Software Project Management · Unit 6
Risk Management
Exam-focused notes for Risk Management (Software Project Management, BIT402): what the TU syllabus asks and how it has actually been tested, with 4 solved past questions from this unit.
Risk Management in short
A risk is something that might go wrong and harm the project. Risk management finds these problems early, judges how serious they are and decides what to do about them.
What this unit covers
- Risk categories and classification
- Risk items and identification
- Risk assessment process
- Risk exposure value
- Risk handling approaches
Risk categories and classification
2082 · 10 marks
What are different categories of risk? Explain.[10]
Show solved answerHide answer
Model Answer: Categories of Risk
Introduction
Risk in project management and business contexts can be categorized in several ways.
Main Categories of Risk
1. Technical Risk
Technical risks arise from uncertainties in technology, tools, and development approaches:
- Unfamiliar or unproven technologies
- Integration challenges between systems
- Performance and scalability issues
- Obsolescence of technology during project lifecycle
- Lack of technical expertise in the team
2. Schedule Risk
These risks relate to project timeline and deadlines:
- Unrealistic time estimates
- Resource unavailability
- Dependency delays
- Scope creep extending timelines
- Unexpected technical complications
3. Resource Risk
Risks associated with human and material resources:
- Key personnel turnover or unavailability
- Insufficient skilled staff
- Budget constraints
- Equipment or infrastructure limitations
- Training and learning curve requirements
4. Organizational Risk
Risks stemming from organizational structure and management:
- Poor communication channels
- Unclear project objectives
- Inadequate management support
- Organizational restructuring
- Conflicting priorities
5. External Risk
Risks from factors outside project control:
- Market changes and competition
- Regulatory and compliance changes
- Natural disasters or force majeure
- Vendor or supplier failures
- Economic fluctuations
6. Operational Risk
Risks in day-to-day project operations:
- Process inefficiencies
- Quality assurance failures
- Security vulnerabilities
- Data loss or corruption
- Inadequate testing procedures
Conclusion
Effective risk management requires identifying and categorizing risks appropriately, then developing mitigation strategies for each category to ensure project success.
Risk assessment process
2081 · 5 marks
How risk assessment is carried out? Explain with an example. [5]
Risk handling approaches
2080 · 5 marks
Explain different approaches that can be used to handle risk. [5]
Risk exposure value
0 · 5 marks
List different risk items. How can the risk exposure value help in handling risk? [5]