Software Project Management20785 marksObjectives of activity planning

Differentiate between activity-based approach and hybrid-based approach for identifying activities.

Differentiate between activity-based approach and hybrid-based approach for identifying activities. [5]

The activity-based approach uses the Work Breakdown Structure (WBS) to generate a complete task list for the project. It focuses on identifying and decomposing activities/tasks in a top-down hierarchical manner. 1. Identify the main tasks of the project at the highest level. 2. Break each main ta...