2 Planning

System Analysis and Design · Unit 2 · 5 hrs

Planning

Exam-focused notes for Planning (System Analysis and Design, CSC326): what the TU syllabus asks and how it has actually been tested, with 12 solved past questions from this unit.

Planning in short

This chapter covers the planning phase of the SDLC: how candidate projects are found and chosen, how that choice fits into the organisation's wider strategic and information systems planning, how a selected project is initiated and its feasibility assessed with real numbers, and how the resulting baseline plan is built and reviewed.

Planning: notes

Identifying and Selecting Systems Development Projects

Planning is the first SDLC phase, and it consists of two activities: project identification and selection, then project initiation and planning. During identification and selection, a senior manager, business group, IS manager, or steering committee identifies every systems development project an organisational unit could undertake; the candidates are then matched against available resources and a subset is chosen for development.

This has three primary activities.

  • Identifying potential development projects, performed by top management (the CEO or a senior executive), a steering committee of managers with an interest in systems, user departments themselves, or the development group/senior IS manager.
  • Classifying and ranking projects, performed by the same groups using criteria such as cost, duration, complexity, system size and business focus; value chain analysis is a widely used method for assessing the merit of a candidate IS project.
  • Selecting IS development projects, the final activity, weighing existing systems and ongoing projects, resource availability, the evaluation criteria, current business conditions, and the perspectives of the decision makers; because business conditions change, project selection is an ongoing activity, not a one-off decision.

The primary deliverable of this phase is a schedule of specific IS development projects, with the assurance that the organisation gave careful, documented consideration to each selection and understood how it serves its objectives. Incremental commitment is the strategy of reviewing and rejustifying a project at each of these checkpoints, rather than committing to it once and for all.

Corporate and Information Systems Planning

Corporate strategic planning is the ongoing process of defining an organisation's mission, objectives and strategy, and it is a prerequisite for good project selection because it clarifies where the organisation is, where it wants to be, and how to get there. It runs as three steps: understand the current enterprise, define the future enterprise, then develop the strategic plan that guides the transition between the two.

Information systems planning (ISP) applies the same three-step logic to information needs: assessing what information systems, databases and technologies will best satisfy the organisation's needs.

  • Current situation: an inventory of manual and automated processes, manual and automated data, technology, and human resources.
  • Future situation: blueprints for each of the same four areas.
  • Schedule of projects that will carry the organisation from the current to the future situation.

A typical information systems plan documents five things: the organisation's mission, objectives and strategy; an information inventory of business processes, functions, data entities and information needs (current and future); the mission and objectives of IS in transforming the organisation; the constraints on IS development imposed by technology and resources; and a set of conclusions noting likely, but not yet certain, events and their estimated impact on the plan.

What this unit covers

  • Identifying and Selecting Systems Development Projects: Introduction
  • Identifying and Selecting Systems Development Projects
  • Corporate and Information Systems Planning
  • Initiating and Planning Systems Development Projects: Introduction
  • Initiating and Planning Systems Development Projects
  • Process of Initiating and Planning IS Development Projects, Assessing Project Feasibility
  • Building and Reviewing the Baseline Project Plan

Process of Initiating and Planning IS Development Projects, Assessing Project Feasibility

2082 · 5 marks

An initial investment of Rs. 5,00,000 is required to start a company. The cash flow-in is Rs. 60,000 per year. Assuming the interest rate as 15%, calculate the discounted payback period. (use Net Present Value) [5]

Show solved answer

Discounted Payback Period Using Net Present Value

Given

ParameterValue
Initial Investment ($I_0$)Rs. 5,00,000
Annual Cash Inflow ($Y$)Rs. 60,000
Discount Rate ($i$)15% = 0.15

Solution

Present Value Formula

$$PV_n = Y \times \frac{1}{(1+i)^n} = 60{,}000 \times \frac{1}{(1.15)^n}$$

Discounted Cash Flow Table

Year (n)Discount Factor $1/(1.15)^n$Discounted Inflow (Rs.)Cumulative Discounted Inflow (Rs.)
10.869652,17452,174
20.756145,36997,543
30.657539,4521,36,995
40.571834,3061,71,301
50.497229,8312,01,132
60.432325,9402,27,072
70.375922,5572,49,629
80.326919,6152,69,244
90.284317,0572,86,301
100.247214,8323,01,133

Key Observation - Limiting Value

The discounted inflows form a decreasing geometric series. The maximum possible cumulative present value (i.e. as $n \to \infty$, a perpetuity) is:

$$PV_{\max} = \frac{Y}{i} = \frac{60{,}000}{0.15} = Rs.\ 4{,}00{,}000$$

Since the sum of ALL discounted inflows to infinity is only Rs. 4,00,000, and this is less than the initial investment of Rs. 5,00,000, the cumulative discounted cash inflows can never recover the initial investment.

