Software Project Management208010 marksResource smoothening and resource balancing

Explain about different categories of resources? Highlight on the process of resource histogram equalization. Why do you think it is a crucial activity?

Explain about different categories of resources? Highlight on the process of resource histogram equalization. Why do you think it is a crucial activity?[10]

--- For each and every activity in a project, we need to identify the resources required. Resources are broadly classified into the following categories: - Human resources involved in the project such as developers, testers, analysts, project managers, and support staff. - Labour is often the mos...