ORS255 · 2079 · 10 marks
Network Diagram and Critical Path Analysis
Network Diagram and Critical Path Analysis
Network Analysis - Critical Path Method
Given
| Activity | Predecessor | Duration (weeks) |
|---|---|---|
| A | - | 5 |
| B | - | 12 |
| C | A | 6 |
| D | B | 3 |
| E | A, D | 2 |
| F | B | 6 |
| G | C, E, F | 14 |
| H | G | 22 |
Step 2: Forward Pass (ES, EF)
Using $EF = ES + t$ and $ES = \max(EF \text{ of predecessors})$:
| Activity | Dur | Predecessor | ES | EF |
|---|---|---|---|---|
| A | 5 | - | 0 | 5 |
| B | 12 | - | 0 | 12 |
| C | 6 | A | 5 | 11 |
| D | 3 | B | 12 | 15 |
| E | 2 | A, D | max(5,15)=15 | 17 |
| F | 6 | B | 12 | 18 |
| G | 14 | C,E,F | max(11,17,18)=18 | 32 |
| H | 22 | G | 32 | 54 |
Project completion time = 54 weeks
Step 3: Backward Pass (LF, LS)
Using $LS = LF - t$ and $LF = \min(LS \text{ of successors})$. Project LF = 54.
Successor mapping:
- H → end; G → H; C, E, F → G; D → E; A → C, E; B → D, F
| Activity | Dur | Successors | LF | LS |
|---|---|---|---|---|
| H | 22 | - | 54 | 32 |
| G | 14 | H | 32 | 18 |
| F | 6 | G | 18 | 12 |
| E | 2 | G | 18 | 16 |
| C | 6 | G | 18 | 12 |
| D | 3 | E | 16 | 13 |
| B | 12 | D, F | min(13,12)=12 | 0 |
| A | 5 | C, E | min(12,16)=12 | 7 |
Step 4: Slack and Critical Activities
$\text{Slack} = LS - ES$
| Activity | ES | LS | Slack | Critical? |
|---|---|---|---|---|
| A | 0 | 7 | 7 | No |
| B | 0 | 0 | 0 | Yes |
| C | 5 | 12 | 7 | No |
| D | 12 | 13 | 1 | No |
| E | 15 | 16 | 1 | No |
| F | 12 | 12 | 0 | Yes |
| G | 18 | 18 | 0 | Yes |
| H | 32 | 32 | 0 | Yes |
Step 5: Critical Path
Critical activities (zero slack): B, F, G, H
$$\text{Critical Path: } B \rightarrow F \rightarrow G \rightarrow H$$
Verification of length: $$12 + 6 + 14 + 22 = 54 \text{ weeks}$$
Network Diagram
A(5) ── C(6) ─┐
/ │
Start │
\ ├── G(14) ── H(22) ── End
B(12) ─ D(3) ─ E(2) ┐
\ │
F(6) ─────────┘
Answer Summary
| Item | Result |
|---|---|
| Minimum Project Duration | 54 weeks |
| Critical Activities | B, F, G, H |
| Critical Path | B → F → G → H |
Check the slack before calling an activity critical: activity A has slack = 7 (LS = 7, ES = 0), so A is not critical. With a project duration of 54 weeks and critical path B -> F -> G -> H, the critical activities are only B, F, G, H.