Operations Research ยท Unit 5
Network Analysis and Project Management
Exam-focused notes for Network Analysis and Project Management (Operations Research, ORS255): what the TU syllabus asks and how it has actually been tested, with 10 solved past questions from this unit.
Network Analysis and Project Management in short
A project is a set of activities that must follow a given order, such as building a bridge or launching software. Network analysis draws the order as a diagram and finds the shortest time in which the whole project can finish. The two main methods are CPM and PERT.
What this unit covers
- Network diagram construction
- Activity relationships and predecessors
- Critical path identification
- Critical activities and bottleneck activities
- Slack time and float calculations
- Project completion time estimation
- PERT network diagrams
- Time duration analysis
Critical path identification
2082 ยท 5 marks
Project Network Analysis
The table gives the information about the activities, their predecessors and time duration required to complete the activities of the project. Find the shortest time duration of the project within which the project can be completed.
| Activity | A | B | C | D | E | F | G |
|---|---|---|---|---|---|---|---|
| Predecessor | - | - | B | B | B | E | A,D,C |
| Time (in days) | 18 | 8 | 14 | 14 | 16 | 10 | 20 |
[5]
2081 ยท 5 marks
Critical Path Analysis
The following activities must be completed to complete the project. Determine the critical path and time duration of the project.
| Activity | Predecessor | Time (in a week) |
|---|---|---|
| A | - | 3 |
| B | - | 8 |
| C | A,B | 4 |
| D | B | 2 |
| E | A | 1 |
| F | C | 7 |
| G | E,F | 5 |
| H | D,F | 6 |
| I | G,H | 8 |
| J | I | 9 |
[5]
Show solved answerHide answer
Critical Path Analysis
Given
| Activity | Predecessor | Duration (weeks) |
|---|---|---|
| A | - | 3 |
| B | - | 8 |
| C | A, B | 4 |
| D | B | 2 |
| E | A | 1 |
| F | C | 7 |
| G | E, F | 5 |
| H | D, F | 6 |
| I | G, H | 8 |
| J | I | 9 |
Step 2: Forward Pass (Earliest Times)
$ES$ = max of predecessors' $EF$; $EF = ES + \text{duration}$.
| Activity | Dur | ES | EF |
|---|---|---|---|
| A | 3 | 0 | 3 |
| B | 8 | 0 | 8 |
| C | 4 | max(3,8)=8 | 12 |
| D | 2 | 8 | 10 |
| E | 1 | 3 | 4 |
| F | 7 | 12 | 19 |
| G | 5 | max(4,19)=19 | 24 |
| H | 6 | max(10,19)=19 | 25 |
| I | 8 | max(24,25)=25 | 33 |
| J | 9 | 33 | 42 |
Project completion time = 42 weeks
Step 3: Backward Pass (Latest Times)
Project finish $LF = 42$. $LF$ = min of successors' $LS$; $LS = LF - \text{duration}$; Slack $= LS - ES$.
Successor mapping:
- J โ none; I โ J; G, H โ I; F โ G, H; E โ G; D โ H; C โ F; A โ C, E; B โ C, D
| Activity | Dur | LF | LS | Slack |
|---|---|---|---|---|
| J | 9 | 42 | 33 | 0 |
| I | 8 | 33 | 25 | 0 |
| H | 6 | 25 | 19 | 0 |
| G | 5 | 25 | 20 | 1 |
| F | 7 | min(20,19)=19 | 12 | 0 |
| E | 1 | 20 | 19 | 15 |
| D | 2 | 19 | 17 | 7 |
| C | 4 | 12 | 8 | 0 |
| A | 3 | min(8,19)=8 | 5 | 2 |
| B | 8 | min(8,17)=8 | 0 | 0 |
Step 4: Identify Critical Path
Activities with Slack = 0: B, C, F, H, I, J.
$$\textbf{Critical Path: } B \to C \to F \to H \to I \to J$$
Duration check: $$8 + 4 + 7 + 6 + 8 + 9 = 42 \text{ weeks}$$
Final Answer
- Critical Path: $B \to C \to F \to H \to I \to J$
- Project Duration: $42$ weeks
2080 ยท 5 marks
Network Diagram and Critical Path Analysis
Show solved answerHide answer
Network Diagram and Critical Path Analysis
Given
| Activity | A | B | C | D | E | F | G |
|---|---|---|---|---|---|---|---|
| Predecessors | - | A | A | A | B,C | C,D | E,F |
| Time (days) | 7 | 4 | 5 | 6 | 7 | 5 | 6 |
Solution
Network Diagram
B(4)
โโโโโโโโโโบ โข
โ \
โ โโA(7)โโโบโกโโC(5)โโโบโฃโโโE(7)โโโบโคโโG(6)โโโบโฅ
โ \ /
โ \/
โโD(6)โโโบ(F merges C,D)โโF(5)โโโบโค
Logical structure of dependencies:
- A starts the project.