NPV Check

$$NPV = PV_{\max} - I_0 = 4{,}00{,}000 - 5{,}00{,}000 = -,Rs.\ 1{,}00{,}000$$

The NPV is negative (approaches $-1{,}00{,}000$), so the project never breaks even on a discounted basis.


Conclusion

The discounted payback period does not exist at a 15% discount rate.

The present value of all future cash inflows (even summed to infinity as a perpetuity) equals only Rs. 4,00,000, which is less than the initial investment of Rs. 5,00,000. Hence the discounted cash inflows never recover the initial outlay, and the project is not viable at 15% (NPV = -Rs. 1,00,000).

Open this answer on its own page →

2081 · 5 marks

An initial investment of Rs. 1,00,000 is required to start a company. The cash flow-in is Rs. 40,000 per year. Assuming interest rate as 10%, calculate the discounted payback period. (use Net Present Value) [5]

Show solved answer

Discounted Payback Period Using Net Present Value

Given

ParameterValue
Initial InvestmentRs. 1,00,000 (outflow at Year 0)
Annual Cash InflowRs. 40,000 per year
Discount Rate ($i$)10% = 0.10

Solution

Present Value Formula

$$PV_n = \frac{Y}{(1+i)^n}$$

Step 1: Discounted Cash Inflows Per Year

Year $n$Discount Factor $\frac{1}{(1.10)^n}$PV of Inflow (Rs.)
10.90909$40000 \times 0.90909 = 36{,}364$
20.82645$40000 \times 0.82645 = 33{,}058$
30.75131$40000 \times 0.75131 = 30{,}053$
40.68301$40000 \times 0.68301 = 27{,}320$

Step 2: Cumulative Discounted Cash Flow (NPV progression)

YearPV of Inflow (Rs.)Cumulative NPV (Rs.)
0--$-1{,}00{,}000$
136,364$-63{,}636$
233,058$-30{,}578$
330,053$-525$
427,320$+26{,}795$

Step 3: Locate the Break-even

  • End of Year 3: cumulative = $-525$ (still negative)
  • End of Year 4: cumulative = $+26{,}795$ (positive)

So the payback occurs during Year 4.

Step 4: Exact Discounted Payback Period

$$\text{Fraction} = \frac{\text{Unrecovered amount at start of year}}{\text{Discounted inflow of that year}} = \frac{525}{27{,}320} = 0.0192$$

$$\boxed{\text{Discounted Payback Period} = 3 + 0.019 \approx 3.02 \text{ years}}$$


Conclusion

Considering the time value of money at a 10% discount rate, the Rs. 1,00,000 investment is recovered in approximately 3.02 years (just over 3 years). The tiny rounding differences (Rs. 525 vs Rs. 528) do not change the result.

Open this answer on its own page →

2080 · 5 marks

Define feasibility study. Explain economic and schedule feasibility in brief. [5]

Show solved answer

Feasibility Study: Definition and Types

Definition of Feasibility Study

A feasibility study is an analysis that considers all of a project's relevant factors -- including economic, technical, legal, and scheduling considerations -- to ascertain the likelihood of completing the project successfully. Whether a project is feasible or not can depend on several factors, including the project's cost and return on investment.

The primary purpose of a feasibility study is to reduce the number of business options and determine whether a proposed project should be pursued, redirected, or abandoned.


Types of Feasibility (Economic and Schedule)

1. Economic Feasibility (Cost-Benefit Analysis)

Economic feasibility is the analysis of a system to determine whether the expected benefits equal or exceed the expected costs.

Key points:

  • The main purpose is to identify the financial benefits and costs associated with the development project.
  • During project initiation and planning, it may be impossible to define precisely all benefits and costs related to a particular project.
  • Worksheets are used to record costs and benefits, and these worksheets are reviewed after each SDLC phase to decide whether to:
    • Continue the project
    • Redirect the project
    • Kill the project

Example considerations:

CostsBenefits
Development costIncreased revenue
Hardware/software costReduced operational cost
Maintenance costImproved efficiency

2. Schedule Feasibility

Schedule feasibility determines whether the project can be completed within the given time frame and deadlines set by the organization.

