CSC425 · 2079 · 5 marks

Draw CPM network diagram for the following and identify the critical path. | Activity | Duration (weeks) | Precedence | |----------|------------------|------------| | A | 4 | | | B | 4 | A | | C | 2 | A | | D | 6 | B, C |

Draw CPM network diagram for the following and identify the critical path.

ActivityDuration (weeks)Precedence
A4
B4A
C2A
D6B, C

[5]

Software Project ManagementChapter 3: Activity Planning and SchedulingNetwork planning modelNumerical: CPM network critical path

CPM Network Diagram and Critical Path

Given

ActivityDuration (weeks)Precedence
A4-
B4A
C2A
D6B, C

Step 2 - Network Diagram (Activity-on-Arrow)

Since CPM traditionally uses Activity-on-Arrow (AOA), I number events 1 to 5.

                B(4)
        (2) ---------->
       /                \
   A(4)                  \  D(6)
   /                      >(4) ----> (5)
 (1)                     /
       \                /
        (2) ---C(2)---> (3) --dummy--> (4)?

Cleaner AOA representation: A splits into B and C, both merge before D.

        +---B(4)---+
        |          v
(1)--A(4)-->(2)   (4)--D(6)-->(5)
        |          ^
        +---C(2)---+
  • Event 1: Start
  • A (1 to 2), duration 4
  • B (2 to 4), duration 4
  • C (2 to 4), duration 2
  • D (4 to 5), duration 6

Step 3 - Forward Pass (ES, EF)

$$EF = ES + \text{Duration}$$

ActivityESDurationEF
A044
B448
C426
D$\max(8,6)=8$614

Project Duration = 14 weeks

Step 4 - Backward Pass (LF, LS)

$$LS = LF - \text{Duration}$$

ActivityLFDurationLS
D1468
B844
C826
A$\min(4,6)=4$40

Step 5 - Total Float

$$\text{Float} = LS - ES = LF - EF$$

ActivityESEFLSLFFloatCritical?
A04040Yes
B48480Yes
C46682No
D8148140Yes

Step 6 - Critical Path

$$\boxed{A \rightarrow B \rightarrow D}$$

Duration $= 4 + 4 + 6 = 14$ weeks.

Activity C has float of 2 weeks (non-critical).