Project Completion Time and Variance Analysis A project consists of nine activities whose time estimates (in weeks) and other characteristics are given below. What is the expected project completion time and its variance? | Activities | A | B | C | D | E | F | G | H | I | |---|---|---|---|---|---|--

Project Completion Time and Variance Analysis

A project consists of nine activities whose time estimates (in weeks) and other characteristics are given below. What is the expected project completion time and its variance?

ActivitiesABCDEFGHI
Preceding activities---AAB,DB,DC,FE
Optimistic time2662118394
Most likely time46125141061510
Pessimistic time66248231292716

[5]

Activity Predecessors $to$ $tm$ $tp$ -------------------------------------------- A - 2 4 6 B - 6 6 6 C - 6 12 24 D A 2 5 8 E A 11 14 23 F B, D 8 10 12 G B, D 3 6 9 H C, F 9 15 27 I E 4 10 16 $$te = \frac{to + 4tm + tp}{6}, \qquad \sigma^2 = \left(\frac{tp - to}{6}\right)^2$$ Activity $te$