Operations Research20795 marksNetwork diagram construction

Network Diagram Project The following activities must be completed in order to complete the project. Draw network diagram to reflect the inter relationship between activities of the project. | Activity | P | Q | R | S | T | U | V | W | X | |----------|---|---|-------|---|---|---|-------|-------|----

Network Diagram Project

The following activities must be completed in order to complete the project. Draw network diagram to reflect the inter relationship between activities of the project.

ActivityPQRSTUVWX
Predecessor--P, QQPRT, US, UV, W

[5]

To draw the network diagram, I need to identify the precedence relationships and create nodes and arrows showing the sequence of activities. Activity Predecessor Dependencies ------------------------------------- P - Start (no predecessor) Q - Start (no predecessor) R P, Q Follows both P and Q S ...