Operations Research2080.25 marksNumerical: Critical path methodCritical path identification

Critical Path Analysis The following activities must be completed in the order to complete the project. Determine critical path and time duration of the project. | Activity | A | B | C | D | E | F | G | H | I | J | |----------|---|---|---|---|---|---|---|---|---|---| | Predecessor | - | - | A,B | B

Critical Path Analysis

The following activities must be completed in the order to complete the project. Determine critical path and time duration of the project.

ActivityABCDEFGHIJ
Predecessor--A,BBACE,FD,FG,HI
Time (in week)3842175689

[5]

Activity Predecessor(s) Duration (weeks) ------------------------------------------- A - 3 B - 8 C A, B 4 D B 2 E A 1 F C 7 G E, F 5 H D, F 6 I G, H 8 J I 9 $EF = ES + \text{Duration}$, and $ES = \max(EF \text{ of predecessors})$. Activity Predecessors ES EF ------------------------------- A - 0 ...