CSC425 · 2080 · 5 marks

Draw precedence network diagram for the following and identify the critical path. | Activity | Duration (weeks) | Precedence | |----------|------------------|------------| | A | 2 | | | B | 2 | | | C | 4 | A | | D | 2 | B | | E | 4 | B, D |

Draw precedence network diagram for the following and identify the critical path.

ActivityDuration (weeks)Precedence
A2
B2
C4A
D2B
E4B, D

[5]

Software Project ManagementChapter 3: Activity Planning and SchedulingNetwork planning modelNumerical: Precedence network critical path

Precedence Network Diagram and Critical Path

Given

ActivityDuration (weeks)Precedence
A2none
B2none
C4A
D2B
E4B, D

A and B are start activities.


Solution

Activity-on-Node Network Diagram

          +--> [A: 2] --> [C: 4] --+
          |                        |
 [Start] -+                        +--> [Finish]
          |                        |
          +--> [B: 2] --+--> [D: 2] --+--> [E: 4] --+
                        |                            |
                        +----------------------------+
                        (B is also predecessor of E)

Possible Paths

PathActivitiesDuration
1A -> C$2 + 4 = 6$
2B -> D -> E$2 + 2 + 4 = 8$
3B -> E$2 + 4 = 6$

Forward Pass (ES, EF)

$$EF = ES + \text{Duration}$$

ActivityESEF
A02
B02
C26
D24
E$\max(EF_B, EF_D) = \max(2,4) = 4$8

Project duration = 8 weeks

Backward Pass (LS, LF)

$$LS = LF - \text{Duration}$$

ActivityLFLS
E84
D42
C84
B$\min(LS_D, LS_E) = \min(2,4) = 2$0
A42

Float = LS - ES

ActivityESEFLSLFFloat
A02242
B02020
C26482
D24240
E48480

Critical Path

Activities with zero float: B, D, E

$$\boxed{\text{Critical Path: } B \to D \to E \quad \text{Duration} = 8 \text{ weeks}}$$

Activities A and C are non-critical (float = 2 weeks each).