3 Activity Planning And Scheduling

Software Project Management · Unit 3 · 7 hrs

Activity Planning and Scheduling

Exam-focused notes for Activity Planning and Scheduling (Software Project Management, CSC425): what the TU syllabus asks and how it has actually been tested, with 8 solved past questions from this unit.

Activity Planning and Scheduling in short

This chapter covers activity planning and scheduling: breaking a project into activities, representing them as a bar chart or a network, and computing the critical path that fixes how long the project must take.

Activity Planning and Scheduling: notes

Objectives of Activity Planning

Activity planning serves five purposes. Feasibility assessment asks whether the project is possible within the required timescale and resource constraints. Resource allocation asks what the most effective way of allocating resources to the project is, and when each resource should be available. Detailed costing asks how much the project will cost and when that expenditure is likely to fall due. Motivation comes from giving staff clear targets and visibly monitoring progress against them. Co-ordination ensures staff in different departments know when they are needed to work on a particular part of the project. Planning is necessary because it draws attention to the methodology, standards and methods used to develop the project, keeps it aligned with budget, resources and deadlines, and helps in allocating tasks, avoiding obstacles, and making the best use of time and resources.

Work Breakdown Structure

The work breakdown structure (WBS) breaks an engineering project down into subprojects, tasks, subtasks and work packages. It is an important planning tool that links objectives with resources and activities in a logical framework, and it becomes an important status monitor once implementation is under way. There are three ways of building a WBS.

  • The activity-based approach identifies the main tasks first, then breaks each main task into subtasks, and those subtasks further into lower-level tasks.
  • The product-based approach uses a product breakdown structure (PBS) to show how a system decomposes into products for development, together with a product flow diagram (PFD) showing which products are required as inputs to which others.
  • The hybrid approach, the most commonly used, mixes both: a list of the project's products, and a list of activities needed to produce each product.

A WBS and a PBS answer different questions and are often confused.

Work breakdown structureProduct breakdown structure
ShowsThe work required to produce the productsThe output of scope management, the products themselves
StructureHierarchical breakdown of the work to be completedHierarchical breakdown of the products to be produced
ObjectiveIdentify and organize all the work needed to complete the projectGive a clear picture of the products' composition and how each will be delivered
DefinesTasks, deliverables and assignments needed to reach the goalsThe final product broken into smaller components, parts, functions and interfaces
Example (software project)Requirement analysis, design, coding, testing, deploymentUser interface, data storage, user management, security and access control

What this unit covers

  • Objectives of activity planning
  • Work breakdown structure
  • Bar chart
  • Network planning model: Critical path method (CPM), Program evaluation and review technique (PERT), Precedence diagramming method (PDM)
  • Shortening project duration
  • Identifying critical activities

Network planning model

2081 · 10 marks

Precedence Network Diagram and Critical Path Analysis

Activity Duration (Weeks) Predecessors ------------------------------------------ A 1 - B 2 A C 5 A D 2 - E 4 C, D F 3 - G 4 B, E, F - A, D, F have no predecessors (start activities). - E depends on C and D. - G depends on B, E, F (final activity).

Open this answer on its own page →

2080 · 5 marks

Draw precedence network diagram for the following and identify the critical path.

ActivityDuration (weeks)Precedence
A2
B2
C4A
D2B
E4B, D

[5]

Show solved answer

Precedence Network Diagram and Critical Path

Given

ActivityDuration (weeks)Precedence
A2none
B2none
C4A
D2B
E4B, D

A and B are start activities.


Solution

Activity-on-Node Network Diagram

          +--> [A: 2] --> [C: 4] --+
          |                        |
 [Start] -+                        +--> [Finish]
          |                        |
          +--> [B: 2] --+--> [D: 2] --+--> [E: 4] --+
                        |                            |
                        +----------------------------+
                        (B is also predecessor of E)

Possible Paths

PathActivitiesDuration
1A -> C$2 + 4 = 6$
2B -> D -> E$2 + 2 + 4 = 8$
3B -> E$2 + 4 = 6$

Forward Pass (ES, EF)

$$EF = ES + \text{Duration}$$

ActivityESEF
A02
B02
C26
D24
E$\max(EF_B, EF_D) = \max(2,4) = 4$8

Project duration = 8 weeks

Backward Pass (LS, LF)

$$LS = LF - \text{Duration}$$

ActivityLFLS
E84
D42
C84
B$\min(LS_D, LS_E) = \min(2,4) = 2$0
A42

Float = LS - ES

ActivityESEFLSLFFloat
A02242
B02020
C26482
D24240
E48480

Critical Path

Activities with zero float: B, D, E

$$\boxed{\text{Critical Path: } B \to D \to E \quad \text{Duration} = 8 \text{ weeks}}$$

Activities A and C are non-critical (float = 2 weeks each).

Open this answer on its own page →

2079 · 5 marks

Draw CPM network diagram for the following and identify the critical path.

ActivityDuration (weeks)Precedence
A4
B4A
C2A
D6B, C

[5]

Show solved answer

CPM Network Diagram and Critical Path

Given

ActivityDuration (weeks)Precedence
A4-
B4A
C2A
D6B, C

Step 2 - Network Diagram (Activity-on-Arrow)

Since CPM traditionally uses Activity-on-Arrow (AOA), I number events 1 to 5.

                B(4)
        (2) ---------->
       /                \
   A(4)                  \  D(6)
   /                      >(4) ----> (5)
 (1)                     /
       \                /
        (2) ---C(2)---> (3) --dummy--> (4)?

