CSC425 · 2079 · 5 marks
Draw CPM network diagram for the following and identify the critical path. | Activity | Duration (weeks) | Precedence | |----------|------------------|------------| | A | 4 | | | B | 4 | A | | C | 2 | A | | D | 6 | B, C |
Draw CPM network diagram for the following and identify the critical path.
| Activity | Duration (weeks) | Precedence |
|---|---|---|
| A | 4 | |
| B | 4 | A |
| C | 2 | A |
| D | 6 | B, C |
[5]
CPM Network Diagram and Critical Path
Given
| Activity | Duration (weeks) | Precedence |
|---|---|---|
| A | 4 | - |
| B | 4 | A |
| C | 2 | A |
| D | 6 | B, C |
Step 2 - Network Diagram (Activity-on-Arrow)
Since CPM traditionally uses Activity-on-Arrow (AOA), I number events 1 to 5.
B(4)
(2) ---------->
/ \
A(4) \ D(6)
/ >(4) ----> (5)
(1) /
\ /
(2) ---C(2)---> (3) --dummy--> (4)?
Cleaner AOA representation: A splits into B and C, both merge before D.
+---B(4)---+
| v
(1)--A(4)-->(2) (4)--D(6)-->(5)
| ^
+---C(2)---+
- Event 1: Start
- A (1 to 2), duration 4
- B (2 to 4), duration 4
- C (2 to 4), duration 2
- D (4 to 5), duration 6
Step 3 - Forward Pass (ES, EF)
$$EF = ES + \text{Duration}$$
| Activity | ES | Duration | EF |
|---|---|---|---|
| A | 0 | 4 | 4 |
| B | 4 | 4 | 8 |
| C | 4 | 2 | 6 |
| D | $\max(8,6)=8$ | 6 | 14 |
Project Duration = 14 weeks
Step 4 - Backward Pass (LF, LS)
$$LS = LF - \text{Duration}$$
| Activity | LF | Duration | LS |
|---|---|---|---|
| D | 14 | 6 | 8 |
| B | 8 | 4 | 4 |
| C | 8 | 2 | 6 |
| A | $\min(4,6)=4$ | 4 | 0 |
Step 5 - Total Float
$$\text{Float} = LS - ES = LF - EF$$
| Activity | ES | EF | LS | LF | Float | Critical? |
|---|---|---|---|---|---|---|
| A | 0 | 4 | 0 | 4 | 0 | Yes |
| B | 4 | 8 | 4 | 8 | 0 | Yes |
| C | 4 | 6 | 6 | 8 | 2 | No |
| D | 8 | 14 | 8 | 14 | 0 | Yes |
Step 6 - Critical Path
$$\boxed{A \rightarrow B \rightarrow D}$$
Duration $= 4 + 4 + 6 = 14$ weeks.
Activity C has float of 2 weeks (non-critical).