Critical Path Analysis The following activities must be completed in order to complete the project. Determine the critical path and time duration of the project based on slack time of the activity. | Activity | A | B | C | D | E | F | G | H | I | J | |----------|---|---|---|---|---|---|---|---|---|-

Critical Path Analysis

The following activities must be completed in order to complete the project. Determine the critical path and time duration of the project based on slack time of the activity.

ActivityABCDEFGHIJ
Predecessor--A, BBACE, FD, FG, HI
Time (in days)3842175689

[10]

Operations ResearchChapter 5: Network Analysis and Project ManagementCritical path identificationNumerical: CPM critical path

Activity A B C D E F G H I J ---------------------------------------- Predecessor โˆ’ โˆ’ A,B B A C E,F D,F G,H I Duration (days) 3 8 4 2 1 7 5 6 8 9 $ES = \max(EF \text{ of predecessors})$, $EF = ES + \text{Duration}$ Activity Dur ES EF ----------------------- A 3 0 3 B 8 0 8 C 4 max(3,8)=8 12 D 2 8...