5 Network Analysis And Project Management

Operations Research · Unit 5

Network Analysis and Project Management

Exam-focused notes for Network Analysis and Project Management (Operations Research, ORS255): what the TU syllabus asks and how it has actually been tested, with 10 solved past questions from this unit.

What this unit covers

  • Network diagram construction
  • Activity relationships and predecessors
  • Critical path identification
  • Critical activities and bottleneck activities
  • Slack time and float calculations
  • Project completion time estimation
  • PERT network diagrams
  • Time duration analysis

Critical path identification

20825 marks

Project Network Analysis

The table gives the information about the activities, their predecessors and time duration required to complete the activities of the project. Find the shortest time duration of the project within which the project can be completed.

ActivityABCDEFG
Predecessor--BBBEA,D,C
Time (in days)1881414161020

[5]

Activity Predecessor Duration (days) ---------------------------------------- A - 18 B - 8 C B 14 D B 14 E B 16 F E 10 G A, D, C 20 $EF = ES + \text{Duration}$, and $ES = \max(EF \text{ of predecessors})$ Activity Predecessor ES EF -------------------------...

Full solved answer →
20815 marks

Critical Path Analysis

The following activities must be completed to complete the project. Determine the critical path and time duration of the project.

ActivityPredecessorTime (in a week)
A-3
B-8
CA,B4
DB2
EA1
FC7
GE,F5
HD,F6
IG,H8
JI9

[5]

Activity Predecessor Duration (weeks) ----------------------------------------- A - 3 B - 8 C A, B 4 D B 2 E A 1 F C 7 G E, F 5 H D, F 6 I G, H 8 J I 9 $ES$ = max of predecessors' $EF$; $EF = ES + \text{duration}$. Activity Dur ES EF -----------------------...

Full solved answer →
20805 marks

Network Diagram and Critical Path Analysis

Activity A B C D E F G ------------------------------- Predecessors - A A A B,C C,D E,F Time (days) 7 4 5 6 7 5 6 Logical structure of dependencies: - A starts the project. - B, C, D all follow A. - E follows B and C. - F follows C and D. - G follows E and ...

Full solved answer →
207910 marks

Network Diagram and Critical Path Analysis

Activity Predecessor Duration (weeks) ----------------------------------------- A - 5 B - 12 C A 6 D B 3 E A, D 2 F B 6 G C, E, F 14 H G 22 Using $EF = ES + t$ and $ES = \max(EF \text{ of predecessors})$: Activity Dur Predecessor ES EF ---------------------...

Full solved answer →
2080.25 marks

Critical Path Analysis

The following activities must be completed in the order to complete the project. Determine critical path and time duration of the project.

ActivityABCDEFGHIJ
Predecessor--A,BBACE,FD,FG,HI
Time (in week)3842175689

[5]

Activity Predecessor(s) Duration (weeks) ------------------------------------------- A - 3 B - 8 C A, B 4 D B 2 E A 1 F C 7 G E, F 5 H D, F 6 I G, H 8 J I 9 $EF = ES + \text{Duration}$, and $ES = \max(EF \text{ of predecessors})$. Activity Predecessors ES E...

Full solved answer →
010 marks

Critical Path Analysis

The following activities must be completed in order to complete the project. Determine the critical path and time duration of the project based on slack time of the activity.

ActivityABCDEFGHIJ
Predecessor--A, BBACE, FD, FG, HI
Time (in days)3842175689

[10]

Activity A B C D E F G H I J ---------------------------------------- Predecessor − − A,B B A C E,F D,F G,H I Duration (days) 3 8 4 2 1 7 5 6 8 9 $ES = \max(EF \text{ of predecessors})$, $EF = ES + \text{Duration}$ Activity Dur ES EF -----------------------...

Full solved answer →

PERT network diagrams

20815 marks

Project Completion Time and Variance Analysis

A project consists of nine activities whose time estimates (in weeks) and other characteristics are given below. What is the expected project completion time and its variance?

ActivitiesABCDEFGHI
Preceding activities---AAB,DB,DC,FE
Optimistic time2662118394
Most likely time46125141061510
Pessimistic time66248231292716

[5]

Activity Predecessors $to$ $tm$ $tp$ -------------------------------------------- A - 2 4 6 B - 6 6 6 C - 6 12 24 D A 2 5 8 E A 11 14 23 F B, D 8 10 12 G B, D 3 6 9 H C, F 9 15 27 I E 4 10 16 $$te = \frac{to + 4tm + tp}{6}, \qquad \sigma^2 = \left(\frac{tp ...

Full solved answer →
208010 marks

PERT Network Analysis Problem

A project consists of nine activities whose time estimates (in weeks) and other characteristics are given below:

ActivitiesABCDEFGHI
Preceding activities---AAB, DB, DC, FE
Optimistic time2662118394
Most likely time46125141061510
Pessimistic time66248231292716

(a) Show the PERT network diagram for the project.

(b) Identify the critical activities.

(c) What is the expected project completing time and its variance?

[10]

Activity Predecessors a (opt) m (likely) b (pess) ------------------------------------------------------ A - 2 4 6 B - 6 6 6 C - 6 12 24 D A 2 5 8 E A 11 14 23 F B, D 8 10 12 G B, D 3 6 9 H C, F 9 15 27 I E 4 10 16 Note: Activities G and I have no successor...

Full solved answer →

Network diagram construction

20795 marks

Network Diagram Project

The following activities must be completed in order to complete the project. Draw network diagram to reflect the inter relationship between activities of the project.

ActivityPQRSTUVWX
Predecessor--P, QQPRT, US, UV, W

[5]

To draw the network diagram, I need to identify the precedence relationships and create nodes and arrows showing the sequence of activities. Activity Predecessor Dependencies ------------------------------------- P - Start (no predecessor) Q - Start (no pre...

Full solved answer →
05 marks

A work project consists of twelve activities labeled through L. Upon being asked to specify the order in which the jobs had to be done, the manager answered as follows: A, B, and C are the first activities of the project and can start simultaneously and immediately; A and B precede D while B precede E, F and H. Activities F and C precede G while E and H precede I and J. The activities C, D, F and J precede K which, in turn, precedes L. Further I, G and L are the terminal activities of the project. Draw a network diagram corresponding to the project. [5]

From the manager's specifications: Activity Predecessors ------------------------ A None (start) B None (start) C None (start) D A, B E B F B G F, C H B I E, H J E, H K C, D, F, J L K Terminal activities: I, G, L Level 0 (Start): A, B, C Level 1: D (from A,...

Full solved answer →