- B, C, D all follow A.
- E follows B and C.
- F follows C and D.
- G follows E and F (final activity).
Forward Pass (Earliest Times)
$$ES = \max(EF \text{ of all predecessors}), \quad EF = ES + t$$
- A: ES = 0, EF = 0 + 7 = 7
- B: ES = 7, EF = 7 + 4 = 11
- C: ES = 7, EF = 7 + 5 = 12
- D: ES = 7, EF = 7 + 6 = 13
- E: ES = max(EF$_B$, EF$_C$) = max(11, 12) = 12, EF = 12 + 7 = 19
- F: ES = max(EF$_C$, EF$_D$) = max(12, 13) = 13, EF = 13 + 5 = 18
- G: ES = max(EF$_E$, EF$_F$) = max(19, 18) = 19, EF = 19 + 6 = 25
Project Duration = 25 days
Backward Pass (Latest Times)
$$LF = \min(LS \text{ of all successors}), \quad LS = LF - t$$
- G: LF = 25, LS = 25 - 6 = 19
- F: LF = 19, LS = 19 - 5 = 14
- E: LF = 19, LS = 19 - 7 = 12
- D: LF = LS$_F$ = 14, LS = 14 - 6 = 8
- C: LF = min(LS$_E$, LS$_F$) = min(12, 14) = 12, LS = 12 - 5 = 7
- B: LF = LS$_E$ = 12, LS = 12 - 4 = 8
- A: LF = min(LS$_B$, LS$_C$, LS$_D$) = min(8, 7, 8) = 7, LS = 7 - 7 = 0
Slack Table
| Activity | ES | EF | LS | LF | Slack (LS-ES) | Critical? |
|---|---|---|---|---|---|---|
| A | 0 | 7 | 0 | 7 | 0 | โ |
| B | 7 | 11 | 8 | 12 | 1 | โ |
| C | 7 | 12 | 7 | 12 | 0 | โ |
| D | 7 | 13 | 8 | 14 | 1 | โ |
| E | 12 | 19 | 12 | 19 | 0 | โ |
| F | 13 | 18 | 14 | 19 | 1 | โ |
| G | 19 | 25 | 19 | 25 | 0 | โ |
Critical Path
Activities with zero slack: A โ C โ E โ G
$$\text{Duration} = 7 + 5 + 7 + 6 = 25 \text{ days}$$
Bottleneck Activities
Bottleneck (critical) activities with zero slack that control the project completion:
$$\boxed{A,\ C,\ E,\ G}$$
Any delay in these directly delays the whole project.
Keep the node table consistent with the forward pass: values such as E at ES = 11, EF = 18, or G at ES = 13, EF = 19, contradict the forward pass computed above. The critical path A -> C -> E -> G and the 25-day duration are unaffected, but an internally inconsistent table loses marks.
2079 ยท 10 marks
Network Diagram and Critical Path Analysis
Show solved answerHide answer
Network Analysis - Critical Path Method
Given
| Activity | Predecessor | Duration (weeks) |
|---|---|---|
| A | - | 5 |
| B | - | 12 |
| C | A | 6 |
| D | B | 3 |
| E | A, D | 2 |
| F | B | 6 |
| G | C, E, F | 14 |
| H | G | 22 |
Step 2: Forward Pass (ES, EF)
Using $EF = ES + t$ and $ES = \max(EF \text{ of predecessors})$:
| Activity | Dur | Predecessor | ES | EF |
|---|---|---|---|---|
| A | 5 | - | 0 | 5 |
| B | 12 | - | 0 | 12 |
| C | 6 | A | 5 | 11 |
| D | 3 | B | 12 | 15 |
| E | 2 | A, D | max(5,15)=15 | 17 |
| F | 6 | B | 12 | 18 |
| G | 14 | C,E,F | max(11,17,18)=18 | 32 |
| H | 22 | G | 32 | 54 |
Project completion time = 54 weeks
Step 3: Backward Pass (LF, LS)
Using $LS = LF - t$ and $LF = \min(LS \text{ of successors})$. Project LF = 54.
