CSC425 · 2078 · 5 marks

Draw precedence network diagram for the following and identify the critical path. | Activity | Duration (Weeks) | Precedence | |----------|------------------|-----------| | A | 5 | | | B | 3 | A | | C | 5 | A | | D | 10 | B, C |

Draw precedence network diagram for the following and identify the critical path.

ActivityDuration (Weeks)Precedence
A5
B3A
C5A
D10B, C

[5]

Software Project ManagementChapter 3: Activity Planning and SchedulingNetwork planning modelNumerical: CPM network critical path

Precedence Network Diagram and Critical Path

Given

ActivityDuration (Weeks)Precedence
A5None (start)
B3A
C5A
D10B, C

Solution

Precedence Network (Activity-on-Node)

                 +--------+
             +-->|  B: 3  |---+
             |   +--------+   |
+--------+   |                v   +--------+
|  A: 5  |---+                +-->|  D: 10 |---> Finish
+--------+   |                ^   +--------+
             |   +--------+   |
             +-->|  C: 5  |---+
                 +--------+
  • A has no predecessor (starts the project).
  • B and C both follow A.
  • D follows both B and C (both must complete before D starts).

Forward Pass (Earliest Start / Earliest Finish)

$EF = ES + \text{Duration}$

ActivityESDurationEF
A055
B538
C5510
D$\max(8,10)=10$1020

Project Duration = 20 weeks

Backward Pass (Latest Finish / Latest Start)

$LS = LF - \text{Duration}$

ActivityLFDurationLS
D201010
C1055
B1037
A$\min(7,5)=5$50

Total Float ($TF = LS - ES$)

ActivityESLSTotal FloatCritical?
A000Yes
B572No
C550Yes
D10100Yes

Critical Path

Path enumeration:

  • $A \to B \to D = 5 + 3 + 10 = 18$ weeks
  • $A \to C \to D = 5 + 5 + 10 = 20$ weeks (longest)

$$\boxed{A \rightarrow C \rightarrow D, \quad \text{Duration} = 20 \text{ weeks}}$$