Software Project Management ยท Unit 2
Project Planning and Scheduling
Exam-focused notes for Project Planning and Scheduling (Software Project Management, BIT402): what the TU syllabus asks and how it has actually been tested, with 6 solved past questions from this unit.
Project Planning and Scheduling in short
Planning and scheduling decide what work is needed, in what order, and who does it and when. A good schedule shows the shortest possible project time and the activities that must not slip.
What this unit covers
- Project planning process
- Activity-on-arrow network diagrams
- Critical path and critical activities
- Stages of creating project schedule
- Timeline charts and slip charts
- Resource histograms and equalization
Stages of creating project schedule
2082 ยท 5 marks
Explain different stages of creating project schedule. [5]
Resource histograms and equalization
2082 ยท 5 marks
Why do you think resource histogram equalization is necessary? Explain with example. [5]
2081 ยท 5 marks
What is resource histogram equalization? Why is it carried out? [5]
Show solved answerHide answer
Resource Histogram Equalization
Definition
Resource histogram equalization is a technique used in project scheduling and resource management to level or balance the allocation of resources (labour, equipment, materials) across the project timeline. It involves adjusting the project schedule to reduce resource peaks and valleys, creating a more uniform distribution of resource usage over time.
Why It Is Carried Out
Resource histogram equalization is performed for the following reasons:
1. Minimize Resource Conflicts
- Prevents excessive demand for the same resource at the same time
- Reduces competition for limited resources among different project activities
2. Optimize Resource Utilization
- Ensures efficient and consistent use of available resources
- Reduces idle time and underutilization of resources
- Improves overall productivity
3. Cost Reduction
- Avoids the need to hire temporary or contract resources during peak periods
- Reduces overtime costs and premium payments
- Lowers resource procurement and management costs
4. Improve Project Feasibility
- Makes the project schedule realistic given actual resource constraints
- Prevents resource overallocation that could cause project delays
- Ensures resource availability matches project demands
5. Better Resource Planning
- Provides a smoother, more predictable resource demand pattern
- Facilitates better workforce planning and scheduling
- Enables more accurate budgeting and resource forecasting
6. Reduce Project Duration Risk
- Prevents bottlenecks caused by resource unavailability
- Maintains consistent progress throughout the project
In essence, resource histogram equalization transforms an uneven resource demand pattern into a balanced one, making projects more manageable, cost-effective, and achievable within constraints.
Project planning process
2081 ยท 5 marks
Write short notes on a. Product based approach b. Project planning [5]
Critical path and critical activities
2080 ยท 10 marks
Draw activity-on-arrow diagram for the above scenario and find the critical path.
| Project Activities | Duration (Week) | Precedence |
|---|---|---|
| A | 2 | |
| B | 3 | A |
| C | 4 | A |
| D | 5 | B, C |
| E | 2 | D |
[10]
Show solved answerHide answer
Activity-on-Arrow (AOA) Diagram and Critical Path
Given
| Activity | Duration (weeks) | Predecessor |
|---|---|---|
| A | 2 | - |
| B | 3 | A |
| C | 4 | A |
| D | 5 | B, C |
| E | 2 | D |
Step 2: Build the AOA Network
Nodes (events) are numbered; arrows are activities.
- Node 1: Start
- A runs from Node 1 โ Node 2
- After A, both B and C start from Node 2
- B and C both must finish before D. So B: 2 โ 3 and C: 2 โ 3 (both merge at Node 3)
- D runs from Node 3 โ Node 4
- E runs from Node 4 โ Node 5 (End)
B(3)
โโโโโโโโโโโโ
โ โ
(1)โโA(2)โโโบ(2) โโโโบ(3)โโD(5)โโโบ(4)โโE(2)โโโบ(5)
โ โ
โโโโโโโโโโโโ
C(4)
Since B and C share the same start (Node 2) and end (Node 3), a dummy activity is technically required to keep unique identification in strict AOA notation:
(1) --A(2)--> (2) --B(3)--> (3)
\ ^
C(4) | dummy(0)
\ |
v |
(3')----+
|
D(5)
v
(4) --E(2)--> (5)
For simplicity the merge is shown at Node 3.
Step 3: Forward Pass (ES, EF)
$EF = ES + \text{Duration}$
| Activity | Duration | ES | EF |
|---|---|---|---|
| A | 2 | 0 | 2 |
| B | 3 | 2 | 5 |
| C | 4 | 2 | 6 |
| D | 5 | $\max(5,6)=6$ | 11 |
| E | 2 | 11 | 13 |
Project duration (EF of E) = 13 weeks
Step 4: Backward Pass (LF, LS)
$LS = LF - \text{Duration}$, starting from $LF_E = 13$
| Activity | Duration | LF | LS |
|---|---|---|---|
| E | 2 | 13 | 11 |
| D | 5 | 11 | 6 |
| B | 3 | 6 | 3 |
| C | 4 | 6 | 2 |
| A | 2 | 2 | 0 |
Step 5: Slack / Float
$\text{Slack} = LS - ES$
| Activity | ES | LS | Slack | Critical? |
|---|---|---|---|---|
| A | 0 | 0 | 0 | Yes |
| B | 2 | 3 | 1 | No |
| C | 2 | 2 | 0 | Yes |
| D | 6 | 6 | 0 | Yes |
| E | 11 | 11 | 0 | Yes |
Step 6: Critical Path
Activities with zero slack: A, C, D, E
$$\boxed{\text{Critical Path: } A \to C \to D \to E}$$
Total Project Duration $= 2 + 4 + 5 + 2 = 13$ weeks
Any delay in A, C, D, or E delays the whole project. Activity B has 1 week of float.
0 ยท 10 marks
What is critical activity and critical path? Explain network diagram with a suitable example.[10]