CSC326 · 2076 · 10 marks
What is the waterfall model? Explain the prototyping model for developing information systems along with merits and demerits.
What is the waterfall model? Explain the prototyping model for developing information systems along with merits and demerits.[10]
Quick answer
The Waterfall Model is a linear, sequential approach to software/information system development where each phase must be completed before the next phase begins. It follows a strict top-down approach, resembling a waterfall flowing downward. It was one of the earliest SDLC models, proposed by Winston W. Royce in 1970.
Waterfall Model and Prototyping Model
Waterfall Model
Phases of the Waterfall Model:
| Phase | Description |
|---|---|
| 1. Requirements Gathering | All system requirements are collected and documented |
| 2. System Analysis | Requirements are analyzed for feasibility and clarity |
| 3. System Design | Architecture and system specifications are designed |
| 4. Implementation (Coding) | The actual system is developed/coded |
| 5. Testing | The system is verified and validated |
| 6. Deployment and Maintenance | The system is delivered and maintained |
Each phase acts as an input to the next phase, and once a phase is completed, it is assumed to be final. There is no going back to a previous phase.
Prototyping Model
Prototyping is a form of Rapid Application Development (RAD). Instead of spending a lot of time producing very detailed specifications, the developers find out only generally what the users want. The developers do not develop the complete system all at once. Instead, they quickly create a prototype, which either contains portions of the system or is a small-scale working model of the entire system. After reviewing the prototype with the users, the developers refine and extend it. This process is continued until the final specifications are met.
A prototype is a preliminary working model of the system that demonstrates the functionality but may not contain exact logic or complete features.
Steps in the Prototyping Model:
Step 1: Requirement Gathering
- Basic and initial requirements are identified from the user.
- Developers find out generally what the users want without going into full detail.
Step 2: Quick Design
- When requirements are known, a quick design for the system is created.
- It is not a detailed design and includes only the important aspects of the system.
Step 3: Build Prototype
- Information gathered from the quick design is used to form the first prototype.
- This prototype represents the working model of the required system.
Step 4: User Evaluation
- The proposed prototype is presented to the user.
- The user recognizes its strengths and weaknesses, such as what is to be added or removed.
Step 5: Refine Prototype
- If the user is not satisfied with the prototype, the current prototype is refined with the additional information provided by the user.
- The cycle of build → evaluate → refine continues iteratively.
Step 6: Engineer Final Product
- Once the requirements are completely met, the user accepts the final prototype.
- The final system is then followed by routine maintenance on a regular basis to prevent large-scale failures and minimize downtime.
Diagram of Prototyping Model:
Requirement Gathering
↓
Quick Design
↓
Build Prototype
↓
User Evaluation ←─────────────┐
↓ │
Satisfied? ──── No ──→ Refine Prototype
│
Yes
↓
Engineer Final Product
↓
Maintenance
Merits of the Prototyping Model
- Active User Involvement -- Users participate throughout the development process, leading to better understanding of requirements.
- Reduced Risk of Failure -- Errors and misunderstandings are detected early through continuous user feedback.
- Better Requirement Clarity -- Helps identify missing or unclear requirements at an early stage.
- Improved Communication -- The prototype serves as a visual and working tool for discussion between users and developers.
- Faster Initial Delivery -- Users can see a working model quickly, which increases confidence and satisfaction.
- Flexibility -- Changes can be easily incorporated at early stages before full development begins.
Demerits of the Prototyping Model
- Increased Cost -- Multiple iterations of building and refining prototypes can be expensive and resource-intensive.
- Time-Consuming -- Continuous user feedback and revisions may delay the overall project completion.
- Scope Creep -- Users may keep requesting changes endlessly, expanding the project scope beyond original plans.
- Poor Documentation -- Focus on rapid prototyping may lead to inadequate or incomplete documentation.
- User Confusion -- Users may mistake the prototype for the final system, leading to unrealistic expectations.
- Quality Compromise -- Developers may use shortcuts in the prototype that inadvertently carry over to the final system.
Conclusion
The Waterfall Model is best suited for projects with well-defined and stable requirements, where each phase can be completed sequentially without revisiting. The Prototyping Model, on the other hand, is ideal when requirements are unclear or likely to change, as it allows iterative refinement through active user participation and rapid model building. Both models are important SDLC approaches used in information systems development depending on the nature and complexity of the project.