Earned Value Analysis

Earned Value Analysis

Software Project ManagementChapter 6: Monitoring and ControlEarned value analysisNumerical: Earned value analysis

Activities: Activity Duration (days) Precedence Cost/day (Rs.) BAC = Dur ร— Cost/day ----------------------------------------------------------------------------- A 8 - 200 1600 B 4 - 200 800 C 4 A, B 300 1200 D 4 B 400 1600 Total Budget (BAC) = 1600 + 800 + 1200 + 1600 = Rs. 5200 Progress at end ...