Software Project Management20785 marksVisualizing progress

Differentiate between Gantt chart and slip chart.

Differentiate between Gantt chart and slip chart. [5]

A Gantt chart is one of the oldest and simplest techniques for tracking project progress. It is an activity bar chart that indicates scheduled activity dates. It plots activities against a timeline using horizontal bars, where each bar represents the duration of a task from its start date to its ...