5 Network Analysis And Project Management

Operations Research ยท Unit 5

Network Analysis and Project Management

Exam-focused notes for Network Analysis and Project Management (Operations Research, ORS255): what the TU syllabus asks and how it has actually been tested, with 10 solved past questions from this unit.

Network Analysis and Project Management in short

A project is a set of activities that must follow a given order, such as building a bridge or launching software. Network analysis draws the order as a diagram and finds the shortest time in which the whole project can finish. The two main methods are CPM and PERT.

Network Analysis and Project Management: notes

Network diagram construction

A network diagram shows activities and their order. In the arrow method, each activity is an arrow, and each event is a circle that marks the start or finish of activities.

Rules for drawing:

  • Each activity is one arrow and has a tail event and a head event.
  • The network has one start event and one end event.
  • An activity can start only after all its predecessors finish.
  • Two activities must not share the same pair of tail and head events.
  • A dummy activity (dotted arrow, zero time) shows order or avoids a clash. It uses no time and no resource.
  • No loops are allowed, since time cannot go backward.

Activity relationships and predecessors

A predecessor is an activity that must finish before another begins. The table below is the usual input to a network problem.

ActivityPredecessorDuration (days)
Anone4
Bnone6
CA5
DA8
EB, C7
FD, E4
GE5

The diagram below uses numbered events. Dummy arrow 5-6 keeps F waiting for E, while G waits for E only.

A: 1 -> 2     B: 1 -> 3     C: 2 -> 3     D: 2 -> 6
E: 3 -> 5     G: 5 -> 7     F: 6 -> 7     Dummy: 5 -> 6

What this unit covers

  • Network diagram construction
  • Activity relationships and predecessors
  • Critical path identification
  • Critical activities and bottleneck activities
  • Slack time and float calculations
  • Project completion time estimation
  • PERT network diagrams
  • Time duration analysis

Critical path identification

2082 ยท 5 marks

Project Network Analysis

The table gives the information about the activities, their predecessors and time duration required to complete the activities of the project. Find the shortest time duration of the project within which the project can be completed.

ActivityABCDEFG
Predecessor--BBBEA,D,C
Time (in days)1881414161020

[5]

Activity Predecessor Duration (days) ---------------------------------------- A - 18 B - 8 C B 14 D B 14 E B 16 F E 10 G A, D, C 20 $EF = ES + \text{Duration}$, and $ES = \max(EF \text{ of predecessors})$ Activity Predecessor ES EF ------------------------------- A - 0 18 B - 0 8 C B 8 22 D B 8 2...

Open this answer on its own page โ†’

2081 ยท 5 marks

Critical Path Analysis

The following activities must be completed to complete the project. Determine the critical path and time duration of the project.

ActivityPredecessorTime (in a week)
A-3
B-8
CA,B4
DB2
EA1
FC7
GE,F5
HD,F6
IG,H8
JI9

[5]

Show solved answer

Critical Path Analysis

Given

ActivityPredecessorDuration (weeks)
A-3
B-8
CA, B4
DB2
EA1
FC7
GE, F5
HD, F6
IG, H8
JI9

Step 2: Forward Pass (Earliest Times)

$ES$ = max of predecessors' $EF$; $EF = ES + \text{duration}$.

ActivityDurESEF
A303
B808
C4max(3,8)=812
D2810
E134
F71219
G5max(4,19)=1924
H6max(10,19)=1925
I8max(24,25)=2533
J93342

Project completion time = 42 weeks

Step 3: Backward Pass (Latest Times)

Project finish $LF = 42$. $LF$ = min of successors' $LS$; $LS = LF - \text{duration}$; Slack $= LS - ES$.