Successor mapping:
- H โ end; G โ H; C, E, F โ G; D โ E; A โ C, E; B โ D, F
| Activity | Dur | Successors | LF | LS |
|---|---|---|---|---|
| H | 22 | - | 54 | 32 |
| G | 14 | H | 32 | 18 |
| F | 6 | G | 18 | 12 |
| E | 2 | G | 18 | 16 |
| C | 6 | G | 18 | 12 |
| D | 3 | E | 16 | 13 |
| B | 12 | D, F | min(13,12)=12 | 0 |
| A | 5 | C, E | min(12,16)=12 | 7 |
Step 4: Slack and Critical Activities
$\text{Slack} = LS - ES$
| Activity | ES | LS | Slack | Critical? |
|---|---|---|---|---|
| A | 0 | 7 | 7 | No |
| B | 0 | 0 | 0 | Yes |
| C | 5 | 12 | 7 | No |
| D | 12 | 13 | 1 | No |
| E | 15 | 16 | 1 | No |
| F | 12 | 12 | 0 | Yes |
| G | 18 | 18 | 0 | Yes |
| H | 32 | 32 | 0 | Yes |
Step 5: Critical Path
Critical activities (zero slack): B, F, G, H
$$\text{Critical Path: } B \rightarrow F \rightarrow G \rightarrow H$$
Verification of length: $$12 + 6 + 14 + 22 = 54 \text{ weeks}$$
Network Diagram
A(5) โโ C(6) โโ
/ โ
Start โ
\ โโโ G(14) โโ H(22) โโ End
B(12) โ D(3) โ E(2) โ
\ โ
F(6) โโโโโโโโโโ
Answer Summary
| Item | Result |
|---|---|
| Minimum Project Duration | 54 weeks |
| Critical Activities | B, F, G, H |
| Critical Path | B โ F โ G โ H |
Check the slack before calling an activity critical: activity A has slack = 7 (LS = 7, ES = 0), so A is not critical. With a project duration of 54 weeks and critical path B -> F -> G -> H, the critical activities are only B, F, G, H.
2080.2 ยท 5 marks
Critical Path Analysis
The following activities must be completed in the order to complete the project. Determine critical path and time duration of the project.
| Activity | A | B | C | D | E | F | G | H | I | J |
|---|---|---|---|---|---|---|---|---|---|---|
| Predecessor | - | - | A,B | B | A | C | E,F | D,F | G,H | I |
| Time (in week) | 3 | 8 | 4 | 2 | 1 | 7 | 5 | 6 | 8 | 9 |
[5]
Show solved answerHide answer
Critical Path Analysis - Verified Solution
Given Data
| Activity | Predecessor(s) | Duration (weeks) |
|---|---|---|
| A | - | 3 |
| B | - | 8 |
| C | A, B | 4 |
| D | B | 2 |
| E | A | 1 |
| F | C | 7 |
| G | E, F | 5 |
| H | D, F | 6 |
| I | G, H | 8 |
| J | I | 9 |
Step 1: Forward Pass (ES, EF)
$EF = ES + \text{Duration}$, and $ES = \max(EF \text{ of predecessors})$.
| Activity | Predecessors | ES | EF |
|---|---|---|---|
| A | - | 0 | 3 |
| B | - | 0 | 8 |
| C | A(3), B(8) | 8 | 12 |
| D | B(8) | 8 | 10 |
| E | A(3) | 3 | 4 |
| F | C(12) | 12 | 19 |
| G | E(4), F(19) | 19 | 24 |
| H | D(10), F(19) | 19 | 25 |
| I | G(24), H(25) | 25 | 33 |
| J | I(33) | 33 | 42 |
Project duration = 42 weeks.
Step 2: Backward Pass (LF, LS)
$LS = LF - \text{Duration}$, and $LF = \min(LS \text{ of successors})$.
