CSC425 · 2081 · 10 marks

Precedence Network Diagram and Critical Path Analysis

Precedence Network Diagram and Critical Path Analysis

Software Project ManagementChapter 3: Activity Planning and SchedulingNetwork planning modelNumerical: Precedence network critical path

Activity Duration (Weeks) Predecessors ------------------------------------------ A 1 - B 2 A C 5 A D 2 - E 4 C, D F 3 - G 4 B, E, F - A, D, F have no predecessors (start activities). - E depends on C and D. - G depends on B, E, F (final activity).