Successor mapping:

  • J โ†’ none; I โ†’ J; G, H โ†’ I; F โ†’ G, H; E โ†’ G; D โ†’ H; C โ†’ F; A โ†’ C, E; B โ†’ C, D
ActivityDurLFLSSlack
J942330
I833250
H625190
G525201
F7min(20,19)=19120
E1201915
D219177
C41280
A3min(8,19)=852
B8min(8,17)=800

Step 4: Identify Critical Path

Activities with Slack = 0: B, C, F, H, I, J.

$$\textbf{Critical Path: } B \to C \to F \to H \to I \to J$$

Duration check: $$8 + 4 + 7 + 6 + 8 + 9 = 42 \text{ weeks}$$

Final Answer

  • Critical Path: $B \to C \to F \to H \to I \to J$
  • Project Duration: $42$ weeks
Open this answer on its own page โ†’

2080 ยท 5 marks

Network Diagram and Critical Path Analysis

Show solved answer

Network Diagram and Critical Path Analysis

Given

ActivityABCDEFG
Predecessors-AAAB,CC,DE,F
Time (days)7456756

Solution

Network Diagram

                B(4)
             โ”Œโ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ–บ โ‘ข
             โ”‚           \
  โ‘ โ”€โ”€A(7)โ”€โ”€โ–บโ‘กโ”€โ”€C(5)โ”€โ”€โ–บโ‘ฃโ”€โ”€โ”€E(7)โ”€โ”€โ–บโ‘คโ”€โ”€G(6)โ”€โ”€โ–บโ‘ฅ
             โ”‚      \  /
             โ”‚       \/
             โ””โ”€D(6)โ”€โ”€โ–บ(F merges C,D)โ”€โ”€F(5)โ”€โ”€โ–บโ‘ค

Logical structure of dependencies:

  • A starts the project.
  • B, C, D all follow A.
  • E follows B and C.
  • F follows C and D.
  • G follows E and F (final activity).

Forward Pass (Earliest Times)

$$ES = \max(EF \text{ of all predecessors}), \quad EF = ES + t$$

  • A: ES = 0, EF = 0 + 7 = 7
  • B: ES = 7, EF = 7 + 4 = 11
  • C: ES = 7, EF = 7 + 5 = 12
  • D: ES = 7, EF = 7 + 6 = 13
  • E: ES = max(EF$_B$, EF$_C$) = max(11, 12) = 12, EF = 12 + 7 = 19
  • F: ES = max(EF$_C$, EF$_D$) = max(12, 13) = 13, EF = 13 + 5 = 18
  • G: ES = max(EF$_E$, EF$_F$) = max(19, 18) = 19, EF = 19 + 6 = 25

Project Duration = 25 days

Backward Pass (Latest Times)

$$LF = \min(LS \text{ of all successors}), \quad LS = LF - t$$

  • G: LF = 25, LS = 25 - 6 = 19
  • F: LF = 19, LS = 19 - 5 = 14
  • E: LF = 19, LS = 19 - 7 = 12
  • D: LF = LS$_F$ = 14, LS = 14 - 6 = 8
  • C: LF = min(LS$_E$, LS$_F$) = min(12, 14) = 12, LS = 12 - 5 = 7
  • B: LF = LS$_E$ = 12, LS = 12 - 4 = 8
  • A: LF = min(LS$_B$, LS$_C$, LS$_D$) = min(8, 7, 8) = 7, LS = 7 - 7 = 0

Slack Table

ActivityESEFLSLFSlack (LS-ES)Critical?
A07070โœ“
B7118121โœ—
C7127120โœ“
D7138141โœ—
E121912190โœ“
F131814191โœ—
G192519250โœ“

Critical Path

Activities with zero slack: A โ†’ C โ†’ E โ†’ G

$$\text{Duration} = 7 + 5 + 7 + 6 = 25 \text{ days}$$

Bottleneck Activities

Bottleneck (critical) activities with zero slack that control the project completion:

$$\boxed{A,\ C,\ E,\ G}$$

Any delay in these directly delays the whole project.

Keep the node table consistent with the forward pass: values such as E at ES = 11, EF = 18, or G at ES = 13, EF = 19, contradict the forward pass computed above. The critical path A -> C -> E -> G and the 25-day duration are unaffected, but an internally inconsistent table loses marks.