Key points:

  • It evaluates whether the project timeline is realistic and achievable given the available resources.
  • It considers the project size, complexity, and team capacity when estimating time requirements.
  • If a project cannot be delivered on time, it may lose its business value even if technically and economically sound.
  • Schedule feasibility is closely linked to project planning, where the project manager creates a blueprint mapping out estimated time and execution plan.

Factors affecting schedule feasibility:

  • Size and complexity of the project
  • Availability of skilled personnel
  • Dependencies between project tasks
  • Risk factors that may cause delays

Summary

Feasibility TypeFocus
EconomicCost vs. benefit analysis
ScheduleCompletion within time constraints

Both economic and schedule feasibility are critical during the initiation phase of a project to ensure resources are wisely invested and deadlines are realistically met.

Open this answer on its own page →

2079 · 5 marks

List and describe the steps in the project initiation and planning process. [5]

Project initiation and planning is the first major phase of the SDLC. It lays the foundation for all subsequent development activities by clearly defining what the project is, why it is needed, and how it will be carried out. --- The process begins when a senior manager, a business group, an IS m...

Open this answer on its own page →

2078 · 10 marks

Assume monetary benefits of an information system of $70,000 the first year and increasing benefits of $10,000 a year for the next four years; one-time development costs of $90,000, and recurring costs of $40,000 per year over the duration of the system's life. The discount rate for the company was 1! percent. Using a five-year time horizon, calculate the net present value of these costs and benefits. Also, calculate the overall return on investment and then present a breakeven analysis. At what point does breakeven occur?[10]

Parameter Value ------ Benefit Year 1 $70,000 Benefit increase $10,000/year (Years 2-5) One-time development cost $90,000 Recurring cost $40,000/year Discount rate 11% (0.11) Time horizon 5 years Benefits: Y1 = 70,000; Y2 = 80,000; Y3 = 90,000; Y4 = 100,000; Y5 = 110,000. Discount factors

Open this answer on its own page →

2078 · 5 marks

Explain the process initialing and planning information system development project in brief. [5]

Project management is a controlled process of initiating, planning, executing, monitoring, controlling, and closing a project. Its focus is to ensure that systems development projects meet customer expectations and are delivered within budget and time constraints. --- The initiation phase involve...

Open this answer on its own page →

2076 · 10 marks

Define feasibility. Explain different categories of feasibility. How do you measure economic feasibility?[10]

Show solved answer

Feasibility Study: Definition, Categories, and Economic Feasibility Measurement


1. Definition of Feasibility

A feasibility study is an analysis that considers all of a project's relevant factors -- including economic, technical, legal, and scheduling considerations -- to ascertain the likelihood of completing the project successfully. Whether a project is feasible or not can depend on several factors, including the project's cost and return on investment.

In simple terms, feasibility determines whether a proposed system or project is worth pursuing before significant resources are committed to it. It reduces the number of business options and helps the organization decide whether to continue, redirect, or kill a project.


2. Categories of Feasibility

There are four major categories of feasibility studied during system development:


2.1 Economic Feasibility (Cost-Benefit Analysis)

Economic feasibility (also called Cost-Benefit Analysis) is the analysis of a system to determine whether the expected benefits equal or exceed the expected costs.

  • The main purpose is to identify the financial benefits and costs associated with the development project.
  • During project initiation and planning, it may be impossible to define precisely all benefits and costs.
  • Review worksheets are used to record costs and benefits.
  • These worksheets are used after each SDLC phase to decide whether to continue, redirect, or terminate the project.

2.2 Technical Feasibility

Technical feasibility evaluates:

  • Whether the new system will perform adequately.
  • Whether the organization has the ability to construct the proposed system.

Key points:

  • All projects carry risk, and that risk is not necessarily something to avoid.
  • Organizations typically expect a greater return on investment for riskier projects.
  • Potential risks need to be identified as early as possible.

The amount of technical risk associated with a project depends on four primary factors:

FactorDescription
Project SizeLarger projects carry more risk
Project StructureWell-structured projects are less risky
Development Group's ExperienceExperience with the application and technology area
User Group's ExperienceExperience with systems development and the application area

2.3 Operational Feasibility

Operational feasibility assesses whether the proposed system will likely solve the business problem or take advantage of identified opportunities.

  • It is important to understand how the new system will fit into the existing organizational environment.
  • It considers whether users will accept and use the new system.
  • It evaluates whether the system will be supported by management and staff.

