ORS255 · 2081 · 5 marks
Project Completion Time and Variance Analysis A project consists of nine activities whose time estimates (in weeks) and other characteristics are given below. What is the expected project completion time and its variance? | Activities | A | B | C | D | E | F | G | H | I | |---|---|---|---|---|---|--
Project Completion Time and Variance Analysis
A project consists of nine activities whose time estimates (in weeks) and other characteristics are given below. What is the expected project completion time and its variance?
| Activities | A | B | C | D | E | F | G | H | I |
|---|---|---|---|---|---|---|---|---|---|
| Preceding activities | - | - | - | A | A | B,D | B,D | C,F | E |
| Optimistic time | 2 | 6 | 6 | 2 | 11 | 8 | 3 | 9 | 4 |
| Most likely time | 4 | 6 | 12 | 5 | 14 | 10 | 6 | 15 | 10 |
| Pessimistic time | 6 | 6 | 24 | 8 | 23 | 12 | 9 | 27 | 16 |
[5]
Operations ResearchChapter 5: Network Analysis and Project ManagementPERT network diagramsNumerical: PERT expected time variance