2081 12

CSC425 ยท 2081 ยท 5 marks

Write short notes on: a. Baseline b. Schedule variance

Write short notes on: a. Baseline b. Schedule variance [5]

Software Project ManagementChapter 9: Software Configuration ManagementBaseline

Quick answer

A baseline is an approved, fixed reference point used to measure and compare the actual progress of a project against what was originally planned.

Short Notes: Baseline and Schedule Variance


a. Baseline (2.5 marks)

In software project management, the baseline is established during the planning phase and serves as a standard against which project performance is monitored and controlled. As noted in the SPM framework, the "Check" phase of the project control cycle involves measuring "Progress against baseline" and tracking "Costs to date" -- this confirms that the baseline is the foundation for all monitoring and control activities.

Key characteristics of a baseline:

  • It is set after the project plan is approved and work is about to begin.
  • It captures the planned scope, schedule, and cost of the project.
  • It remains fixed unless a formal change control process approves modifications.
  • It enables the project manager to detect deviations early and take corrective actions.

Types of Baselines:

TypeDescription
Scope BaselineApproved version of the project scope and work breakdown structure (WBS)
Schedule BaselineApproved version of the project timeline and milestones
Cost BaselineApproved budget against which cost performance is measured

The baseline is a critical component of the project control cycle in the SPM framework, enabling the team to identify variances and take corrective actions when actual progress deviates from the plan.


b. Schedule Variance (2.5 marks)

Schedule Variance (SV) is a measure of how much a project is ahead of or behind the planned schedule at any given point in time. It is a key metric used in Earned Value Management (EVM) to monitor project time performance.

Formula:

$$SV = EV - PV$$

Where:

  • EV (Earned Value) = Budgeted cost of work actually performed
  • PV (Planned Value) = Budgeted cost of work that was scheduled to be done by this point

Interpretation:

ResultMeaning
SV > 0 (Positive)Project is ahead of schedule
SV = 0Project is exactly on schedule
SV < 0 (Negative)Project is behind schedule (a warning sign)

Example:

Suppose by the end of week 5:

  • Planned Value (PV) = Rs. 50,000 (work that should have been done)
  • Earned Value (EV) = Rs. 40,000 (work actually completed)

$$SV = EV - PV = 40,000 - 50,000 = -10,000$$

A negative SV of Rs. 10,000 means the project is behind schedule by that amount of work value.

Importance of Schedule Variance:

  • It helps project managers identify schedule slippage early.
  • It supports corrective actions such as reallocating resources or adjusting timelines.
  • It is used alongside the baseline in the project control cycle to keep the project on track.
  • It directly supports the SPM framework activity of monitoring "Progress against baseline".

Summary: The baseline defines what was planned, and schedule variance measures how far actual execution has deviated from that plan. Together, they form the core of project monitoring and control in software project management.

Short on time? The 1, 5 and 10 mark versions of this answer, flashcards and practice sets come with a program pass.