CSC326 ยท 2080 ยท 5 marks
Define feasibility study. Explain economic and schedule feasibility in brief.
Define feasibility study. Explain economic and schedule feasibility in brief. [5]
Quick answer
A feasibility study is an analysis that considers all of a project's relevant factors -- including economic, technical, legal, and scheduling considerations -- to ascertain the likelihood of completing the project successfully. Whether a project is feasible or not can depend on several factors, including the project's cost and return on investment.
Feasibility Study: Definition and Types
Definition of Feasibility Study
The primary purpose of a feasibility study is to reduce the number of business options and determine whether a proposed project should be pursued, redirected, or abandoned.
Types of Feasibility (Economic and Schedule)
1. Economic Feasibility (Cost-Benefit Analysis)
Economic feasibility is the analysis of a system to determine whether the expected benefits equal or exceed the expected costs.
Key points:
- The main purpose is to identify the financial benefits and costs associated with the development project.
- During project initiation and planning, it may be impossible to define precisely all benefits and costs related to a particular project.
- Worksheets are used to record costs and benefits, and these worksheets are reviewed after each SDLC phase to decide whether to:
- Continue the project
- Redirect the project
- Kill the project
Example considerations:
| Costs | Benefits |
|---|---|
| Development cost | Increased revenue |
| Hardware/software cost | Reduced operational cost |
| Maintenance cost | Improved efficiency |
2. Schedule Feasibility
Schedule feasibility determines whether the project can be completed within the given time frame and deadlines set by the organization.
Key points:
- It evaluates whether the project timeline is realistic and achievable given the available resources.
- It considers the project size, complexity, and team capacity when estimating time requirements.
- If a project cannot be delivered on time, it may lose its business value even if technically and economically sound.
- Schedule feasibility is closely linked to project planning, where the project manager creates a blueprint mapping out estimated time and execution plan.
Factors affecting schedule feasibility:
- Size and complexity of the project
- Availability of skilled personnel
- Dependencies between project tasks
- Risk factors that may cause delays
Summary
| Feasibility Type | Focus |
|---|---|
| Economic | Cost vs. benefit analysis |
| Schedule | Completion within time constraints |
Both economic and schedule feasibility are critical during the initiation phase of a project to ensure resources are wisely invested and deadlines are realistically met.