Software Project Management20795 marksNumerical: CPM network critical pathNetwork planning model

Draw CPM network diagram for the following and identify the critical path. | Activity | Duration (weeks) | Precedence | |----------|------------------|------------| | A | 4 | | | B | 4 | A | | C | 2 | A | | D | 6 | B, C |

Draw CPM network diagram for the following and identify the critical path.

ActivityDuration (weeks)Precedence
A4
B4A
C2A
D6B, C

[5]

Activity Duration (weeks) Precedence ---------------------------------------- A 4 - B 4 A C 2 A D 6 B, C Since CPM traditionally uses Activity-on-Arrow (AOA), I number events 1 to 5. Cleaner AOA representation: A splits into B and C, both merge before D. - Event 1: Start - A (1 to 2), duration 4 ...