2 Project Planning And Scheduling

Software Project Management ยท Unit 2

Project Planning and Scheduling

Exam-focused notes for Project Planning and Scheduling (Software Project Management, BIT402): what the TU syllabus asks and how it has actually been tested, with 6 solved past questions from this unit.

Project Planning and Scheduling in short

Planning and scheduling decide what work is needed, in what order, and who does it and when. A good schedule shows the shortest possible project time and the activities that must not slip.

Project Planning and Scheduling: notes

Project planning process

Planning turns the project goal into a set of activities that can be carried out and checked. The usual process is:

  • Define the scope and objectives, and list the deliverables.
  • Identify the activities needed to produce each deliverable (a work breakdown).
  • Work out the dependencies: which activity must finish before another starts.
  • Estimate the effort and duration of each activity.
  • Identify and allocate resources such as people, tools and machines.
  • Analyse risks and add time or actions to deal with them.
  • Draw the network and find the critical path.
  • Produce the schedule, review it with stakeholders and approve it.
  • Plan how progress will be monitored and how changes will be handled.

A plan is not fixed for ever. It is reviewed and updated as real progress becomes known. Planning in detail is done only for the near future, and later parts are kept outline until more is known.

Activity-on-arrow network diagrams

A network diagram shows activities and their order. In an activity-on-arrow (AOA) diagram, each activity is drawn as an arrow. The circles are events (nodes) that mark the start or finish of activities.

Rules:

  • There is one start event and one end event.
  • Each activity is one arrow, with its name and duration written on it.
  • An activity cannot start until its start event has happened, so all earlier activities must be done.
  • Two activities cannot share both the same start and end event.
  • A dummy activity (dashed arrow, zero duration) shows a dependency or keeps two activities separate.
  • The diagram must have no loops.

Example: A takes 2 weeks and has no predecessor. B (3 weeks) and C (4 weeks) both follow A. D (5 weeks) needs both B and C. E (2 weeks) follows D.

        B(3)
     /--------\
(1)-A(2)->(2)   (3)-D(5)->(4)-E(2)->(5)
     \- C(4) -/

Here B and C would both run from event 2 to event 3. A dummy arrow is placed so they have different end events. Event 3 is then reached when both B and C are done.

What this unit covers

  • Project planning process
  • Activity-on-arrow network diagrams
  • Critical path and critical activities
  • Stages of creating project schedule
  • Timeline charts and slip charts
  • Resource histograms and equalization

Stages of creating project schedule

2082 ยท 5 marks

Explain different stages of creating project schedule. [5]

Since reference notes are not provided, this answer is based on standard project management practice aligned with typical BSc CSIT curriculum: - Break down the project into individual tasks/activities - Identify all work that must be completed - Document activity descriptions clearly - Ensure act...

Open this answer on its own page โ†’

Resource histograms and equalization

2082 ยท 5 marks

Why do you think resource histogram equalization is necessary? Explain with example. [5]

Resource histogram equalization is necessary for the following reasons: Resource histograms reveal periods where resource demand exceeds availability. Equalization helps identify these critical bottlenecks early in project planning, allowing managers to take corrective action before problems occu...

Open this answer on its own page โ†’

2081 ยท 5 marks

What is resource histogram equalization? Why is it carried out? [5]

Show solved answer

Resource Histogram Equalization

Definition

Resource histogram equalization is a technique used in project scheduling and resource management to level or balance the allocation of resources (labour, equipment, materials) across the project timeline. It involves adjusting the project schedule to reduce resource peaks and valleys, creating a more uniform distribution of resource usage over time.

