2080 1

Software Project Management2080Numerical: Earned Value AnalysisEarned value analysis

Earned Value Analysis

Earned Value Analysis

Activity Duration (days) Precedence Cost/day (Rs.) BAC (Rs.) ------------------------------------------------------------------ A 6 - 100 600 B 6 A 100 600 C 8 B 200 1600 D 4 B 300 1200 Total BAC = 600 + 600 + 1600 + 1200 = Rs. 4000 Progress at end of Day 16: Activity % Completion Incurred Cost (...

Up nextElaborate on the issues and questions to be considered during strategic assessment. List t