Operations Research20815 marksNumerical: Critical path methodCritical path identification

Critical Path Analysis The following activities must be completed to complete the project. Determine the critical path and time duration of the project. | Activity | Predecessor | Time (in a week) | |----------|-------------|-----------------| | A | - | 3 | | B | - | 8 | | C | A,B | 4 | | D | B | 2

Critical Path Analysis

The following activities must be completed to complete the project. Determine the critical path and time duration of the project.

ActivityPredecessorTime (in a week)
A-3
B-8
CA,B4
DB2
EA1
FC7
GE,F5
HD,F6
IG,H8
JI9

[5]

Activity Predecessor Duration (weeks) ----------------------------------------- A - 3 B - 8 C A, B 4 D B 2 E A 1 F C 7 G E, F 5 H D, F 6 I G, H 8 J I 9 $ES$ = max of predecessors' $EF$; $EF = ES + \text{duration}$. Activity Dur ES EF ----------------------- A 3 0 3 B 8 0 8 C 4 max(3,8)=8 12 D 2 8...

Up nextA bank operates a single-channel queuing system with customers arriving at a rate of 6 per