Why It Is Carried Out

Resource histogram equalization is performed for the following reasons:

1. Minimize Resource Conflicts

  • Prevents excessive demand for the same resource at the same time
  • Reduces competition for limited resources among different project activities

2. Optimize Resource Utilization

  • Ensures efficient and consistent use of available resources
  • Reduces idle time and underutilization of resources
  • Improves overall productivity

3. Cost Reduction

  • Avoids the need to hire temporary or contract resources during peak periods
  • Reduces overtime costs and premium payments
  • Lowers resource procurement and management costs

4. Improve Project Feasibility

  • Makes the project schedule realistic given actual resource constraints
  • Prevents resource overallocation that could cause project delays
  • Ensures resource availability matches project demands

5. Better Resource Planning

  • Provides a smoother, more predictable resource demand pattern
  • Facilitates better workforce planning and scheduling
  • Enables more accurate budgeting and resource forecasting

6. Reduce Project Duration Risk

  • Prevents bottlenecks caused by resource unavailability
  • Maintains consistent progress throughout the project

In essence, resource histogram equalization transforms an uneven resource demand pattern into a balanced one, making projects more manageable, cost-effective, and achievable within constraints.

Open this answer on its own page โ†’

Project planning process

2081 ยท 5 marks

Write short notes on a. Product based approach b. Project planning [5]

Definition: The product-based approach is a software development methodology that focuses on creating reusable software products or components that can be applied across multiple projects and domains. Key Characteristics: - Reusability: Components and modules are designed to be generic and reusab...

Open this answer on its own page โ†’

Critical path and critical activities

2080 ยท 10 marks

Draw activity-on-arrow diagram for the above scenario and find the critical path.

Project ActivitiesDuration (Week)Precedence
A2
B3A
C4A
D5B, C
E2D

[10]

Show solved answer

Activity-on-Arrow (AOA) Diagram and Critical Path

Given

ActivityDuration (weeks)Predecessor
A2-
B3A
C4A
D5B, C
E2D

Step 2: Build the AOA Network

Nodes (events) are numbered; arrows are activities.

  • Node 1: Start
  • A runs from Node 1 โ†’ Node 2
  • After A, both B and C start from Node 2
  • B and C both must finish before D. So B: 2 โ†’ 3 and C: 2 โ†’ 3 (both merge at Node 3)
  • D runs from Node 3 โ†’ Node 4
  • E runs from Node 4 โ†’ Node 5 (End)
            B(3)
        โ”Œโ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”
        โ†“          โ”‚
(1)โ”€โ”€A(2)โ”€โ”€โ–บ(2)     โ”œโ”€โ”€โ–บ(3)โ”€โ”€D(5)โ”€โ”€โ–บ(4)โ”€โ”€E(2)โ”€โ”€โ–บ(5)
        โ”‚          โ†‘
        โ””โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”˜
            C(4)

Since B and C share the same start (Node 2) and end (Node 3), a dummy activity is technically required to keep unique identification in strict AOA notation:

(1) --A(2)--> (2) --B(3)--> (3)
                 \          ^
                  C(4)      | dummy(0)
                   \        |
                    v       |
                    (3')----+
                    |
                    D(5)
                    v
                   (4) --E(2)--> (5)

For simplicity the merge is shown at Node 3.

Step 3: Forward Pass (ES, EF)

$EF = ES + \text{Duration}$

ActivityDurationESEF
A202
B325
C426
D5$\max(5,6)=6$11
E21113

Project duration (EF of E) = 13 weeks

Step 4: Backward Pass (LF, LS)

$LS = LF - \text{Duration}$, starting from $LF_E = 13$

ActivityDurationLFLS
E21311
D5116
B363
C462
A220

Step 5: Slack / Float

$\text{Slack} = LS - ES$

ActivityESLSSlackCritical?
A000Yes
B231No
C220Yes
D660Yes
E11110Yes

Step 6: Critical Path

Activities with zero slack: A, C, D, E

$$\boxed{\text{Critical Path: } A \to C \to D \to E}$$

Total Project Duration $= 2 + 4 + 5 + 2 = 13$ weeks

Any delay in A, C, D, or E delays the whole project. Activity B has 1 week of float.

Open this answer on its own page โ†’

0 ยท 10 marks

What is critical activity and critical path? Explain network diagram with a suitable example.[10]

A critical activity is an activity in a project network where any delay in its execution will directly delay the completion of the entire project. In other words, a critical activity has zero slack or float time. Key characteristics: - Has no buffer time - Any delay in this activity causes projec...

Open this answer on its own page โ†’