2080 4

ORS255 · 2080 · 5 marks

Network Diagram and Critical Path Analysis

Network Diagram and Critical Path Analysis

Operations ResearchChapter 5: Network Analysis and Project ManagementCritical path identificationNumerical: Network diagram critical path

Network Diagram and Critical Path Analysis

Given

ActivityABCDEFG
Predecessors-AAAB,CC,DE,F
Time (days)7456756

Solution

Network Diagram

                B(4)
             ┌────────► ③
             │           \
  ①──A(7)──►②──C(5)──►④───E(7)──►⑤──G(6)──►⑥
             │      \  /
             │       \/
             └─D(6)──►(F merges C,D)──F(5)──►⑤

Logical structure of dependencies:

  • A starts the project.
  • B, C, D all follow A.
  • E follows B and C.
  • F follows C and D.
  • G follows E and F (final activity).

Forward Pass (Earliest Times)

$$ES = \max(EF \text{ of all predecessors}), \quad EF = ES + t$$

  • A: ES = 0, EF = 0 + 7 = 7
  • B: ES = 7, EF = 7 + 4 = 11
  • C: ES = 7, EF = 7 + 5 = 12
  • D: ES = 7, EF = 7 + 6 = 13
  • E: ES = max(EF$_B$, EF$_C$) = max(11, 12) = 12, EF = 12 + 7 = 19
  • F: ES = max(EF$_C$, EF$_D$) = max(12, 13) = 13, EF = 13 + 5 = 18
  • G: ES = max(EF$_E$, EF$_F$) = max(19, 18) = 19, EF = 19 + 6 = 25

Project Duration = 25 days

Backward Pass (Latest Times)

$$LF = \min(LS \text{ of all successors}), \quad LS = LF - t$$

  • G: LF = 25, LS = 25 - 6 = 19
  • F: LF = 19, LS = 19 - 5 = 14
  • E: LF = 19, LS = 19 - 7 = 12
  • D: LF = LS$_F$ = 14, LS = 14 - 6 = 8
  • C: LF = min(LS$_E$, LS$_F$) = min(12, 14) = 12, LS = 12 - 5 = 7
  • B: LF = LS$_E$ = 12, LS = 12 - 4 = 8
  • A: LF = min(LS$_B$, LS$_C$, LS$_D$) = min(8, 7, 8) = 7, LS = 7 - 7 = 0

Slack Table

ActivityESEFLSLFSlack (LS-ES)Critical?
A07070✓
B7118121✗
C7127120✓
D7138141✗
E121912190✓
F131814191✗
G192519250✓

Critical Path

Activities with zero slack: A → C → E → G

$$\text{Duration} = 7 + 5 + 7 + 6 = 25 \text{ days}$$

Bottleneck Activities

Bottleneck (critical) activities with zero slack that control the project completion:

$$\boxed{A,\ C,\ E,\ G}$$

Any delay in these directly delays the whole project.

Keep the node table consistent with the forward pass: values such as E at ES = 11, EF = 18, or G at ES = 13, EF = 19, contradict the forward pass computed above. The critical path A -> C -> E -> G and the 25-day duration are unaffected, but an internally inconsistent table loses marks.