Software Project Management2079Numerical: Earned value analysisEarned value analysis

Earned Value Analysis

Earned Value Analysis

Activities: Activity Duration (days) Precedence Cost/day (Rs) Total Cost (Rs) ----------------------------------------------------------------------- A 5 - 200 1000 B 5 A 200 1000 C 10 A 100 1000 D 5 A, B 200 1000 Total planned budget (BAC) = $1000 \times 4 = 4000$ Progress at end of Day 10: Acti...