The TechZone Software Company combines two key resources - Front-End Developers (A) and Back-End Developers (B) - to complete a software system that must involve exactly 150 person-hours of total work. Each Front-End Developer hour costs Rs. 2,000, and each Back-End Developer hour costs Rs. 8,000. T

The TechZone Software Company combines two key resources - Front-End Developers (A) and Back-End Developers (B) - to complete a software system that must involve exactly 150 person-hours of total work. Each Front-End Developer hour costs Rs. 2,000, and each Back-End Developer hour costs Rs. 8,000. The company must use at least 14 hours of Back-End work and no more than 20 hours of Front-End work in a project. Formulate objective function and constraints of this LPP. [5]

Operations ResearchChapter 2: Linear Programming ProblemsFormulation of linear programming problemsNumerical: LPP formulation

Given

Decision variables:

  • $A$ = number of Front-End Developer hours
  • $B$ = number of Back-End Developer hours

Numeric inputs:

  • Total work required: exactly 150 person-hours
  • Cost per Front-End hour: Rs. 2,000
  • Cost per Back-End hour: Rs. 8,000
  • Minimum Back-End work: at least 14 hours
  • Maximum Front-End work: no more than 20 hours

STEP 2 - Formulation

Objective Function

Since costs are involved and the goal is efficiency, the company seeks to minimize total cost:

$$\text{Minimize } Z = 2000A + 8000B$$

where:

  • $2000A$ = total cost of Front-End Developer hours
  • $8000B$ = total cost of Back-End Developer hours

Constraints

1. Total work requirement (exactly 150 person-hours): $$A + B = 150$$

2. Minimum Back-End Developer hours (at least 14): $$B \geq 14$$

3. Maximum Front-End Developer hours (no more than 20): $$A \leq 20$$

4. Non-negativity: $$A \geq 0, \quad B \geq 0$$


Complete LPP Formulation

$$\boxed{\text{Minimize } Z = 2000A + 8000B}$$

Subject to: $$A + B = 150$$ $$B \geq 14$$ $$A \leq 20$$ $$A, B \geq 0$$

Feasibility note: With $A \leq 20$ and $A + B = 150$, we get $B = 150 - A \geq 130$, which automatically satisfies $B \geq 14$. So the binding constraint on cost is $A \leq 20$. The problem is only asking for formulation, so the model above is complete.