Software Project Management · Unit 1 · 5 hrs
Introduction to Software Project Management
Exam-focused notes for Introduction to Software Project Management (Software Project Management, CSC425): what the TU syllabus asks and how it has actually been tested, with 4 solved past questions from this unit.
Introduction to Software Project Management in short
This chapter introduces software project management as a discipline in its own right: what makes a software project different from other engineering projects, the phases every project passes through, and the framework and plan types a manager uses to keep a project under control.
What this unit covers
- Software engineering problem and software product
- Software product attributes
- Definition of a Software Project (SP)
- SP Vs. other types of projects activities covered by SPM
- Categorizing SPs
- Project management cycle
- SPM framework
- Types of project plan
Types of project plan
2081 · 5 marks
Explain different types of project plan. [5]
Show solved answerHide answer
Types of Project Plan
Definition
A project plan defines project goals and objectives, specifies tasks and how goals will be achieved, identifies what resources will be needed, and associated budgets and timelines for completion.
A typical project plan consists of the following key types/components:
1. Statement of Work (SOW)
- A formal document that defines the scope, objectives, and deliverables of the project.
- It describes what work needs to be done, the timeline, and the expected outcomes.
- It serves as a foundation for all other planning activities.
2. Resource Plan
- Identifies what resources (human, hardware, software, financial) are required for the project.
- Determines when resources should be available and how they should be allocated effectively.
- Helps in scheduling staff across different departments at the right time.
3. Work Breakdown Structure (WBS)
- The WBS breaks an engineering project down into subprojects, tasks, subtasks, and work packages.
- It is an important planning tool that links objectives with resources and activities in a logical framework.
- It becomes an important status monitor during actual implementation.
- Two common approaches:
- Activity-based approach: Uses WBS to generate a task list by identifying main tasks and breaking them into subtasks.
- Product-based approach: Uses Product Breakdown Structure (PBS) and Product Flow Diagram (PFD) to show how a system is broken into products.
4. Project Schedule
- Defines the timeline for completing each task and milestone.
- Helps in:
- Feasibility assessment: Is the project possible within required timescales?
- Motivation: Providing targets and monitoring achievement against them.
- Co-ordination: Ensuring staff in different departments are available at the right time.
5. Risk Plan
- Identifies potential risks that may affect the project.
- Involves analyzing risks and planning corrective actions to minimize or mitigate their impact.
- Risk management is performed continuously during project execution to identify possible risks and address them proactively.
Summary Table
| Plan Type | Purpose |
|---|---|
| Statement of Work | Defines scope and objectives |
| Resource Plan | Allocates human and material resources |
| Work Breakdown Structure | Breaks project into manageable tasks |
| Project Schedule | Defines timelines and milestones |
| Risk Plan | Identifies and mitigates project risks |
Together, these five types of project plans ensure that a software project is delivered on time, within budget, and with the required quality.
SPM framework
Project management cycle
SP Vs. other types of projects activities covered by SPM
2078 · 5 marks
Why software project management is a challenging activity? [5]