CSC425 · 2080 · 5 marks
Draw precedence network diagram for the following and identify the critical path. | Activity | Duration (weeks) | Precedence | |----------|------------------|------------| | A | 2 | | | B | 2 | | | C | 4 | A | | D | 2 | B | | E | 4 | B, D |
Draw precedence network diagram for the following and identify the critical path.
| Activity | Duration (weeks) | Precedence |
|---|---|---|
| A | 2 | |
| B | 2 | |
| C | 4 | A |
| D | 2 | B |
| E | 4 | B, D |
[5]
Software Project ManagementChapter 3: Activity Planning and SchedulingNetwork planning modelNumerical: Precedence network critical path
Precedence Network Diagram and Critical Path
Given
| Activity | Duration (weeks) | Precedence |
|---|---|---|
| A | 2 | none |
| B | 2 | none |
| C | 4 | A |
| D | 2 | B |
| E | 4 | B, D |
A and B are start activities.
Solution
Activity-on-Node Network Diagram
+--> [A: 2] --> [C: 4] --+
| |
[Start] -+ +--> [Finish]
| |
+--> [B: 2] --+--> [D: 2] --+--> [E: 4] --+
| |
+----------------------------+
(B is also predecessor of E)
Possible Paths
| Path | Activities | Duration |
|---|---|---|
| 1 | A -> C | $2 + 4 = 6$ |
| 2 | B -> D -> E | $2 + 2 + 4 = 8$ |
| 3 | B -> E | $2 + 4 = 6$ |
Forward Pass (ES, EF)
$$EF = ES + \text{Duration}$$
| Activity | ES | EF |
|---|---|---|
| A | 0 | 2 |
| B | 0 | 2 |
| C | 2 | 6 |
| D | 2 | 4 |
| E | $\max(EF_B, EF_D) = \max(2,4) = 4$ | 8 |
Project duration = 8 weeks
Backward Pass (LS, LF)
$$LS = LF - \text{Duration}$$
| Activity | LF | LS |
|---|---|---|
| E | 8 | 4 |
| D | 4 | 2 |
| C | 8 | 4 |
| B | $\min(LS_D, LS_E) = \min(2,4) = 2$ | 0 |
| A | 4 | 2 |
Float = LS - ES
| Activity | ES | EF | LS | LF | Float |
|---|---|---|---|---|---|
| A | 0 | 2 | 2 | 4 | 2 |
| B | 0 | 2 | 0 | 2 | 0 |
| C | 2 | 6 | 4 | 8 | 2 |
| D | 2 | 4 | 2 | 4 | 0 |
| E | 4 | 8 | 4 | 8 | 0 |
Critical Path
Activities with zero float: B, D, E
$$\boxed{\text{Critical Path: } B \to D \to E \quad \text{Duration} = 8 \text{ weeks}}$$
Activities A and C are non-critical (float = 2 weeks each).
Short on time? The 1, 5 and 10 mark versions of this answer, flashcards and practice sets come with a program pass.