2080 12

CSC425 ยท 2080 ยท 5 marks

Write short notes on: a. Future worth b. Bubble chart

Write short notes on: a. Future worth b. Bubble chart [5]

Software Project ManagementChapter 2: Project AnalysisEconomic analysis

Quick answer

Future Worth (FW) refers to the value of an investment at a specific point in the future, taking into account factors such as interest rates and price rise. It is a financial concept used to determine how much a present sum of money will be worth at a future date.

Short Notes

a. Future Worth (2.5 marks)

Key Points:

  • Future worth is used in financial analysis and decision-making to compare different investment options and to evaluate the potential return on investment.
  • It helps in assessing whether an investment today will yield sufficient returns in the future.

Two Types of Future Value Calculations:

1. Future Value of a Lump Sum:

  • It is the value of a single deposit (e.g., a bank fixed deposit) accumulated over time.
  • Formula:

$$FV = PV \times (1 + i)^n$$

Where:

  • FV = Future Value
  • PV = Present Value (initial investment)
  • i = interest rate per period
  • n = number of periods

2. Future Value of a Series (Annuity):

  • It is the accumulated value of a series of equal periodic payments over time.

Significance:

  • Future worth analysis allows project managers and financial analysts to evaluate whether the future benefits of a project justify the present investment.
  • It is the reverse concept of Present Worth (PW/NPV), which discounts future cash flows to the present.

b. Bubble Chart (2.5 marks)

A Bubble Chart is a type of data visualization tool used in project management and business analysis to display and compare multiple variables simultaneously in a two-dimensional space.

Key Features:

  • It is an extension of a scatter plot, where each data point is represented as a bubble (circle).
  • Three variables can be represented:
    • X-axis -- one variable (e.g., cost)
    • Y-axis -- another variable (e.g., benefit or return)
    • Size of the bubble -- a third variable (e.g., risk level or project size)

Uses in Project Management:

PurposeDescription
Portfolio AnalysisCompare multiple projects based on cost, benefit, and risk
Risk VisualizationLarger bubbles indicate higher risk projects
Resource AllocationHelps prioritize projects with best return
Decision MakingVisually identify the most viable investment options

Advantages:

  • Allows visualization of three dimensions of data in a single chart.
  • Easy to identify patterns, outliers, and relationships between variables.
  • Useful for comparing project options during feasibility and planning stages.

Example:

In software project management, a bubble chart can plot projects with:

  • X-axis: Development Cost
  • Y-axis: Expected Revenue
  • Bubble Size: Project Complexity or Risk

This helps managers quickly identify high-value, low-risk projects for prioritization.