Open this answer on its own page โ†’

2079 ยท 10 marks

Network Diagram and Critical Path Analysis

Show solved answer

Network Analysis - Critical Path Method

Given

ActivityPredecessorDuration (weeks)
A-5
B-12
CA6
DB3
EA, D2
FB6
GC, E, F14
HG22

Step 2: Forward Pass (ES, EF)

Using $EF = ES + t$ and $ES = \max(EF \text{ of predecessors})$:

ActivityDurPredecessorESEF
A5-05
B12-012
C6A511
D3B1215
E2A, Dmax(5,15)=1517
F6B1218
G14C,E,Fmax(11,17,18)=1832
H22G3254

Project completion time = 54 weeks

Step 3: Backward Pass (LF, LS)

Using $LS = LF - t$ and $LF = \min(LS \text{ of successors})$. Project LF = 54.

Successor mapping:

  • H โ†’ end; G โ†’ H; C, E, F โ†’ G; D โ†’ E; A โ†’ C, E; B โ†’ D, F
ActivityDurSuccessorsLFLS
H22-5432
G14H3218
F6G1812
E2G1816
C6G1812
D3E1613
B12D, Fmin(13,12)=120
A5C, Emin(12,16)=127

Step 4: Slack and Critical Activities

$\text{Slack} = LS - ES$

ActivityESLSSlackCritical?
A077No
B000Yes
C5127No
D12131No
E15161No
F12120Yes
G18180Yes
H32320Yes

Step 5: Critical Path

Critical activities (zero slack): B, F, G, H

$$\text{Critical Path: } B \rightarrow F \rightarrow G \rightarrow H$$

Verification of length: $$12 + 6 + 14 + 22 = 54 \text{ weeks}$$

Network Diagram

        A(5) โ”€โ”€ C(6) โ”€โ”
       /              โ”‚
Start                 โ”‚
       \              โ”œโ”€โ”€ G(14) โ”€โ”€ H(22) โ”€โ”€ End
        B(12) โ”€ D(3) โ”€ E(2) โ”
             \              โ”‚
              F(6) โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”˜

Answer Summary

ItemResult
Minimum Project Duration54 weeks
Critical ActivitiesB, F, G, H
Critical PathB โ†’ F โ†’ G โ†’ H

Check the slack before calling an activity critical: activity A has slack = 7 (LS = 7, ES = 0), so A is not critical. With a project duration of 54 weeks and critical path B -> F -> G -> H, the critical activities are only B, F, G, H.

Open this answer on its own page โ†’

2080.2 ยท 5 marks

Critical Path Analysis

The following activities must be completed in the order to complete the project. Determine critical path and time duration of the project.

ActivityABCDEFGHIJ
Predecessor--A,BBACE,FD,FG,HI
Time (in week)3842175689

[5]

Show solved answer

Critical Path Analysis - Verified Solution

Given Data

ActivityPredecessor(s)Duration (weeks)
A-3
B-8
CA, B4
DB2
EA1
FC7
GE, F5
HD, F6
IG, H8
JI9

Step 1: Forward Pass (ES, EF)

$EF = ES + \text{Duration}$, and $ES = \max(EF \text{ of predecessors})$.

ActivityPredecessorsESEF
A-03
B-08
CA(3), B(8)812
DB(8)810
EA(3)34
FC(12)1219
GE(4), F(19)1924
HD(10), F(19)1925
IG(24), H(25)2533
JI(33)3342

Project duration = 42 weeks.

Step 2: Backward Pass (LF, LS)

$LS = LF - \text{Duration}$, and $LF = \min(LS \text{ of successors})$.

Successors:

  • J โ†’ (end)
  • I โ†’ J
  • H โ†’ I
  • G โ†’ I
  • F โ†’ G, H
  • E โ†’ G
  • D โ†’ H
  • C โ†’ F
  • B โ†’ C, D
  • A โ†’ C, E
ActivityLFLS
J4233
I3325
H2519
G2520
Fmin(20,19)=1912
E2019
D1917
C128
Bmin(8,17)=80
Amin(8,19)=85

Step 3: Slack (LS โˆ’ ES)

ActivityESLSSlackCritical?
A055No
B000Yes
C880Yes
D8179No
E31916No
F12120Yes
G19201No
H19190Yes
I25250Yes
J33330Yes

Step 4: Critical Path

Zero-slack activities: B โ†’ C โ†’ F โ†’ H โ†’ I โ†’ J

Check: $8 + 4 + 7 + 6 + 8 + 9 = 42$ weeks.

