ORS255 · 2080 · 5 marks
Network Diagram and Critical Path Analysis
Network Diagram and Critical Path Analysis
Network Diagram and Critical Path Analysis
Given
| Activity | A | B | C | D | E | F | G |
|---|---|---|---|---|---|---|---|
| Predecessors | - | A | A | A | B,C | C,D | E,F |
| Time (days) | 7 | 4 | 5 | 6 | 7 | 5 | 6 |
Solution
Network Diagram
B(4)
┌────────► ③
│ \
①──A(7)──►②──C(5)──►④───E(7)──►⑤──G(6)──►⑥
│ \ /
│ \/
└─D(6)──►(F merges C,D)──F(5)──►⑤
Logical structure of dependencies:
- A starts the project.
- B, C, D all follow A.
- E follows B and C.
- F follows C and D.
- G follows E and F (final activity).
Forward Pass (Earliest Times)
$$ES = \max(EF \text{ of all predecessors}), \quad EF = ES + t$$
- A: ES = 0, EF = 0 + 7 = 7
- B: ES = 7, EF = 7 + 4 = 11
- C: ES = 7, EF = 7 + 5 = 12
- D: ES = 7, EF = 7 + 6 = 13
- E: ES = max(EF$_B$, EF$_C$) = max(11, 12) = 12, EF = 12 + 7 = 19
- F: ES = max(EF$_C$, EF$_D$) = max(12, 13) = 13, EF = 13 + 5 = 18
- G: ES = max(EF$_E$, EF$_F$) = max(19, 18) = 19, EF = 19 + 6 = 25
Project Duration = 25 days
Backward Pass (Latest Times)
$$LF = \min(LS \text{ of all successors}), \quad LS = LF - t$$
- G: LF = 25, LS = 25 - 6 = 19
- F: LF = 19, LS = 19 - 5 = 14
- E: LF = 19, LS = 19 - 7 = 12
- D: LF = LS$_F$ = 14, LS = 14 - 6 = 8
- C: LF = min(LS$_E$, LS$_F$) = min(12, 14) = 12, LS = 12 - 5 = 7
- B: LF = LS$_E$ = 12, LS = 12 - 4 = 8
- A: LF = min(LS$_B$, LS$_C$, LS$_D$) = min(8, 7, 8) = 7, LS = 7 - 7 = 0
Slack Table
| Activity | ES | EF | LS | LF | Slack (LS-ES) | Critical? |
|---|---|---|---|---|---|---|
| A | 0 | 7 | 0 | 7 | 0 | ✓ |
| B | 7 | 11 | 8 | 12 | 1 | ✗ |
| C | 7 | 12 | 7 | 12 | 0 | ✓ |
| D | 7 | 13 | 8 | 14 | 1 | ✗ |
| E | 12 | 19 | 12 | 19 | 0 | ✓ |
| F | 13 | 18 | 14 | 19 | 1 | ✗ |
| G | 19 | 25 | 19 | 25 | 0 | ✓ |
Critical Path
Activities with zero slack: A → C → E → G
$$\text{Duration} = 7 + 5 + 7 + 6 = 25 \text{ days}$$
Bottleneck Activities
Bottleneck (critical) activities with zero slack that control the project completion:
$$\boxed{A,\ C,\ E,\ G}$$
Any delay in these directly delays the whole project.
Keep the node table consistent with the forward pass: values such as E at ES = 11, EF = 18, or G at ES = 13, EF = 19, contradict the forward pass computed above. The critical path A -> C -> E -> G and the 25-day duration are unaffected, but an internally inconsistent table loses marks.