Critical Path Analysis The following activities must be completed to complete the project. Determine the critical path and time duration of the project. | Activity | Predecessor | Time (in a week) | |----------|-------------|-----------------| | A | - | 3 | | B | - | 8 | | C | A,B | 4 | | D | B | 2

Critical Path Analysis

The following activities must be completed to complete the project. Determine the critical path and time duration of the project.

ActivityPredecessorTime (in a week)
A-3
B-8
CA,B4
DB2
EA1
FC7
GE,F5
HD,F6
IG,H8
JI9

[5]

Operations ResearchChapter 5: Network Analysis and Project ManagementCritical path identificationNumerical: Critical path method

Critical Path Analysis

Given

ActivityPredecessorDuration (weeks)
A-3
B-8
CA, B4
DB2
EA1
FC7
GE, F5
HD, F6
IG, H8
JI9

Step 2: Forward Pass (Earliest Times)

$ES$ = max of predecessors' $EF$; $EF = ES + \text{duration}$.

ActivityDurESEF
A303
B808
C4max(3,8)=812
D2810
E134
F71219
G5max(4,19)=1924
H6max(10,19)=1925
I8max(24,25)=2533
J93342

Project completion time = 42 weeks

Step 3: Backward Pass (Latest Times)

Project finish $LF = 42$. $LF$ = min of successors' $LS$; $LS = LF - \text{duration}$; Slack $= LS - ES$.

Successor mapping:

  • J โ†’ none; I โ†’ J; G, H โ†’ I; F โ†’ G, H; E โ†’ G; D โ†’ H; C โ†’ F; A โ†’ C, E; B โ†’ C, D
ActivityDurLFLSSlack
J942330
I833250
H625190
G525201
F7min(20,19)=19120
E1201915
D219177
C41280
A3min(8,19)=852
B8min(8,17)=800

Step 4: Identify Critical Path

Activities with Slack = 0: B, C, F, H, I, J.

$$\textbf{Critical Path: } B \to C \to F \to H \to I \to J$$

Duration check: $$8 + 4 + 7 + 6 + 8 + 9 = 42 \text{ weeks}$$

Final Answer

  • Critical Path: $B \to C \to F \to H \to I \to J$
  • Project Duration: $42$ weeks