Software Project Management · Unit 3 · 7 hrs
Activity Planning and Scheduling
Exam-focused notes for Activity Planning and Scheduling (Software Project Management, CSC425): what the TU syllabus asks and how it has actually been tested, with 8 solved past questions from this unit.
Activity Planning and Scheduling in short
This chapter covers activity planning and scheduling: breaking a project into activities, representing them as a bar chart or a network, and computing the critical path that fixes how long the project must take.
What this unit covers
- Objectives of activity planning
- Work breakdown structure
- Bar chart
- Network planning model: Critical path method (CPM), Program evaluation and review technique (PERT), Precedence diagramming method (PDM)
- Shortening project duration
- Identifying critical activities
Network planning model
2081 · 10 marks
Precedence Network Diagram and Critical Path Analysis
2080 · 5 marks
Draw precedence network diagram for the following and identify the critical path.
| Activity | Duration (weeks) | Precedence |
|---|---|---|
| A | 2 | |
| B | 2 | |
| C | 4 | A |
| D | 2 | B |
| E | 4 | B, D |
[5]
Show solved answerHide answer
Precedence Network Diagram and Critical Path
Given
| Activity | Duration (weeks) | Precedence |
|---|---|---|
| A | 2 | none |
| B | 2 | none |
| C | 4 | A |
| D | 2 | B |
| E | 4 | B, D |
A and B are start activities.
Solution
Activity-on-Node Network Diagram
+--> [A: 2] --> [C: 4] --+
| |
[Start] -+ +--> [Finish]
| |
+--> [B: 2] --+--> [D: 2] --+--> [E: 4] --+
| |
+----------------------------+
(B is also predecessor of E)
Possible Paths
| Path | Activities | Duration |
|---|---|---|
| 1 | A -> C | $2 + 4 = 6$ |
| 2 | B -> D -> E | $2 + 2 + 4 = 8$ |
| 3 | B -> E | $2 + 4 = 6$ |
Forward Pass (ES, EF)
$$EF = ES + \text{Duration}$$
| Activity | ES | EF |
|---|---|---|
| A | 0 | 2 |
| B | 0 | 2 |
| C | 2 | 6 |
| D | 2 | 4 |
| E | $\max(EF_B, EF_D) = \max(2,4) = 4$ | 8 |
Project duration = 8 weeks
Backward Pass (LS, LF)
$$LS = LF - \text{Duration}$$
| Activity | LF | LS |
|---|---|---|
| E | 8 | 4 |
| D | 4 | 2 |
| C | 8 | 4 |
| B | $\min(LS_D, LS_E) = \min(2,4) = 2$ | 0 |
| A | 4 | 2 |
Float = LS - ES
| Activity | ES | EF | LS | LF | Float |
|---|---|---|---|---|---|
| A | 0 | 2 | 2 | 4 | 2 |
| B | 0 | 2 | 0 | 2 | 0 |
| C | 2 | 6 | 4 | 8 | 2 |
| D | 2 | 4 | 2 | 4 | 0 |
| E | 4 | 8 | 4 | 8 | 0 |
Critical Path
Activities with zero float: B, D, E
$$\boxed{\text{Critical Path: } B \to D \to E \quad \text{Duration} = 8 \text{ weeks}}$$
Activities A and C are non-critical (float = 2 weeks each).
2079 · 5 marks
Draw CPM network diagram for the following and identify the critical path.
| Activity | Duration (weeks) | Precedence |
|---|---|---|
| A | 4 | |
| B | 4 | A |
| C | 2 | A |
| D | 6 | B, C |
[5]
Show solved answerHide answer
CPM Network Diagram and Critical Path
Given
| Activity | Duration (weeks) | Precedence |
|---|---|---|
| A | 4 | - |
| B | 4 | A |
| C | 2 | A |
| D | 6 | B, C |
Step 2 - Network Diagram (Activity-on-Arrow)
Since CPM traditionally uses Activity-on-Arrow (AOA), I number events 1 to 5.
B(4)
(2) ---------->
/ \
A(4) \ D(6)
/ >(4) ----> (5)
(1) /
\ /
(2) ---C(2)---> (3) --dummy--> (4)?
Cleaner AOA representation: A splits into B and C, both merge before D.
