CSC326 · 2082 · 10 marks

List different phases of project management. Explain the different steps involved in the first phase of project management.

List different phases of project management. Explain the different steps involved in the first phase of project management.[10]

System Analysis and DesignChapter 1: Foundations for Systems DevelopmentManaging the Information Systems Project

Quick answer

Project Management is the process of planning, organizing, directing, and controlling resources (people, equipment, and materials) to meet the technical, cost, and time constraints of a project.

Phases of Project Management and Steps in the First Phase

Definition


Different Phases of Project Management

The project management process consists of the following phases:

PhaseName
Phase 1Initiating (Project Conceptualization and Planning)
Phase 2Planning (Blueprint and Schedule Development)
Phase 3Executing (Implementation)
Phase 4Monitoring and Control (Tracking Progress)
Phase 5Closure/Termination (Delivery and Review)

Steps Involved in the First Phase: Initiating / Project Planning

The first phase is the most critical phase where the foundation of the entire project is laid. During this phase, the project is conceptualized and feasibility is determined. The following steps are involved:


Step 1: Defining the Project Goal and Scope

  • Clearly identify what the project will deliver
  • Define the boundaries of the project (what is included and what is not)
  • A scope statement is prepared which is a list of project objectives and deliverables
  • Set measurable goals and success criteria
  • This step answers the question: "What are we building and why?"

Step 2: Identifying the Project Manager and Team

  • A suitable project manager is identified who will be responsible for the entire project
  • Key stakeholders and team members are identified
  • Roles and responsibilities are assigned to team members
  • The right personnel with required skills are selected

Step 3: Feasibility Analysis

Feasibility analysis determines whether the project is worth pursuing. It reduces the number of business options. The three main types are:

a) Economic Feasibility (Cost-Benefit Analysis)

  • Analyzes whether the expected benefits equal or exceed the expected costs
  • Identifies financial benefits and costs associated with the development project
  • Review worksheets are used to record costs and benefits
  • These worksheets are used after each phase to decide whether to continue, redirect, or kill the project

b) Technical Feasibility

  • Evaluates whether the new system will perform adequately
  • Assesses whether the organization has the ability to construct the proposed system
  • The amount of technical risk depends on four primary factors:
    • Project size
    • Project structure
    • Development group's experience with the application and technology area
    • User group's experience with systems development

c) Operational Feasibility

  • Assesses whether the proposed system will likely solve the business problems or take advantage of opportunities
  • Evaluates how the new system will fit into the existing organizational environment

Step 4: Identifying Potential Risks

  • Identify potential risks that may affect the project as early as possible
  • Assess their probability and impact
  • Organizations typically expect a greater return on investment for riskier projects
  • Develop mitigation and contingency plans to handle identified risks

Step 5: Project Identification and Selection

  • Classifying and ranking projects can be performed by top managers, a steering committee, business units, or the IS development group
  • Criteria used to assign merit to a project include: cost, duration, complexity, system size, and focus
  • An important evaluation method is Value Chain Analysis
  • Factors considered during selection include:
    • Existing systems and ongoing projects
    • Resource availability
    • Evaluation criteria
    • Current business conditions
    • Perspectives of decision makers

Step 6: Setting the Project Baseline

  • Determine the scope of the project using a scope statement
  • Break down all work required into individual tasks and subtasks with detailed descriptions
  • Map out the project schedule with clearly defined due dates and a final deadline
    • A Gantt chart is a good tool for this purpose
  • Plan the total cost of the project including hourly rates, available resources, etc.
  • The project baseline must be clearly outlined before moving to the next stage

Step 7: Creating the Project Plan Document

  • Document all the above information into a formal Software Project Plan (SPP)
  • The primary deliverable from this phase is a schedule of specific IS development projects
  • Acts as a reference guide throughout the project lifecycle
  • Provides assurance that people gave careful consideration to project selection

Incremental Commitment

An important concept in the first phase is incremental commitment, which is a strategy in which the project is reviewed in system analysis and design, and the project is rejustified in each of these reviews. This ensures that only viable projects continue forward.


Conclusion

The first phase (Initiating/Planning) is the most important phase as all other phases depend on it. A well-planned project has higher chances of being delivered on time, within budget, and with expected quality. Poor planning leads to project failure, cost overruns, and missed deadlines. The feasibility analysis conducted during this phase ensures that only projects with genuine business value and technical viability are pursued.