Operations Research208010 marksNumerical: PERT network analysisPERT network diagrams

PERT Network Analysis Problem A project consists of nine activities whose time estimates (in weeks) and other characteristics are given below: | Activities | A | B | C | D | E | F | G | H | I | |---|---|---|---|---|---|---|---|---|---| | Preceding activities | - | - | - | A | A | B, D | B, D | C, F

PERT Network Analysis Problem

A project consists of nine activities whose time estimates (in weeks) and other characteristics are given below:

ActivitiesABCDEFGHI
Preceding activities---AAB, DB, DC, FE
Optimistic time2662118394
Most likely time46125141061510
Pessimistic time66248231292716

(a) Show the PERT network diagram for the project.

(b) Identify the critical activities.

(c) What is the expected project completing time and its variance?

[10]

Activity Predecessors a (opt) m (likely) b (pess) ------------------------------------------------------ A - 2 4 6 B - 6 6 6 C - 6 12 24 D A 2 5 8 E A 11 14 23 F B, D 8 10 12 G B, D 3 6 9 H C, F 9 15 27 I E 4 10 16 Note: Activities G and I have no successors, so they are terminal along with H. $$...