Software Project Management ยท Unit 5 ยท 4 hrs
Resource Allocation
Exam-focused notes for Resource Allocation (Software Project Management, CSC425): what the TU syllabus asks and how it has actually been tested, with 2 solved past questions from this unit.
Resource Allocation in short
This chapter covers resource allocation: identifying what a project actually needs to run, assigning people and other resources to activities, and smoothing that assignment so demand stays within what is actually available.
What this unit covers
- Identifying resource requirements
- Resource allocation
- Resource smoothening and resource balancing
Resource smoothening and resource balancing
2081 ยท 5 marks
Why do you think resource smoothening and resource balancing is required? Explain how it is carried out? [5]
2080 ยท 10 marks
Explain about different categories of resources? Highlight on the process of resource histogram equalization. Why do you think it is a crucial activity?[10]
Show solved answerHide answer
Resource Categories, Resource Histogram Equalization, and Its Importance
1. Categories of Resources
For each and every activity in a project, we need to identify the resources required. Resources are broadly classified into the following categories:
a) Labour
- Human resources involved in the project such as developers, testers, analysts, project managers, and support staff.
- Labour is often the most significant resource in software projects.
- Skills, availability, and cost of each person must be considered during planning.
b) Equipment
- Physical tools and machinery required to carry out project activities.
- Examples: computers, servers, testing devices, networking hardware.
- Equipment availability must be scheduled carefully to avoid bottlenecks.
c) Materials
- Consumable or physical materials needed during the project.
- Examples: storage media, printed documentation, stationery, cables.
- Unlike equipment, materials are consumed and cannot be reused.
d) Space / Facilities
- Physical workspace required for the team, such as office space, labs, meeting rooms, and data centers.
- Availability of space must be planned in advance, especially for large teams.
e) Time
- Time is a critical resource in every project.
- It includes deadlines, milestones, and the overall project schedule.
- Poor time management leads to project delays and cost overruns.
f) Money / Finance
- Budget allocated for the project covering all other resource costs.
- Tracked through cost schedules that show planned cumulative expenditure over time.
- Closely linked to the resource schedule and activity schedule.
g) Services / Utilities
- External services such as cloud platforms, licensed software, internet connectivity, and third-party APIs.
- These are often overlooked but are essential for modern software projects.
Resource allocation is the process of assigning and scheduling available resources in the most effective and economical way as much as possible, so that the entire project development process runs smoothly.
2. Resource Histogram and the Process of Resource Histogram Equalization
What is a Resource Histogram?
A resource histogram is a bar chart that shows the amount of a particular resource (usually labour, measured in person-days or hours) required over a period of time across the project schedule. The horizontal axis represents time (weeks/days) and the vertical axis represents the resource demand level.
Example of a typical resource histogram:
Resource
Demand
(persons)
8 | โโโโ
7 | โโโโ โโโโ
6 | โโโโ โโโโ โโโโ
5 | โโโโ โโโโ โโโโ โโโโ
4 | โโโโ โโโโ โโโโ โโโโ
---------------------------------> Time (weeks)
W1 W2 W3 W4 W5
In the above, demand peaks at Week 3, which may exceed available resources.
What is Resource Histogram Equalization (Resource Leveling / Smoothing)?
Resource histogram equalization (also called resource leveling or resource smoothing) is the process of adjusting the project schedule so that resource usage is distributed as evenly as possible over the project duration, without exceeding the available resource limits.
Resource smoothing is defined as a technique that adjusts the activity of a schedule model so that all the requirements for the resources do not go beyond limits than that of pre-defined planning. It is one of the project management tools used in resource optimization techniques.
Process of Resource Histogram Equalization
The step-by-step process is as follows:
Step 1: Draw the Initial Resource Histogram
- Plot the resource requirements for each time period based on the current activity schedule.
- Identify peaks (over-allocation) and troughs (under-utilization).
Step 2: Identify the Resource Availability Limit
- Determine the maximum number of resources available at any given time (the resource ceiling).
- Mark this limit as a horizontal line on the histogram.
Step 3: Identify Over-Allocated Periods
- Locate all time periods where resource demand exceeds the available limit.
- These are the problem areas that need to be resolved.
Step 4: Reschedule Non-Critical Activities
- Activities that have float (slack) in the schedule can be delayed or shifted without affecting the project end date.
- Move these activities from peak periods to trough periods to balance the load.
- This is done using the activity schedule and network diagram (CPM/PERT).
Step 5: Split or Reassign Activities
- If rescheduling is not sufficient, consider:
- Splitting a task into smaller parts spread over different time periods.
- Reassigning tasks to different team members who are under-utilized.
Step 6: Draw the Equalized Resource Histogram
- After adjustments, redraw the histogram.
- The new histogram should show a more uniform distribution of resources, ideally at or below the resource ceiling.
Step 7: Verify Project Constraints
- Ensure that the equalization has not violated any hard deadlines or dependencies.
- If the project end date is affected, negotiate with stakeholders or acquire additional resources.
Before and After Equalization:
BEFORE (Uneven): AFTER (Equalized):
Demand Demand
8 | โโโโ 6 | โโโโ โโโโ โโโโ โโโโ โโโโ
6 | โโโโโโโโโโโโ 4 | โโโโ โโโโ โโโโ โโโโ โโโโ
4 | โโโโโโโโโโโโ 2 | โโโโ โโโโ โโโโ โโโโ โโโโ
W1 W2 W3 W4 W1 W2 W3 W4 W5
3. Why Resource Histogram Equalization is a Crucial Activity
Resource histogram equalization is considered a crucial project management activity for the following reasons:
a) Prevents Over-Allocation
- Without equalization, certain periods may demand more resources than are available, making the schedule unrealistic and unachievable.
b) Reduces Project Costs
- Hiring temporary staff or paying overtime during peak periods is expensive. A leveled schedule reduces such unnecessary costs.
c) Improves Team Productivity and Morale
- Uneven workloads cause burnout during peaks and boredom during troughs. Equalization ensures a steady, manageable workload, which improves motivation and performance.
d) Produces a Realistic and Achievable Schedule
- A schedule that respects the resource availability limit can actually be delivered, so commitments made to the client on the basis of the leveled histogram are trustworthy.
e) Improves Utilization of Resources
- Moving work from the peaks into the troughs keeps people and equipment busy through the whole project instead of leaving them idle between bursts of demand.
4. Conclusion
Project resources fall into distinct categories (labour, equipment, materials, space, time, money and services), and each of them is limited. A resource histogram exposes how the demand for one of these resources varies week by week, and equalization reshapes that demand by rescheduling non-critical activities within their float until the profile fits under the availability line without extending the project. It is a crucial activity because it turns a schedule that is merely logically correct into one that is resource-feasible, cheaper to staff, and kinder to the team delivering it.