Define feasibility study. Explain economic and schedule feasibility in brief.

Define feasibility study. Explain economic and schedule feasibility in brief. [5]

System Analysis and DesignChapter 2: PlanningProcess of Initiating and Planning IS Development Projects,

Quick answer

A feasibility study is an analysis that considers all of a project's relevant factors -- including economic, technical, legal, and scheduling considerations -- to ascertain the likelihood of completing the project successfully. Whether a project is feasible or not can depend on several factors, including the project's cost and return on investment.

Feasibility Study: Definition and Types

Definition of Feasibility Study

The primary purpose of a feasibility study is to reduce the number of business options and determine whether a proposed project should be pursued, redirected, or abandoned.


Types of Feasibility (Economic and Schedule)

1. Economic Feasibility (Cost-Benefit Analysis)

Economic feasibility is the analysis of a system to determine whether the expected benefits equal or exceed the expected costs.

Key points:

  • The main purpose is to identify the financial benefits and costs associated with the development project.
  • During project initiation and planning, it may be impossible to define precisely all benefits and costs related to a particular project.
  • Worksheets are used to record costs and benefits, and these worksheets are reviewed after each SDLC phase to decide whether to:
    • Continue the project
    • Redirect the project
    • Kill the project

Example considerations:

CostsBenefits
Development costIncreased revenue
Hardware/software costReduced operational cost
Maintenance costImproved efficiency

2. Schedule Feasibility

Schedule feasibility determines whether the project can be completed within the given time frame and deadlines set by the organization.

Key points:

  • It evaluates whether the project timeline is realistic and achievable given the available resources.
  • It considers the project size, complexity, and team capacity when estimating time requirements.
  • If a project cannot be delivered on time, it may lose its business value even if technically and economically sound.
  • Schedule feasibility is closely linked to project planning, where the project manager creates a blueprint mapping out estimated time and execution plan.

Factors affecting schedule feasibility:

  • Size and complexity of the project
  • Availability of skilled personnel
  • Dependencies between project tasks
  • Risk factors that may cause delays

Summary

Feasibility TypeFocus
EconomicCost vs. benefit analysis
ScheduleCompletion within time constraints

Both economic and schedule feasibility are critical during the initiation phase of a project to ensure resources are wisely invested and deadlines are realistically met.