Cleaner AOA representation: A splits into B and C, both merge before D.

        +---B(4)---+
        |          v
(1)--A(4)-->(2)   (4)--D(6)-->(5)
        |          ^
        +---C(2)---+
  • Event 1: Start
  • A (1 to 2), duration 4
  • B (2 to 4), duration 4
  • C (2 to 4), duration 2
  • D (4 to 5), duration 6

Step 3 - Forward Pass (ES, EF)

$$EF = ES + \text{Duration}$$

ActivityESDurationEF
A044
B448
C426
D$\max(8,6)=8$614

Project Duration = 14 weeks

Step 4 - Backward Pass (LF, LS)

$$LS = LF - \text{Duration}$$

ActivityLFDurationLS
D1468
B844
C826
A$\min(4,6)=4$40

Step 5 - Total Float

$$\text{Float} = LS - ES = LF - EF$$

ActivityESEFLSLFFloatCritical?
A04040Yes
B48480Yes
C46682No
D8148140Yes

Step 6 - Critical Path

$$\boxed{A \rightarrow B \rightarrow D}$$

Duration $= 4 + 4 + 6 = 14$ weeks.

Activity C has float of 2 weeks (non-critical).

Open this answer on its own page →

2079 · 5 marks

Why PERT chart is an efficient technique? Explain estimated time, standard deviation and Z-value with respect to PERT chart. [5]

PERT (Program Evaluation and Review Technique) is considered an efficient technique for project management for the following reasons: - Activities are shown as a network of precedence relationships using activity-on-arrow network, making dependencies clear and easy to understand. - It is used for...

Open this answer on its own page →

2078 · 5 marks

Draw precedence network diagram for the following and identify the critical path.

ActivityDuration (Weeks)Precedence
A5
B3A
C5A
D10B, C

[5]

Show solved answer

Precedence Network Diagram and Critical Path

Given

ActivityDuration (Weeks)Precedence
A5None (start)
B3A
C5A
D10B, C

Solution

Precedence Network (Activity-on-Node)

                 +--------+
             +-->|  B: 3  |---+
             |   +--------+   |
+--------+   |                v   +--------+
|  A: 5  |---+                +-->|  D: 10 |---> Finish
+--------+   |                ^   +--------+
             |   +--------+   |
             +-->|  C: 5  |---+
                 +--------+
  • A has no predecessor (starts the project).
  • B and C both follow A.
  • D follows both B and C (both must complete before D starts).

Forward Pass (Earliest Start / Earliest Finish)

$EF = ES + \text{Duration}$

ActivityESDurationEF
A055
B538
C5510
D$\max(8,10)=10$1020

Project Duration = 20 weeks

Backward Pass (Latest Finish / Latest Start)

$LS = LF - \text{Duration}$

ActivityLFDurationLS
D201010
C1055
B1037
A$\min(7,5)=5$50

Total Float ($TF = LS - ES$)

ActivityESLSTotal FloatCritical?
A000Yes
B572No
C550Yes
D10100Yes

Critical Path

Path enumeration:

  • $A \to B \to D = 5 + 3 + 10 = 18$ weeks
  • $A \to C \to D = 5 + 5 + 10 = 20$ weeks (longest)

$$\boxed{A \rightarrow C \rightarrow D, \quad \text{Duration} = 20 \text{ weeks}}$$

Open this answer on its own page →

Objectives of activity planning

2080 · 5 marks

What are the objectives that activity planning aims to achieve? [5]

Show solved answer

Objectives of Activity Planning

Activity planning is a crucial part of software project management. It aims to achieve the following objectives:


1. Feasibility Assessment

Activity planning helps determine whether the project is possible within the required timescales and resource constraints. It allows the project manager to evaluate if the goals are realistic before committing fully to execution.


2. Resource Allocation

Planning identifies the most effective ways of allocating resources to the project. It answers key questions such as:

  • What resources are needed?
  • When should those resources be made available?

This ensures no resource is over-committed or left idle.


3. Detailed Costing

Activity planning helps estimate how much the project will cost and when that expenditure is likely to take place. This supports budgeting and financial control throughout the project lifecycle.


4. Motivation

By providing clear targets and monitoring achievement against those targets, activity planning serves as an effective way of motivating staff. When team members can see progress and milestones, it encourages better performance.


5. Co-ordination

Activity planning helps determine when staff from different departments need to be available to work on a particular project. This ensures smooth collaboration and avoids scheduling conflicts between teams.


Summary Table:

ObjectivePurpose
Feasibility AssessmentCheck if project is achievable
Resource AllocationAssign resources effectively
Detailed CostingEstimate costs and expenditure timing
MotivationSet targets to encourage staff
Co-ordinationSynchronize availability of different teams

These five objectives together ensure that a project is well-planned, properly resourced, and realistically achievable within the defined constraints.

Open this answer on its own page →

2079 · 5 marks

What are different stages required to create a project schedule? [5]

A project schedule is a key component of the overall project plan. It defines when tasks will be performed, who will perform them, and what resources are needed. The following are the different stages required to create a project schedule: --- The first stage involves clearly identifying what the...

Open this answer on its own page →

2078 · 5 marks

Differentiate between activity-based approach and hybrid-based approach for identifying activities. [5]

The activity-based approach uses the Work Breakdown Structure (WBS) to generate a complete task list for the project. It focuses on identifying and decomposing activities/tasks in a top-down hierarchical manner. 1. Identify the main tasks of the project at the highest level. 2. Break each main ta...

Open this answer on its own page →