obtaining the optimal solution of transportation problem. [5]

    The MODI method (also called the Multiplier method or u-v method) is an iterative technique used to find the optimal solution to a transportation problem after an initial basic feasible solution has been obtained. The MODI method works b...

  10. 105 marksOperating characteristics of queuing systeAnswer

    Describe different operation characteristics of single channel queuing model. [5]

    A single channel queuing model (M/M/1) consists of one server serving customers arriving from a single queue. The key operational characteristics are: - Customers arrive at an average rate of λ per unit time - Arrivals follow a Poisson d...

  11. 115 marksDominance rule methodAnswer

    Describe the dominance rule of solving game theory problem. [5]

    The dominance rule (or principle of dominance) is a method used to simplify and solve game theory problems by eliminating strategies that are clearly inferior for a player, regardless of what the opponent does. A strategy is said to be d...

  12. 125 marksVogel's Approximation MethodAnswer

    Write short notes on: (a) Vogel's Approximation Method (VAM) (b) Objectives of operations research [0+2.5+2.5]

    Model Answer: Vogel's Approximation Method & Objectives of Operations Research

    (a) Vogel's Approximation Method (VAM)

    Definition: Vogel's Approximation Method is an improved initial solution technique for the Transportation Problem that generally produces a better starting solution than the North-West Corner Method or Least Cost Method.

    Principle: VAM is based on the concept of "penalty" or "regret." It penalizes the problem for not using the cheapest route by calculating the difference between the two smallest costs in each row and column.

    Algorithm Steps:

    1. Calculate penalties for each row and column:

      • Penalty = (Second minimum cost - Minimum cost) in that row/column
    2. Select the row or column with maximum penalty

    3. Allocate maximum possible quantity to the cell with minimum cost in the selected row/column

    4. Delete the exhausted row or column

    5. Repeat steps 1-4 until all supplies and demands are satisfied

    Advantages:

    • Produces near-optimal or optimal initial solution
    • Reduces number of iterations needed to reach final solution
    • More efficient than North-West Corner Method
    • Minimizes total transportation cost

    (b) Objectives of Operations Research

    Primary Objectives:

    1. Optimization:

      • Maximize profit, efficiency, or output
      • Minimize cost, time, or resource wastage
      • Find the best possible solution within given constraints
    2. Decision Making:

      • Provide quantitative basis for managerial decisions
      • Support rational, data-driven choices
      • Reduce uncertainty in complex problems
    3. Resource Allocation:

      • Allocate limited resources optimally among competing activities
      • Ensure efficient utilization of men, money, materials, and machines
    4. Problem Solving:

      • Identify and analyze complex organizational problems
      • Develop systematic solutions using mathematical models
    5. Planning and Control:

      • Assist in strategic planning and forecasting
      • Monitor and control operations effectively

    Overall Goal: To provide management with scientific, quantitative tools for making better decisions and improving organizational performance.