2.4 Schedule Feasibility

Schedule feasibility determines whether the project can be completed within an acceptable time frame.

  • It considers the deadlines and milestones set for the project.
  • If the project cannot be delivered on time, it may not be feasible even if it is economically and technically sound.

Note: Schedule and legal feasibility are standard categories supplementing the notes above.


3. Measuring Economic Feasibility

Economic feasibility is measured through Cost-Benefit Analysis (CBA). The steps and methods are as follows:


Step 1: Identify and Estimate Costs

Costs are broadly classified as:

a) Development Costs (One-time costs)

  • Hardware and software purchase
  • Personnel (analysts, programmers, testers)
  • Training costs
  • Installation and setup costs

b) Operational Costs (Recurring costs)

  • Maintenance and support
  • Licensing fees
  • Operational staff salaries

Step 2: Identify and Estimate Benefits

Benefits can be:

a) Tangible Benefits (Quantifiable in monetary terms)

  • Reduction in operational costs
  • Increased revenue or productivity
  • Reduction in errors and rework

b) Intangible Benefits (Difficult to quantify)

  • Improved customer satisfaction
  • Better decision-making
  • Enhanced organizational image

Step 3: Apply Measurement Techniques

The following techniques are commonly used to measure economic feasibility:

a) Break-Even Analysis

Determines the point at which total benefits equal total costs.

Break-Even Point = Total Development Cost / (Annual Benefits - Annual Operating Costs)

b) Return on Investment (ROI)

Measures the profitability of the investment.

ROI = (Net Benefits / Total Costs) x 100%

Where:

Net Benefits = Total Benefits - Total Costs

c) Net Present Value (NPV)

Accounts for the time value of money by discounting future benefits to present value.

NPV = Sum of [Benefit(t) / (1 + r)^t] - Initial Cost

Where:

  • r = discount rate
  • t = time period

If NPV > 0, the project is economically feasible.

d) Payback Period

The time required to recover the initial investment from net benefits.

Payback Period = Initial Investment / Annual Net Benefit

Step 4: Use Review Worksheets

After each SDLC phase, review worksheets are updated with actual and revised cost-benefit data. Based on these worksheets, management decides to:

  • Continue the project as planned
  • Redirect the project (change scope or approach)
  • Kill the project (if costs outweigh benefits)

Summary Table

CategoryKey Question
Economic FeasibilityAre the benefits worth the costs?
Technical FeasibilityCan we build it with available technology?
Operational FeasibilityWill it solve the problem and be accepted?
Schedule FeasibilityCan it be completed on time?

Conclusion: Feasibility study is a critical early step in the SDLC. Economic feasibility, measured through cost-benefit analysis tools like ROI, NPV, and payback period, is the most critical dimension as it directly determines the financial viability of the proposed system.

Open this answer on its own page →

Initiating and Planning Systems Development Projects

2080 · 5 marks

Describe different activities performed by the project manager during project planning. [5]

The project manager is a system analyst with a diverse set of skills including management, leadership, technical, conflict management, and customer relationship skills. The project manager is responsible for initiating, planning, executing, and closing down the project. During the project plannin...

Open this answer on its own page →

2076 · 5 marks

What is project initiation? Explain different activities you will perform during project initiation phase. [5]

Project initiation is the first major activity of the project initiation and planning phase of the SDLC. It focuses on activities that help organize a team to conduct project planning. During this phase, the project is conceptualized and feasibility is determined. It is the starting point where a...

Open this answer on its own page →

Corporate and Information Systems Planning

2080 · 5 marks

Describe the steps involved in corporate strategic planning. [5]

Corporate strategic planning is the ongoing process that defines the mission, objectives, and strategies of an organization. It is a prerequisite for making effective project selection decisions, as it gives a clear idea of where an organization currently is, where it wants to be in the future, a...

Open this answer on its own page →

Identifying and Selecting Systems Development Projects

2079 · 5 marks

Describe the project identification and selection process. [5]

Project identification and selection is the first major activity in the Planning phase of the SDLC. During this process, senior managers, business groups, IS managers, or committees identify all possible systems development projects that an organization could undertake, and then select those proj...

Open this answer on its own page →

2076 · 5 marks

What is the process of identifying and selecting information system development project in brief. [5]

The process of identifying and selecting IS development projects is an important and ongoing activity that ensures an organization invests its resources in the right systems. It consists of the following key steps: --- Projects are identified from various sources within the organization: - User D...

Open this answer on its own page →