Software Project Management · Unit 9 · 3 hrs
Software Configuration Management
Exam-focused notes for Software Configuration Management (Software Project Management, CSC425): what the TU syllabus asks and how it has actually been tested, with 5 solved past questions from this unit.
Software Configuration Management in short
This chapter covers software configuration management: the discipline of tracking and controlling every change made to a software system, so that what was built, tested and released is always known and reproducible.
What this unit covers
- Introduction
- Need
- Basic configuration
- Management function
- Baseline
- Configuration management responsibilities
Configuration management responsibilities
2081 · 5 marks
Highlight on configuration management responsibilities. [5]
2080 · 5 marks
How can Software Configuration Management aid in change control and version control? [5]
Baseline
2081 · 5 marks
Write short notes on: a. Baseline b. Schedule variance [5]
Show solved answerHide answer
Short Notes: Baseline and Schedule Variance
a. Baseline (2.5 marks)
A baseline is an approved, fixed reference point used to measure and compare the actual progress of a project against what was originally planned.
In software project management, the baseline is established during the planning phase and serves as a standard against which project performance is monitored and controlled. As noted in the SPM framework, the "Check" phase of the project control cycle involves measuring "Progress against baseline" and tracking "Costs to date" -- this confirms that the baseline is the foundation for all monitoring and control activities.
Key characteristics of a baseline:
- It is set after the project plan is approved and work is about to begin.
- It captures the planned scope, schedule, and cost of the project.
- It remains fixed unless a formal change control process approves modifications.
- It enables the project manager to detect deviations early and take corrective actions.
Types of Baselines:
| Type | Description |
|---|---|
| Scope Baseline | Approved version of the project scope and work breakdown structure (WBS) |
| Schedule Baseline | Approved version of the project timeline and milestones |
| Cost Baseline | Approved budget against which cost performance is measured |
The baseline is a critical component of the project control cycle in the SPM framework, enabling the team to identify variances and take corrective actions when actual progress deviates from the plan.
b. Schedule Variance (2.5 marks)
Schedule Variance (SV) is a measure of how much a project is ahead of or behind the planned schedule at any given point in time. It is a key metric used in Earned Value Management (EVM) to monitor project time performance.
Formula:
$$SV = EV - PV$$
Where:
- EV (Earned Value) = Budgeted cost of work actually performed
- PV (Planned Value) = Budgeted cost of work that was scheduled to be done by this point
Interpretation:
| Result | Meaning |
|---|---|
| SV > 0 (Positive) | Project is ahead of schedule |
| SV = 0 | Project is exactly on schedule |
| SV < 0 (Negative) | Project is behind schedule (a warning sign) |
Example:
Suppose by the end of week 5:
- Planned Value (PV) = Rs. 50,000 (work that should have been done)
- Earned Value (EV) = Rs. 40,000 (work actually completed)
$$SV = EV - PV = 40,000 - 50,000 = -10,000$$
A negative SV of Rs. 10,000 means the project is behind schedule by that amount of work value.
Importance of Schedule Variance:
- It helps project managers identify schedule slippage early.
- It supports corrective actions such as reallocating resources or adjusting timelines.
- It is used alongside the baseline in the project control cycle to keep the project on track.
- It directly supports the SPM framework activity of monitoring "Progress against baseline".
Summary: The baseline defines what was planned, and schedule variance measures how far actual execution has deviated from that plan. Together, they form the core of project monitoring and control in software project management.
2079 · 5 marks
What is a baseline? Why Software Configuration Management is a critical activity? [5]
Introduction
2078 · 5 marks
Explain the process of Software Configuration Management. [5]
Make Unit 9 stick
Practice CSC425 with flashcards & quizzes