6 Risk Management

Software Project Management · Unit 6

Risk Management

Exam-focused notes for Risk Management (Software Project Management, BIT402): what the TU syllabus asks and how it has actually been tested, with 4 solved past questions from this unit.

Risk Management in short

A risk is something that might go wrong and harm the project. Risk management finds these problems early, judges how serious they are and decides what to do about them.

Risk Management: notes

Risk categories and classification

A risk is an uncertain event that, if it happens, has a bad effect on cost, time, scope or quality. It is different from a problem, which has already happened.

Risks can be classified in several ways.

By source:

  • Project risks threaten the schedule and resources: staff turnover, budget cuts, late delivery by a supplier.
  • Product (technical) risks threaten quality or performance: unclear requirements, new technology, poor design.
  • Business risks threaten the value of the product: a rival product, loss of market, a change in company policy.

By knowledge:

  • Known risks can be found by careful study.
  • Predictable risks come from past experience, such as low staff morale.
  • Unpredictable risks are very hard to foresee.

By area of the project:

  • Management risks: poor planning, unrealistic schedules.
  • Technical risks: complexity, performance limits.
  • People risks: lack of skill, conflict, key people leaving.
  • External risks: law changes, supplier failure, natural events.

Risk items and identification

Risk identification means making a list of the risks that may affect the project. Common ways are:

  • Checklists of risks seen in past projects.
  • Brainstorming with the team and stakeholders.
  • Expert interviews and the Delphi technique.
  • Review of past project records and lessons learned.
  • Assumption analysis to see which assumptions may be false.
  • SWOT analysis of the project.

Boehm's list of the top software risk items is widely used:

  1. Personnel shortfalls.
  2. Unrealistic schedules and budgets.
  3. Developing the wrong software functions.
  4. Developing the wrong user interface.
  5. Gold plating (adding features that are not needed).
  6. A continuing stream of requirement changes.
  7. Shortfalls in externally furnished components.
  8. Shortfalls in externally performed tasks.
  9. Real-time performance shortfalls.
  10. Straining computer science capabilities.

The result is a risk register listing each risk, its cause, owner and status.

What this unit covers

  • Risk categories and classification
  • Risk items and identification
  • Risk assessment process
  • Risk exposure value
  • Risk handling approaches

Risk categories and classification

2082 · 10 marks

What are different categories of risk? Explain.[10]

Show solved answer

Model Answer: Categories of Risk

Introduction

Risk in project management and business contexts can be categorized in several ways.

Main Categories of Risk

1. Technical Risk

Technical risks arise from uncertainties in technology, tools, and development approaches:

  • Unfamiliar or unproven technologies
  • Integration challenges between systems
  • Performance and scalability issues
  • Obsolescence of technology during project lifecycle
  • Lack of technical expertise in the team

2. Schedule Risk

These risks relate to project timeline and deadlines:

  • Unrealistic time estimates
  • Resource unavailability
  • Dependency delays
  • Scope creep extending timelines
  • Unexpected technical complications

3. Resource Risk

Risks associated with human and material resources:

  • Key personnel turnover or unavailability
  • Insufficient skilled staff
  • Budget constraints
  • Equipment or infrastructure limitations
  • Training and learning curve requirements

4. Organizational Risk

Risks stemming from organizational structure and management:

  • Poor communication channels
  • Unclear project objectives
  • Inadequate management support
  • Organizational restructuring
  • Conflicting priorities

5. External Risk

Risks from factors outside project control:

  • Market changes and competition
  • Regulatory and compliance changes
  • Natural disasters or force majeure
  • Vendor or supplier failures
  • Economic fluctuations

6. Operational Risk

Risks in day-to-day project operations:

  • Process inefficiencies
  • Quality assurance failures
  • Security vulnerabilities
  • Data loss or corruption
  • Inadequate testing procedures

Conclusion

Effective risk management requires identifying and categorizing risks appropriately, then developing mitigation strategies for each category to ensure project success.

Open this answer on its own page →

Risk assessment process

2081 · 5 marks

How risk assessment is carried out? Explain with an example. [5]

Risk assessment is a systematic process to identify, analyze, and evaluate potential risks that could affect a project or system. The process typically follows these steps: - Identify all potential risks that could occur during the project lifecycle - Use techniques like brainstorming, checklists...

Open this answer on its own page →

Risk handling approaches

2080 · 5 marks

Explain different approaches that can be used to handle risk. [5]

Risk handling (or risk response) involves taking action to address identified risks. The main approaches are: - Eliminate the risk by avoiding the activity or condition that causes it - Change project scope, requirements, or approach to remove the risk entirely - Example: Avoiding use of an unpro...

Open this answer on its own page →

Risk exposure value

0 · 5 marks

List different risk items. How can the risk exposure value help in handling risk? [5]

Risk items in software project management can be categorized as follows: - Inadequate technology or tools - Unproven or unfamiliar technology - Technical complexity and scalability issues - Integration challenges between components - Performance and reliability concerns - Unrealistic project time...