Successors:
- J โ (end)
- I โ J
- H โ I
- G โ I
- F โ G, H
- E โ G
- D โ H
- C โ F
- B โ C, D
- A โ C, E
| Activity | LF | LS |
|---|---|---|
| J | 42 | 33 |
| I | 33 | 25 |
| H | 25 | 19 |
| G | 25 | 20 |
| F | min(20,19)=19 | 12 |
| E | 20 | 19 |
| D | 19 | 17 |
| C | 12 | 8 |
| B | min(8,17)=8 | 0 |
| A | min(8,19)=8 | 5 |
Step 3: Slack (LS โ ES)
| Activity | ES | LS | Slack | Critical? |
|---|---|---|---|---|
| A | 0 | 5 | 5 | No |
| B | 0 | 0 | 0 | Yes |
| C | 8 | 8 | 0 | Yes |
| D | 8 | 17 | 9 | No |
| E | 3 | 19 | 16 | No |
| F | 12 | 12 | 0 | Yes |
| G | 19 | 20 | 1 | No |
| H | 19 | 19 | 0 | Yes |
| I | 25 | 25 | 0 | Yes |
| J | 33 | 33 | 0 | Yes |
Step 4: Critical Path
Zero-slack activities: B โ C โ F โ H โ I โ J
Check: $8 + 4 + 7 + 6 + 8 + 9 = 42$ weeks.
Result
- Critical Path: $B \rightarrow C \rightarrow F \rightarrow H \rightarrow I \rightarrow J$
- Project Duration: $42$ weeks
0 ยท 10 marks
Critical Path Analysis
The following activities must be completed in order to complete the project. Determine the critical path and time duration of the project based on slack time of the activity.
| Activity | A | B | C | D | E | F | G | H | I | J |
|---|---|---|---|---|---|---|---|---|---|---|
| Predecessor | - | - | A, B | B | A | C | E, F | D, F | G, H | I |
| Time (in days) | 3 | 8 | 4 | 2 | 1 | 7 | 5 | 6 | 8 | 9 |
[10]
PERT network diagrams
2081 ยท 5 marks
Project Completion Time and Variance Analysis
A project consists of nine activities whose time estimates (in weeks) and other characteristics are given below. What is the expected project completion time and its variance?
| Activities | A | B | C | D | E | F | G | H | I |
|---|---|---|---|---|---|---|---|---|---|
| Preceding activities | - | - | - | A | A | B,D | B,D | C,F | E |
| Optimistic time | 2 | 6 | 6 | 2 | 11 | 8 | 3 | 9 | 4 |
| Most likely time | 4 | 6 | 12 | 5 | 14 | 10 | 6 | 15 | 10 |
| Pessimistic time | 6 | 6 | 24 | 8 | 23 | 12 | 9 | 27 | 16 |
[5]
2080 ยท 10 marks
PERT Network Analysis Problem
A project consists of nine activities whose time estimates (in weeks) and other characteristics are given below:
| Activities | A | B | C | D | E | F | G | H | I |
|---|---|---|---|---|---|---|---|---|---|
| Preceding activities | - | - | - | A | A | B, D | B, D | C, F | E |
| Optimistic time | 2 | 6 | 6 | 2 | 11 | 8 | 3 | 9 | 4 |
| Most likely time | 4 | 6 | 12 | 5 | 14 | 10 | 6 | 15 | 10 |
| Pessimistic time | 6 | 6 | 24 | 8 | 23 | 12 | 9 | 27 | 16 |
(a) Show the PERT network diagram for the project.
(b) Identify the critical activities.
(c) What is the expected project completing time and its variance?
[10]
Network diagram construction
2079 ยท 5 marks
Network Diagram Project
The following activities must be completed in order to complete the project. Draw network diagram to reflect the inter relationship between activities of the project.
| Activity | P | Q | R | S | T | U | V | W | X |
|---|---|---|---|---|---|---|---|---|---|
| Predecessor | - | - | P, Q | Q | P | R | T, U | S, U | V, W |
[5]
0 ยท 5 marks
A work project consists of twelve activities labeled through L. Upon being asked to specify the order in which the jobs had to be done, the manager answered as follows: A, B, and C are the first activities of the project and can start simultaneously and immediately; A and B precede D while B precede E, F and H. Activities F and C precede G while E and H precede I and J. The activities C, D, F and J precede K which, in turn, precedes L. Further I, G and L are the terminal activities of the project. Draw a network diagram corresponding to the project. [5]