Result

  • Critical Path: $B \rightarrow C \rightarrow F \rightarrow H \rightarrow I \rightarrow J$
  • Project Duration: $42$ weeks
Open this answer on its own page โ†’

0 ยท 10 marks

Critical Path Analysis

The following activities must be completed in order to complete the project. Determine the critical path and time duration of the project based on slack time of the activity.

ActivityABCDEFGHIJ
Predecessor--A, BBACE, FD, FG, HI
Time (in days)3842175689

[10]

Activity A B C D E F G H I J ---------------------------------------- Predecessor โˆ’ โˆ’ A,B B A C E,F D,F G,H I Duration (days) 3 8 4 2 1 7 5 6 8 9 $ES = \max(EF \text{ of predecessors})$, $EF = ES + \text{Duration}$ Activity Dur ES EF ----------------------- A 3 0 3 B 8 0 8 C 4 max(3,8)=8 12 D 2 8...

Open this answer on its own page โ†’

PERT network diagrams

2081 ยท 5 marks

Project Completion Time and Variance Analysis

A project consists of nine activities whose time estimates (in weeks) and other characteristics are given below. What is the expected project completion time and its variance?

ActivitiesABCDEFGHI
Preceding activities---AAB,DB,DC,FE
Optimistic time2662118394
Most likely time46125141061510
Pessimistic time66248231292716

[5]

Activity Predecessors $to$ $tm$ $tp$ -------------------------------------------- A - 2 4 6 B - 6 6 6 C - 6 12 24 D A 2 5 8 E A 11 14 23 F B, D 8 10 12 G B, D 3 6 9 H C, F 9 15 27 I E 4 10 16 $$te = \frac{to + 4tm + tp}{6}, \qquad \sigma^2 = \left(\frac{tp - to}{6}\right)^2$$ Activity $te$

Open this answer on its own page โ†’

2080 ยท 10 marks

PERT Network Analysis Problem

A project consists of nine activities whose time estimates (in weeks) and other characteristics are given below:

ActivitiesABCDEFGHI
Preceding activities---AAB, DB, DC, FE
Optimistic time2662118394
Most likely time46125141061510
Pessimistic time66248231292716

(a) Show the PERT network diagram for the project.

(b) Identify the critical activities.

(c) What is the expected project completing time and its variance?

[10]

Activity Predecessors a (opt) m (likely) b (pess) ------------------------------------------------------ A - 2 4 6 B - 6 6 6 C - 6 12 24 D A 2 5 8 E A 11 14 23 F B, D 8 10 12 G B, D 3 6 9 H C, F 9 15 27 I E 4 10 16 Note: Activities G and I have no successors, so they are terminal along with H. $$...

Open this answer on its own page โ†’

Network diagram construction

2079 ยท 5 marks

Network Diagram Project

The following activities must be completed in order to complete the project. Draw network diagram to reflect the inter relationship between activities of the project.

ActivityPQRSTUVWX
Predecessor--P, QQPRT, US, UV, W

[5]

To draw the network diagram, I need to identify the precedence relationships and create nodes and arrows showing the sequence of activities. Activity Predecessor Dependencies ------------------------------------- P - Start (no predecessor) Q - Start (no predecessor) R P, Q Follows both P and Q S ...

Open this answer on its own page โ†’

0 ยท 5 marks

A work project consists of twelve activities labeled through L. Upon being asked to specify the order in which the jobs had to be done, the manager answered as follows: A, B, and C are the first activities of the project and can start simultaneously and immediately; A and B precede D while B precede E, F and H. Activities F and C precede G while E and H precede I and J. The activities C, D, F and J precede K which, in turn, precedes L. Further I, G and L are the terminal activities of the project. Draw a network diagram corresponding to the project. [5]

From the manager's specifications: Activity Predecessors ------------------------ A None (start) B None (start) C None (start) D A, B E B F B G F, C H B I E, H J E, H K C, D, F, J L K Terminal activities: I, G, L Level 0 (Start): A, B, C Level 1: D (from A, B), E (from B), F (from B), H (from B) ...

Open this answer on its own page โ†’