2079 2

ORS255 · 2079 · 10 marks

Network Diagram and Critical Path Analysis

Network Diagram and Critical Path Analysis

Operations ResearchChapter 5: Network Analysis and Project ManagementCritical path identificationNumerical: CPM network diagram

Network Analysis - Critical Path Method

Given

ActivityPredecessorDuration (weeks)
A-5
B-12
CA6
DB3
EA, D2
FB6
GC, E, F14
HG22

Step 2: Forward Pass (ES, EF)

Using $EF = ES + t$ and $ES = \max(EF \text{ of predecessors})$:

ActivityDurPredecessorESEF
A5-05
B12-012
C6A511
D3B1215
E2A, Dmax(5,15)=1517
F6B1218
G14C,E,Fmax(11,17,18)=1832
H22G3254

Project completion time = 54 weeks

Step 3: Backward Pass (LF, LS)

Using $LS = LF - t$ and $LF = \min(LS \text{ of successors})$. Project LF = 54.

Successor mapping:

  • H → end; G → H; C, E, F → G; D → E; A → C, E; B → D, F
ActivityDurSuccessorsLFLS
H22-5432
G14H3218
F6G1812
E2G1816
C6G1812
D3E1613
B12D, Fmin(13,12)=120
A5C, Emin(12,16)=127

Step 4: Slack and Critical Activities

$\text{Slack} = LS - ES$

ActivityESLSSlackCritical?
A077No
B000Yes
C5127No
D12131No
E15161No
F12120Yes
G18180Yes
H32320Yes

Step 5: Critical Path

Critical activities (zero slack): B, F, G, H

$$\text{Critical Path: } B \rightarrow F \rightarrow G \rightarrow H$$

Verification of length: $$12 + 6 + 14 + 22 = 54 \text{ weeks}$$

Network Diagram

        A(5) ── C(6) ─┐
       /              │
Start                 │
       \              ├── G(14) ── H(22) ── End
        B(12) ─ D(3) ─ E(2) ┐
             \              │
              F(6) ─────────┘

Answer Summary

ItemResult
Minimum Project Duration54 weeks
Critical ActivitiesB, F, G, H
Critical PathB → F → G → H

Check the slack before calling an activity critical: activity A has slack = 7 (LS = 7, ES = 0), so A is not critical. With a project duration of 54 weeks and critical path B -> F -> G -> H, the critical activities are only B, F, G, H.