ORS255 ยท 2081 ยท 5 marks
Critical Path Analysis The following activities must be completed to complete the project. Determine the critical path and time duration of the project. | Activity | Predecessor | Time (in a week) | |----------|-------------|-----------------| | A | - | 3 | | B | - | 8 | | C | A,B | 4 | | D | B | 2
Critical Path Analysis
The following activities must be completed to complete the project. Determine the critical path and time duration of the project.
| Activity | Predecessor | Time (in a week) |
|---|---|---|
| A | - | 3 |
| B | - | 8 |
| C | A,B | 4 |
| D | B | 2 |
| E | A | 1 |
| F | C | 7 |
| G | E,F | 5 |
| H | D,F | 6 |
| I | G,H | 8 |
| J | I | 9 |
[5]
Critical Path Analysis
Given
| Activity | Predecessor | Duration (weeks) |
|---|---|---|
| A | - | 3 |
| B | - | 8 |
| C | A, B | 4 |
| D | B | 2 |
| E | A | 1 |
| F | C | 7 |
| G | E, F | 5 |
| H | D, F | 6 |
| I | G, H | 8 |
| J | I | 9 |
Step 2: Forward Pass (Earliest Times)
$ES$ = max of predecessors' $EF$; $EF = ES + \text{duration}$.
| Activity | Dur | ES | EF |
|---|---|---|---|
| A | 3 | 0 | 3 |
| B | 8 | 0 | 8 |
| C | 4 | max(3,8)=8 | 12 |
| D | 2 | 8 | 10 |
| E | 1 | 3 | 4 |
| F | 7 | 12 | 19 |
| G | 5 | max(4,19)=19 | 24 |
| H | 6 | max(10,19)=19 | 25 |
| I | 8 | max(24,25)=25 | 33 |
| J | 9 | 33 | 42 |
Project completion time = 42 weeks
Step 3: Backward Pass (Latest Times)
Project finish $LF = 42$. $LF$ = min of successors' $LS$; $LS = LF - \text{duration}$; Slack $= LS - ES$.
Successor mapping:
- J โ none; I โ J; G, H โ I; F โ G, H; E โ G; D โ H; C โ F; A โ C, E; B โ C, D
| Activity | Dur | LF | LS | Slack |
|---|---|---|---|---|
| J | 9 | 42 | 33 | 0 |
| I | 8 | 33 | 25 | 0 |
| H | 6 | 25 | 19 | 0 |
| G | 5 | 25 | 20 | 1 |
| F | 7 | min(20,19)=19 | 12 | 0 |
| E | 1 | 20 | 19 | 15 |
| D | 2 | 19 | 17 | 7 |
| C | 4 | 12 | 8 | 0 |
| A | 3 | min(8,19)=8 | 5 | 2 |
| B | 8 | min(8,17)=8 | 0 | 0 |
Step 4: Identify Critical Path
Activities with Slack = 0: B, C, F, H, I, J.
$$\textbf{Critical Path: } B \to C \to F \to H \to I \to J$$
Duration check: $$8 + 4 + 7 + 6 + 8 + 9 = 42 \text{ weeks}$$
Final Answer
- Critical Path: $B \to C \to F \to H \to I \to J$
- Project Duration: $42$ weeks