+---B(4)---+
| v
(1)--A(4)-->(2) (4)--D(6)-->(5)
| ^
+---C(2)---+
- Event 1: Start
- A (1 to 2), duration 4
- B (2 to 4), duration 4
- C (2 to 4), duration 2
- D (4 to 5), duration 6
Step 3 - Forward Pass (ES, EF)
$$EF = ES + \text{Duration}$$
| Activity | ES | Duration | EF |
|---|---|---|---|
| A | 0 | 4 | 4 |
| B | 4 | 4 | 8 |
| C | 4 | 2 | 6 |
| D | $\max(8,6)=8$ | 6 | 14 |
Project Duration = 14 weeks
Step 4 - Backward Pass (LF, LS)
$$LS = LF - \text{Duration}$$
| Activity | LF | Duration | LS |
|---|---|---|---|
| D | 14 | 6 | 8 |
| B | 8 | 4 | 4 |
| C | 8 | 2 | 6 |
| A | $\min(4,6)=4$ | 4 | 0 |
Step 5 - Total Float
$$\text{Float} = LS - ES = LF - EF$$
| Activity | ES | EF | LS | LF | Float | Critical? |
|---|---|---|---|---|---|---|
| A | 0 | 4 | 0 | 4 | 0 | Yes |
| B | 4 | 8 | 4 | 8 | 0 | Yes |
| C | 4 | 6 | 6 | 8 | 2 | No |
| D | 8 | 14 | 8 | 14 | 0 | Yes |
Step 6 - Critical Path
$$\boxed{A \rightarrow B \rightarrow D}$$
Duration $= 4 + 4 + 6 = 14$ weeks.
Activity C has float of 2 weeks (non-critical).
2079 · 5 marks
Why PERT chart is an efficient technique? Explain estimated time, standard deviation and Z-value with respect to PERT chart. [5]
2078 · 5 marks
Draw precedence network diagram for the following and identify the critical path.
| Activity | Duration (Weeks) | Precedence |
|---|---|---|
| A | 5 | |
| B | 3 | A |
| C | 5 | A |
| D | 10 | B, C |
[5]
Show solved answerHide answer
Precedence Network Diagram and Critical Path
Given
| Activity | Duration (Weeks) | Precedence |
|---|---|---|
| A | 5 | None (start) |
| B | 3 | A |
| C | 5 | A |
| D | 10 | B, C |
Solution
Precedence Network (Activity-on-Node)
+--------+
+-->| B: 3 |---+
| +--------+ |
+--------+ | v +--------+
| A: 5 |---+ +-->| D: 10 |---> Finish
+--------+ | ^ +--------+
| +--------+ |
+-->| C: 5 |---+
+--------+
- A has no predecessor (starts the project).
- B and C both follow A.
- D follows both B and C (both must complete before D starts).
Forward Pass (Earliest Start / Earliest Finish)
$EF = ES + \text{Duration}$
| Activity | ES | Duration | EF |
|---|---|---|---|
| A | 0 | 5 | 5 |
| B | 5 | 3 | 8 |
| C | 5 | 5 | 10 |
| D | $\max(8,10)=10$ | 10 | 20 |
Project Duration = 20 weeks
Backward Pass (Latest Finish / Latest Start)
$LS = LF - \text{Duration}$
| Activity | LF | Duration | LS |
|---|---|---|---|
| D | 20 | 10 | 10 |
| C | 10 | 5 | 5 |
| B | 10 | 3 | 7 |
| A | $\min(7,5)=5$ | 5 | 0 |
Total Float ($TF = LS - ES$)
| Activity | ES | LS | Total Float | Critical? |
|---|---|---|---|---|
| A | 0 | 0 | 0 | Yes |
| B | 5 | 7 | 2 | No |
| C | 5 | 5 | 0 | Yes |
| D | 10 | 10 | 0 | Yes |
Critical Path
Path enumeration:
- $A \to B \to D = 5 + 3 + 10 = 18$ weeks
- $A \to C \to D = 5 + 5 + 10 = 20$ weeks (longest)
$$\boxed{A \rightarrow C \rightarrow D, \quad \text{Duration} = 20 \text{ weeks}}$$
Objectives of activity planning
2080 · 5 marks
What are the objectives that activity planning aims to achieve? [5]
Show solved answerHide answer
Objectives of Activity Planning
Activity planning is a crucial part of software project management. It aims to achieve the following objectives:
1. Feasibility Assessment
Activity planning helps determine whether the project is possible within the required timescales and resource constraints. It allows the project manager to evaluate if the goals are realistic before committing fully to execution.
2. Resource Allocation
Planning identifies the most effective ways of allocating resources to the project. It answers key questions such as:
- What resources are needed?
- When should those resources be made available?
This ensures no resource is over-committed or left idle.
3. Detailed Costing
Activity planning helps estimate how much the project will cost and when that expenditure is likely to take place. This supports budgeting and financial control throughout the project lifecycle.
4. Motivation
By providing clear targets and monitoring achievement against those targets, activity planning serves as an effective way of motivating staff. When team members can see progress and milestones, it encourages better performance.
5. Co-ordination
Activity planning helps determine when staff from different departments need to be available to work on a particular project. This ensures smooth collaboration and avoids scheduling conflicts between teams.
Summary Table:
| Objective | Purpose |
|---|---|
| Feasibility Assessment | Check if project is achievable |
| Resource Allocation | Assign resources effectively |
| Detailed Costing | Estimate costs and expenditure timing |
| Motivation | Set targets to encourage staff |
| Co-ordination | Synchronize availability of different teams |
These five objectives together ensure that a project is well-planned, properly resourced, and realistically achievable within the defined constraints.
2079 · 5 marks
What are different stages required to create a project schedule? [5]
2078 · 5 marks
Differentiate between activity-based approach and hybrid-based approach for identifying activities. [5]