Software Project Management20805 marksNumerical: Precedence network critical pathNetwork planning model

Draw precedence network diagram for the following and identify the critical path. | Activity | Duration (weeks) | Precedence | |----------|------------------|------------| | A | 2 | | | B | 2 | | | C | 4 | A | | D | 2 | B | | E | 4 | B, D |

Draw precedence network diagram for the following and identify the critical path.

ActivityDuration (weeks)Precedence
A2
B2
C4A
D2B
E4B, D

[5]

Activity Duration (weeks) Precedence --------------------------------------- A 2 none B 2 none C 4 A D 2 B E 4 B, D All data is present. A and B are start activities. --- Path Activities Duration --------------------------- 1 A - C $2 + 4 = 6$ 2 B - D - E $2 + 2 + 4 = 8$ 3 B - E $2 + 4 = 6$ $$EF ...