ABC Manufacturing Company produces three products: Tables, Chairs, and Desks. These products require processing through three departments: Cutting, Assembly, and Painting. These three departments have limited working time to 300 hours, 450 hours, and 200 hours per week respectively. Each table requi

ABC Manufacturing Company produces three products: Tables, Chairs, and Desks. These products require processing through three departments: Cutting, Assembly, and Painting. These three departments have limited working time to 300 hours, 450 hours, and 200 hours per week respectively. Each table requires 4 hours for cutting, 5 hours for assembly, and 1 hour for painting and contributes Rs. 1000 to profit. Each chair requires 3 hours for cutting, 4 hours for assembly, and 1 hour for painting and contributes Rs. 800 to profit. Each desk requires 2 hours for cutting, 3 hours for assembly, and 2 hours for painting and contributes Rs. 1200 to profit. To maintain balance, the total production of all three products must not exceed 150 units per week. Formulate objective (profit) function and constraints for this LPP. [5]

Operations ResearchChapter 2: Linear Programming ProblemsFormulation of linear programming problemsNumerical: LPP formulation

Given

Products: Tables ($x_1$), Chairs ($x_2$), Desks ($x_3$)

Department time limits per week:

  • Cutting: 300 hours
  • Assembly: 450 hours
  • Painting: 200 hours

Resource requirements and profit:

ProductCutting (hr)Assembly (hr)Painting (hr)Profit (Rs.)
Table ($x_1$)4511000
Chair ($x_2$)341800
Desk ($x_3$)2321200

Balance constraint: Total production $\leq 150$ units per week.


STEP 2 - SOLVE: LPP Formulation

Decision Variables

Let:

  • $x_1$ = number of Tables produced per week
  • $x_2$ = number of Chairs produced per week
  • $x_3$ = number of Desks produced per week

Objective Function (Maximize Profit)

$$\text{Maximize } Z = 1000x_1 + 800x_2 + 1200x_3 \quad \text{(Rs. per week)}$$

Constraints

Cutting department (300 hours): $$4x_1 + 3x_2 + 2x_3 \leq 300$$

Assembly department (450 hours): $$5x_1 + 4x_2 + 3x_3 \leq 450$$

Painting department (200 hours): $$1x_1 + 1x_2 + 2x_3 \leq 200$$

Production balance (max 150 total units): $$x_1 + x_2 + x_3 \leq 150$$

Non-negativity: $$x_1, x_2, x_3 \geq 0$$

Complete Model

$$\text{Max } Z = 1000x_1 + 800x_2 + 1200x_3$$

Subject to: $$ \begin{aligned} 4x_1 + 3x_2 + 2x_3 &\leq 300 \ 5x_1 + 4x_2 + 3x_3 &\leq 450 \ x_1 + x_2 + 2x_3 &\leq 200 \ x_1 + x_2 + x_3 &\leq 150 \ x_1, x_2, x_3 &\geq 0 \end{aligned} $$

All coefficients match the given data exactly. The formulation is correct and complete.